Hershey Mill Dam Pond Looking NE Hershey Mill Dam Pond Looking North - - PowerPoint PPT Presentation

hershey mill dam pond looking ne hershey mill dam pond
SMART_READER_LITE
LIVE PREVIEW

Hershey Mill Dam Pond Looking NE Hershey Mill Dam Pond Looking North - - PowerPoint PPT Presentation

Hershey Mill Dam Pond Looking NE Hershey Mill Dam Pond Looking North Hershey Mill Road Hershey Mill Dam East Embankment Looking Towards Spillway Hershey Mill Dam Embankment East of Spillway Erosion Area Hershey Mill Dam Looking Downstream from


slide-1
SLIDE 1

Hershey Mill Dam Pond Looking NE

slide-2
SLIDE 2

Hershey Mill Dam Pond Looking North

Hershey Mill Road

slide-3
SLIDE 3

Hershey Mill Dam East Embankment Looking Towards Spillway

slide-4
SLIDE 4

Hershey Mill Dam Embankment East of Spillway

Erosion Area

slide-5
SLIDE 5

Hershey Mill Dam Looking Downstream from East Embankment

slide-6
SLIDE 6

Hershey Mill Dam Looking Downstream from East Embankment

slide-7
SLIDE 7

Hershey Mill Dam Looking Downstream from East Embankment

slide-8
SLIDE 8

Hershey Mill Dam Looking Downstream from East Embankment

slide-9
SLIDE 9

Dam Upgrades – October 2008

Option 1 – Addition of 200 feet of concrete spillway adjacent to existing stone spillway

Option 2 – New spillway of articulated concrete block (ACB) – (emergency spillway??)

Option 3 – Breach the dam and restore the stream

Sediment testing results

slide-10
SLIDE 10

Other Options/Discussions

Preserve spillway and viewscape

Pump water over spillway

Appropriate stream restoration

slide-11
SLIDE 11

Commentary to Township

Cost estimate without detail or apparent contingency

Construction cost elements not defined

Removal/Management of Sediment – possibly $3 to $5/CY w/o Transportation & Disposal

Clamshell

Mudcat

  • r Divers

Stream Restoration Costs ‐ up to $1 million/stream mile

Approximately 0.2 to 0.3 stream miles

Wetlands/Habitat

Re‐stocking

Flora/Fauna

slide-12
SLIDE 12

Potential Dam Restoration Elements

Slope/Wall Stability

Sheetpiling

Remove wall/ extend slope

Rip‐rap against stone wall

Hydraulic

Spillway crest lowering (w/ flashboards or gate)

Embankment armoring

slide-13
SLIDE 13

Maintenance – Near Term

Tree/ vegetation removal

Repair of eroded/scoured areas

Low outlet valve operational?

Access to Dam

slide-14
SLIDE 14

Discussions