roberts bank
play

ROBERTS BANK TERMINAL 2 PROJECT UPDATE Gilles Assier Director, - PowerPoint PPT Presentation

ROBERTS BANK TERMINAL 2 PROJECT UPDATE Gilles Assier Director, Infrastructure Sustainability November 5, 2015 portmetrovancouver.com ROBERTS BANK TERMINAL 2 PROJECT Existing Roberts Bank Terminals portmetrovancouver.com 2 PROJECT


  1. ROBERTS BANK TERMINAL 2 PROJECT UPDATE Gilles Assier Director, Infrastructure Sustainability November 5, 2015 portmetrovancouver.com

  2. ROBERTS BANK TERMINAL 2 PROJECT Existing Roberts Bank Terminals portmetrovancouver.com 2

  3. PROJECT RATIONALE Includes: Container forecasts • Building capacity • Capacity requirements • RBT2 overview • Project benefits • Project implementation • portmetrovancouver.com 3

  4. ENVIRONMENTAL IMPACT STATEMENT Submitted: March 2015 portmetrovancouver.com 4

  5. ENVIRONMENTAL IMPACT STATEMENT The RBT2 EIS was prepared according to the EIS • Guidelines issued by the CEA Agency on January 7, 2014, and was submitted in March 2015 The information presented in the EIS is intended to • satisfy both federal and provincial EA requirements The EIS includes: • identification of potential effects and benefits of the • Project description of mitigation measures to reduce • potential Project effects portmetrovancouver.com 5

  6. BIOFILM The widened causeway footprint • has been optimized to minimize encroachment into areas of biofilm Our studies show there is • currently extensive biofilm at Roberts Bank and Fraser River estuary which supports large populations of migrating and overwintering birds Our assessment has concluded that feeding • opportunities for birds would not be significantly affected after the construction of the new terminal portmetrovancouver.com 6

  7. CONCLUSIONS OF THE EIS After the implementation of mitigation, the Roberts • Bank Terminal 2 Project is not expected to result in any significant adverse residual effects on any of the 16 valued components No cumulative effects are anticipated, with the • exception of a cumulative effect to southern resident killer whales These conclusions will be subject to a thorough review • by an independent review panel Port Metro Vancouver is confident potential adverse • effects can be fully or partially avoided or reduced through Project design and the implementation of environmental management programs portmetrovancouver.com 7

  8. EIS COMMENTS AND INFORMATION REQUESTS The CEA Agency invited public comments on the • completeness of the EIS between April 30 and June 15, 2015 On July 31, 2015, the CEA Agency requested additional • information to satisfy the requirements of the EIS Guidelines On October 26, 2015, Port Metro Vancouver submitted • responses to these 31 information requests These responses are posted on the CEA Agency project • registry portmetrovancouver.com 8

  9. UPDATED EIS GUIDELINES – APRIL 17, 2015 CEA Agency issued updated EIS Guidelines on April 17, • 2015 Two additional factors: • Marine shipping . The environmental effects of marine • shipping associated with the Project extending to the 12 nautical limit of Canada’s territorial sea. Provincial socio-economic assessment . The potential • economic, social, heritage and health effects of the Project, including cumulative effects. portmetrovancouver.com 9

  10. MARINE SHIPPING SUPPLEMENTAL REPORT Submitted: October 26, 2015 portmetrovancouver.com 10

  11. MARINE SHIPPING SUPPLEMENTAL REPORT The Marine Shipping Supplemental Report assesses • project-related shipping outside of Port Metro Vancouver’s jurisdiction to the 12 nautical mile limit of Canada’s territorial sea . This thorough and robust assessment was completed by • a team of professional scientists, and considers feedback and input from over 20 Aboriginal groups. The conclusion of this work is that marine shipping • associated with the Project is not likely to result in significant adverse residual effects to the valued components assessed. portmetrovancouver.com 11

  12. ENVIRONMENTAL ASSESSMENT NEXT STEPS Federal Process Provincial Process • Provincial process to principally rely on the Federal review panel • BCEAO to make a recommendation to the B.C. Minister of Environment portmetrovancouver.com 12

  13. PROCUREMENT PROCESS Separate procurement processes for the terminal • operator and infrastructure developer Agreements are subject to environmental approval • Project would be funded by Port Metro Vancouver and • private funding and would not require tax dollars portmetrovancouver.com 13

  14. PROCUREMENT UPDATES Port Metro Vancouver received strong interest in the • RFQ for the Roberts Bank Terminal 2 Project Following rigorous review, Port Metro Vancouver has • shortlisted five teams to respond to the RFP in late 2015 These teams are: • Abu Dhabi Terminals • Grup TCB / Mitsubishi Corp consortium • Ports America • PSA International • Terminal Link / CMHI consortium • portmetrovancouver.com 14

  15. LEARN MORE Available at portmetrovancouver.com/RBT2 and at the Delta Community Office. portmetrovancouver.com 15

  16. LEARN MORE Stay updated Sign up for Project updates at • www.portmetrovancouver.com/RBT2 Sign up for updates from CEAA • process at www.ceaa-acee.gc.ca portmetrovancouver.com 16

  17. THANK YOU Questions? • portmetrovancouver.com 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend