portmetrovancouver.com 1 Projects Requiring PMV Review The 3 - PowerPoint PPT Presentation

portmetrovancouver.com 1 Projects Requiring PMV Review The 3 Criteria of a Project: 1. A physical activity consists of carrying out tasks or actions involved with construction, modification, operation, and decommissioning (i.e. involving a


  1. portmetrovancouver.com 1

  2. Projects Requiring PMV Review The 3 Criteria of a Project: 1. A physical activity consists of carrying out tasks or actions involved with construction, modification, operation, and decommissioning (i.e. involving a degree of physical effort). 2. A physical work includes structures that have been built by humans and that have a defined area and fixed locality (i.e. has a local permanence). 3. Federal lands as defined by section 2(1) of CEAA 2012: this applies to proposed Projects that are wholly or partially located on lands and waters managed by Port Metro Vancouver. portmetrovancouver.com 2

  3. PER Review Categories Description portmetrovancouver.com 3

  4. Process Steps Overview Review Phases Steps W hat’s subm itted Step 1 : Prelim inary Project I nquiry Preliminary Phase 1 : Project Inquiry Step 2 : Prelim inary Project I nquiry Review Submitted Prelim inary Review Application Form Step 3 : Application Subm ission and Documents Submitted Step 4 : Com pleteness Check APPLI CATI ON CONSI DERED COMPLETE. APPLI CANT NOTI FI ED. CLOCK STARTS. Phase 2 : Step 5 : Application Review Application Review Step 6 : Project Decision DECI SI ON MADE. APPLI CANT NOTI FI ED. CLOCK STOPS. Step 7 : Perm it Conditions Follow -up Phase 3 : Monitoring portmetrovancouver.com 4

  5. Project Example – Category A Project Facts: • One for one pile replacement project • Piles replaced in close proximity to the location of the piles to be removed • Piles removed in entirety Requirem ents: • Category A/ B • Supporting • No consultation application form required documents included location drawings and installation methodologies portmetrovancouver.com 5

  6. Project Example – Category B Project Facts: • Shoreline protection works 1000 m 2 footprint – • no change from previous footprint • Placement of 1200 m 3 of rip rap • Removal of 3 piles Requirem ents: • Construction notification portmetrovancouver.com 6

  7. Project Example – Category C Project Facts: • 28,000 square metre (300,000 sq. ft.) warehouse • 218 parking stalls • 65 trailer stalls • Paving, fencing, landscaping • New and existing utilities Requirem ents: • Public notification • Construction • Traffic Impact notification Study • Municipal consultation • Building Permit • Landscaping Plan portmetrovancouver.com 7

  8. Project Example – Category D Project Facts: • New grain terminal facility development • Demolition of existing structures • 48 concrete silos of 51.8 m (170 ft.) tall • Berth demolition and upgrade Requirem ents: • Preliminary • View & Alternative • Environmental Comment Period Siting Analysis Studies • Road, Rail and • Public, Stakeholder & • Seismic and Flood Marine Studies Aboriginal Consultation Impact considerations portmetrovancouver.com 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.