Finn Hill Neighborhood Plan Update Street Connection Draft Plan - - PowerPoint PPT Presentation

finn hill neighborhood
SMART_READER_LITE
LIVE PREVIEW

Finn Hill Neighborhood Plan Update Street Connection Draft Plan - - PowerPoint PPT Presentation

Finn Hill Neighborhood Plan Update Street Connection Draft Plan Planning Commission Meeting September 14, 2017 Background In 1998, the City Council began discussing street connection policies. Street connections were being required with


slide-1
SLIDE 1

Finn Hill Neighborhood Plan Update

Street Connection Draft Plan Planning Commission Meeting September 14, 2017

slide-2
SLIDE 2

Background

  • In 1998, the City Council began discussing street connection policies.
  • Street connections were being required with new development, but the City Council asked

that street connections be identified in neighborhood plans.

  • The purpose of the map was to provide notice about planned street connections to staff,

neighbors, property owners, and developers.

  • In approximately 2001, the Council adopted the first street connection map in the

North Rose Hill Neighborhood Plan.

  • The map was drafted after meetings with neighborhood representatives, and then presented

for review by the Transportation Commission, Planning Commission, and City Council.

slide-3
SLIDE 3

Comprehensive Plan Language related to Street Connections

  • Policy T-5.6: Create a system of streets and trails that form an interconnected network.
  • As a part of land development, new connections to the existing street system are often required. These

could be full streets or connections for emergency vehicles, bicycles, and pedestrians.

  • Traffic that is spread over a grid of streets balances and minimizes traffic impacts across the network.

Therefore, the fact that new connections may increase traffic volume on some existing streets is not a sufficient reason for rejecting such new connections.

  • Emergency response times are shorter and more reliable when responders have several routing options,

and new connections often provide these additional options.

  • Time saving and safe bicycle and pedestrian connections can be made by adding trail connections

between cul-de-sacs.

slide-4
SLIDE 4

The map is a draft

  • The map is a tool used to identify where street connections could be made.
  • The connections have been studied at a high level without detailed survey
  • information. Some connections may not be feasible after more study is completed.
  • The City is not prepared to construct any of the connections.
  • Most of the connections would be required only if new development is proposed.
  • If the connection is required with a subdivision, an appeal can be filed, and the City

Council is the final decision maker.

slide-5
SLIDE 5

Finn Hill Street Connections – How and Why?

  • Staff studied the developable land map to determine where redevelopment

could occur.

  • Studied the existing street network to determine if new connections should be

considered when redevelopment is proposed.

  • Studied past development patterns and layouts determined by King County to better

understand where street connections could/should be considered.

  • Studied topographic, environmental, and other constraints that would prohibit a

connection.

  • Studied existing unopened rights-of-way that could be improved as a connection.
slide-6
SLIDE 6

Connection #1 NE 143rd St. btwn. 84th

  • Ave. NE and Existing

Barricade

Existing street provides access to 10 homes. Street is encompassed in a private access

  • easement. Would require all property
  • wners to dedicate the easement to the City

in order to make the street public, and remove the barricade. (Google link)

slide-7
SLIDE 7

Connection #2 – NE 142nd Street btwn. 84th Ave. NE and Existing Barricade

Existing ROW and limited redevelopment. Existing street provides access to four residential homes. Paving and surface water mitigation required before the street can be

  • pened. Traffic calming techniques and

methods would need to be studied as well. (Google Link)

slide-8
SLIDE 8

Connection #3 NE 141st St

  • btwn. 100th Ave NE and

existing street stub at 97th Ave NE

Property zoned RSA 8. Highly likely to

  • redevelop. Would provide additional access

to the residential property to the east. (Google Link)

slide-9
SLIDE 9

Connection #3A 99th Ave NE/NE 142nd St btwn. NE 141st St (new) and 100th Ave NE (a looped connection)

Property zoned RSA 8. Highly likely to

  • redevelop. Tract F is a drainage tract owned

by City that could potentially have street improvements in it (more research is needed). This connection would provide an interior looped road connection within this property when it is redeveloped. (Google Link)

slide-10
SLIDE 10

Connection #4 NE 140th Pl

  • btwn. 75th Ave NE and 80th

Ave NE

Existing private street connection that serves approximately 25+ homes. City may consider taking it over as a public street if the owners are willing to dedicate it and bring it up to public maintenance standards (overlay). Includes a storm system (primarily ditch and driveway culverts) that are not being maintained by City at this time. (Google Link)

slide-11
SLIDE 11

Connection #5 NE 140th St btwn 75th Ave NE and 80th Ave NE

An existing street connection that serves approximately 14+ homes. The westernmost end of the street is paved approximately 12 ft. wide and the remaining portion of the street is gravel (approx. 12 ft. wide). The street abuts Big Finn Hill Park. City may consider taking it

  • ver as a public street if the owners are willing

to dedicate it and bring it up to public standards by paving it. This would likely trigger significant drainage mitigation, including storm water collection, conveyance, flow control, and water quality. (Google Link)

slide-12
SLIDE 12

Connection #6 NE 135th St & NE 136th St Loop Connection at 72nd Ave NE

5 different lots with development potential. Topography, existing structures, and

  • wnership of the existing private access

streets may make this infeasible. (Google link)

slide-13
SLIDE 13

Connection #7 69th Ave NE to 70th Ave NE Loop Connection at NE 134th St

4 different lots with development potential. Existing structures, and ownership of the existing private access streets may make this infeasible. (Google link)

slide-14
SLIDE 14

Connection #8 NE 132nd St

  • btwn. 74th Pl NE and Juanita

Dr

Would primarily be City-funded because it runs through Big Finn Hill Park. Due to environmental and topographic constraints, more study is needed to determine the feasiblity. (Google Link)

slide-15
SLIDE 15

Connection #9 64th Ave NE

  • btwn. NE 130th Pl to North

end of existing 64th Ave NE

May have topographic or environmental

  • constraints. Further study is needed. May

require the City to purchase and improve some of the connection if it cannot be

  • btained via redevelopment.

(Google Link)

slide-16
SLIDE 16

Connection #10 63rd Ave NE

  • btwn. NE 129th St and South

end of existing pavement in 63rd Ave NE (cul-de-sac)

Short connection (150 ft.) (Google Link)

slide-17
SLIDE 17

Connection #11 64th Ave NE

  • btwn. 68th Ave NE and NE

129th St

Topographic or environmental constraints may make the connection infeasible. If a street connection is not feasible, a pedestrian connection should be required with redevelopment of adjacent property. (Google Link)

slide-18
SLIDE 18

Connection #12 NE 123rd St

  • btwn. Juanita Dr. NE and

80th AVE NE

High development potential that will need public road access. (Google Link)

slide-19
SLIDE 19

Connection #13 79th Ave NE Loop btwn. NE 125th St and 80th Ave NE

South end (250 ft.) of this street was recently constructed with Toll Bros

  • subdivisions. Additional pending subdivision

to the north will build the north end of the street connection. Remaining middle section will be constructed with future redevelopment (Google Link)

slide-20
SLIDE 20

Connection #14 80th Ave NE

  • btwn. NE 126th St and NE

128th St

Two pending subdivisions will be constructing this street connection in 2017/2018 (Google Link)

slide-21
SLIDE 21

Connection #15 NE 126th Pl

  • btwn. 82nd Ave NE and 84th

Ave NE

A 2015 short plat constructed 300 ft. of the street connection from 84th Ave. NE, and in 2017/2018 a pending subdivision will construct the remaining 300 ft. of street connection to 82nd Ave NE. (Google Link)

slide-22
SLIDE 22

Connection #16 80th Ave NE

  • btwn. NE 123rd St and NE

124th St

A viable connection, but intersection sight distance at NE 123rd St may make the street connection infeasible. More study is needed. A good pedestrian/bike connection if street connection is not feasible. (Google Link)

slide-23
SLIDE 23

Connection #17 NE 123rd Pl

  • btwn. 86th Ave NE and existing

east end of NE 123rd Pl

The existing NE 123rd Pl appears to have been required by King Co as part of higher density development. The terminus of the road indicates that King County intended it to be extended east. An extension of NE 123rd Pl will need to be analyzed when the two parcels to the east are redeveloped. (Google Link)

slide-24
SLIDE 24

Connection #18 88th Ave NE or 89th Ave NE btwn. NE 124th St and 89th Pl NE (Goat Hill)

Topographic and environmental constraints may make the connection infeasible. A pedestrian connection should be built if street connection is infeasible. (Google Link)

slide-25
SLIDE 25

Connection #19 NE 121st St

  • btwn. 87th Ave NE and 89th Ave

NE or 89th Pl NE (Goat Hill)

Highly valuable connection to provide alternate access to property on Goat Hill. (Google Link)

slide-26
SLIDE 26

Connection #19A NE 120th St btwn. 86th Ave NE and 87th Ave NE

Continues connection 19 noted above. Redevelopment may be limited, which would in turn limit this connection. (Google Link)

slide-27
SLIDE 27

Connection #20 NE 120th Pl

  • btwn. 84th Ave NE and 86th

Ave NE

Would require a re-platting of the Finn Hill Meadows Subdivision. Redevelopment is unlikely, but street connection should be mapped. (Google Link)

slide-28
SLIDE 28

Connection #21 73rd Pl NE btwn NE 118th St and NE 120th St

Existing 12 ft. wide gravel connection exists

  • today. Topography may make this

connection infeasible, but should be mapped. (Google Link)

slide-29
SLIDE 29

Connection #22 76th Ave NE

  • btwn. NE 116th St and NE

118th St

30 ft. wide existing ROW along west edge of Woodlands Park. Redevelopment could build all or most of the street connection. (Google Link)

slide-30
SLIDE 30

Connection #23 82nd Ave NE btwn. NE 119th St and NE 120th St

Street connection required with redevelopment (Google Link)

slide-31
SLIDE 31

Connection #24 80th Ave NE/NE 117th Street Loop

  • btwn. 80th Ave NE and NE

117th St

300+ feet of the south end of this connection is currently under construction with two short plats. Connection may be deemed undesirable because of cut- through traffic; however, traffic-calming devices could be used to deter this. Also, the narrow and circuitous streets serving this connection (through and east of Chatum Ridge subdivision), together with a challenging intersection at 80th Ave. NE and Juanita Drive, may lead to a decision to improve the connection only for pedestrians and bikes. (Google Link)

slide-32
SLIDE 32

Connection #25 NE 120th St at existing barricade

Existing street connection with barricade. Connection added to this list for discussion. If the barricade was removed, the portion of NE 120th from Juanita Drive to 80th Pl NE would need to be widened. Traffic calming methods would also need to be studied. Fire Dept. has said that this connection would increase response times to the neighborhood; however, infrared-controlled bollards could be installed to allow for emergency access only. (Google Link)

slide-33
SLIDE 33

Connection #26 NE 119th St

  • btwn. 80th Pl NE and 82nd

Ave NE

Street connection required with redevelopment. (Google Link)

slide-34
SLIDE 34

Questions?