portmetrovancouver.com
ROBERTS BANK TERMINAL 2 PROJECT UPDATE Gilles Assier Director, - - PowerPoint PPT Presentation
ROBERTS BANK TERMINAL 2 PROJECT UPDATE Gilles Assier Director, - - PowerPoint PPT Presentation
ROBERTS BANK TERMINAL 2 PROJECT UPDATE Gilles Assier Director, Infrastructure Sustainability November 5, 2015 portmetrovancouver.com ROBERTS BANK TERMINAL 2 PROJECT Existing Roberts Bank Terminals portmetrovancouver.com 2 PROJECT
SLIDE 1
SLIDE 2
portmetrovancouver.com
Existing Roberts Bank Terminals
ROBERTS BANK TERMINAL 2 PROJECT
2
SLIDE 3
portmetrovancouver.com
Includes:
- Container forecasts
- Building capacity
- Capacity requirements
- RBT2 overview
- Project benefits
- Project implementation
PROJECT RATIONALE
3
SLIDE 4
portmetrovancouver.com
ENVIRONMENTAL IMPACT STATEMENT
Submitted: March 2015
4
SLIDE 5
portmetrovancouver.com
- The RBT2 EIS was prepared according to the EIS
Guidelines issued by the CEA Agency on January 7, 2014, and was submitted in March 2015
- The information presented in the EIS is intended to
satisfy both federal and provincial EA requirements
- The EIS includes:
- identification of potential effects and benefits of the
Project
- description of mitigation measures to reduce
potential Project effects ENVIRONMENTAL IMPACT STATEMENT
5
SLIDE 6
portmetrovancouver.com
- The widened causeway footprint
has been optimized to minimize encroachment into areas of biofilm
- Our studies show there is
currently extensive biofilm at Roberts Bank and Fraser River estuary which supports large populations of migrating and
- verwintering birds
BIOFILM
6
- Our assessment has concluded that feeding
- pportunities for birds would not be significantly
affected after the construction of the new terminal
SLIDE 7
portmetrovancouver.com
- After the implementation of mitigation, the Roberts
Bank Terminal 2 Project is not expected to result in any significant adverse residual effects on any of the 16 valued components
- No cumulative effects are anticipated, with the
exception of a cumulative effect to southern resident killer whales
- These conclusions will be subject to a thorough review
by an independent review panel
- Port Metro Vancouver is confident potential adverse
effects can be fully or partially avoided or reduced through Project design and the implementation of environmental management programs CONCLUSIONS OF THE EIS
7
SLIDE 8
portmetrovancouver.com
- The CEA Agency invited public comments on the
completeness of the EIS between April 30 and June 15, 2015
- On July 31, 2015, the CEA Agency requested additional
information to satisfy the requirements of the EIS Guidelines
- On October 26, 2015, Port Metro Vancouver submitted
responses to these 31 information requests
- These responses are posted on the CEA Agency project
registry
EIS COMMENTS AND INFORMATION REQUESTS
8
SLIDE 9
portmetrovancouver.com
- CEA Agency issued updated EIS Guidelines on April 17,
2015
- Two additional factors:
- Marine shipping. The environmental effects of marine
shipping associated with the Project extending to the 12 nautical limit of Canada’s territorial sea.
- Provincial socio-economic assessment. The potential
economic, social, heritage and health effects of the Project, including cumulative effects.
UPDATED EIS GUIDELINES – APRIL 17, 2015
9
SLIDE 10
portmetrovancouver.com
MARINE SHIPPING SUPPLEMENTAL REPORT
Submitted: October 26, 2015
10
SLIDE 11
portmetrovancouver.com
- The Marine Shipping Supplemental Report assesses
project-related shipping outside of Port Metro Vancouver’s jurisdiction to the 12 nautical mile limit of Canada’s territorial sea.
- This thorough and robust assessment was completed by
a team of professional scientists, and considers feedback and input from over 20 Aboriginal groups.
- The conclusion of this work is that marine shipping
associated with the Project is not likely to result in significant adverse residual effects to the valued components assessed. MARINE SHIPPING SUPPLEMENTAL REPORT
11
SLIDE 12
portmetrovancouver.com
ENVIRONMENTAL ASSESSMENT NEXT STEPS
12
- Provincial process to principally rely on the Federal review panel
- BCEAO to make a recommendation to the B.C. Minister of Environment
Federal Process Provincial Process
SLIDE 13
portmetrovancouver.com
- Separate procurement processes for the terminal
- perator and infrastructure developer
- Agreements are subject to environmental approval
- Project would be funded by Port Metro Vancouver and
private funding and would not require tax dollars PROCUREMENT PROCESS
13
SLIDE 14
portmetrovancouver.com
- Port Metro Vancouver received strong interest in the
RFQ for the Roberts Bank Terminal 2 Project
- Following rigorous review, Port Metro Vancouver has
shortlisted five teams to respond to the RFP in late 2015
- These teams are:
- Abu Dhabi Terminals
- Grup TCB / Mitsubishi Corp consortium
- Ports America
- PSA International
- Terminal Link / CMHI consortium
PROCUREMENT UPDATES
14
SLIDE 15
portmetrovancouver.com
LEARN MORE
Available at portmetrovancouver.com/RBT2 and at the Delta Community Office.
15
SLIDE 16
portmetrovancouver.com
LEARN MORE Stay updated
- Sign up for Project updates at
www.portmetrovancouver.com/RBT2
- Sign up for updates from CEAA
process at www.ceaa-acee.gc.ca
16
SLIDE 17
portmetrovancouver.com
- Questions?
THANK YOU
17