Policies for a Rising Bay Project Steering Committee Meeting #4 March - - PowerPoint PPT Presentation

policies for a rising bay
SMART_READER_LITE
LIVE PREVIEW

Policies for a Rising Bay Project Steering Committee Meeting #4 March - - PowerPoint PPT Presentation

The Policies for a Rising Bay Project Steering Committee Meeting #4 March 29, 2016 Welcome & Meeting Objectives Describe case studies and present key points of the policy analysis to develop a shared understanding of how current BCDC


slide-1
SLIDE 1

The

Policies for a Rising Bay

Project

Steering Committee Meeting #4 March 29, 2016

slide-2
SLIDE 2

Welcome & Meeting Objectives

  • Describe case studies and present

key points of the policy analysis to develop a shared understanding

  • f how current BCDC laws and

policies apply to the case-study solutions

  • Discuss key policy questions that

arise out of the case study analysis

  • Discuss equity recommendations

with the Environmental Justice Subcommittee

slide-3
SLIDE 3

What have we been up to?

  • Developed Airport and Contaminated Lands Case

Studies & Analysis

  • BCDC Staff Discuss Case Studies
  • Environmental Justice Subcommittee Meeting
slide-4
SLIDE 4
  • 1. Scoping

(Winter 2015)

  • 2. Policy analysis

(Summer 2015)

  • 3. Case studies

(Spring 2016)

  • 4. Guidance

(Summer / Fall 2016)

Project Progress

  • Guidance on the application of existing fill

policies

  • Explore policy alternatives for

Commission consideration

slide-5
SLIDE 5

Overarching Policy Goals

  • Facilitate projects with multiple benefits that

emphasize nature-based adaptation solutions wherever feasible and that are adaptable in a dynamic estuary;

  • Promote equitable management of the Bay to

increase resilience in vulnerable communities;

  • Preserve, restore, and enhance Bay ecosystem

diversity; and

  • Support sustainable development, economic

health, and quality of life of the Bay Area.

slide-6
SLIDE 6

Agenda

  • Welcome, Introductions

& Announcements

  • Airport Case Study
  • Discussion
  • Contaminated Lands

Case Study

  • Discussion
  • Report Back
  • Environmental Justice

Subcommittee Meeting

slide-7
SLIDE 7

The

Policies for a Rising Bay

Project

Case Studies & Analysis

Miriam Torres

slide-8
SLIDE 8

Case Study Changes

  • Goal: focus on key policy issues
  • Case study description is similar to a

Notice of Preparation

  • Policy analysis is modeled after a

comment letter

slide-9
SLIDE 9
  • Purpose: Fortify

perimeter to meet current flood risk standards and make the airport resilient to 2050

Airport Case Study

slide-10
SLIDE 10

Project Proposal

  • Address height deficiencies and gaps in

perimeter dike

  • Install new embankments and deep

cement-soil mix walls, and underground rock columns

  • Maintenance & Adaptive Management

– Additional riprap – Explore onsite protection and collaboration with neighbors

slide-11
SLIDE 11

Probable Environmental Impacts

  • Air Quality
  • Biological Resources
  • Geology and Soils
  • Hydrology and Water Quality
  • Land Use and Planning
  • Noise and Vibration
slide-12
SLIDE 12

Policy Issues

  • Shoreline

Protection

– Consideration

  • f sea level rise

combined with flooding from storms

slide-13
SLIDE 13

Policy Issues

  • Environmental

Justice

– Airport can flood from neighboring land uses by 2050 – Integration with current or planned shoreline protection

slide-14
SLIDE 14

Policy Issues

  • Adaptive Management

– Raising dike heights over time

slide-15
SLIDE 15

Discussion

slide-16
SLIDE 16
  • Purpose:

Improve a closed landfill’s shoreline protection to meet current flood risk standards and be resilient to 2050

Contaminated Lands Case Study

slide-17
SLIDE 17

Project Proposal

  • Replace degraded concrete revetment.
  • Install engineered graded rocky revetment

topped with riprap.

  • Maintenance & Adaptive Management

– Semi-annual monitoring as required by RWQCB. – Raise revetment height with supplementary graded material to protect until 2100 (if needed). – Cutoff slurry wall to protect groundwater against saltwater intrusion (if needed).

slide-18
SLIDE 18

Probable Environmental Impacts

  • Air Quality
  • Biological Resources
  • Geology and Soils
  • Hazards and Hazardous Materials
  • Hydrology and Water Quality
  • Land Use and Planning
  • Noise and Vibration
slide-19
SLIDE 19

Policy Issues

  • Shoreline Protection

– Project is designed to be resilient to mid- century, and adaptable beyond 2050 – Project should meet sound engineering criteria – Applicant should consider using innovative SLR adaptation strategies

slide-20
SLIDE 20

Policy Issues

  • Environmental Justice

– Assess consequences of upgraded revetment

  • n adjacent land uses

– Discuss efficacy of proposal and alternatives to prevent discharge of pollutants due to changing groundwater levels, flow direction and rates, and salinity as sea level rises – Protection should be integrated with current

  • r planned adjacent shoreline protection

measures

slide-21
SLIDE 21

Policy Issues

  • Adaptive Management

– Risk assessment and best available SLR projection should be used in adaptive management plan – Monitoring and Adaptive management plan should demonstrate how project will prevent pollutants from entering Bay

slide-22
SLIDE 22

Discussion

slide-23
SLIDE 23

Report Back

slide-24
SLIDE 24

Next Steps

  • Draft Summary Report: Guidance and

Recommendations

  • Steering Committee Meeting #5 in May
  • Final Summary Report
slide-25
SLIDE 25

Environmental Justice Subcommittee Agenda

Overview of 3/21 Meeting Discussion – Subcommittee Members Provide Feedback Sea Level Rise and Fill-related Impacts on Environmental Justice Communities

  • How BCDC could address potential impacts with existing policies
  • Policy changes that may be necessary to address potential impacts
  • Other ways BCDC has influence over equity and environmental justice

Next Steps

slide-26
SLIDE 26

Sea Level Rise and Fill-related Impacts on Environmental Justice Communities

  • How BCDC could address potential

impacts with existing policies

  • Policy changes that may be necessary to

address potential impacts

  • Other ways BCDC has influence over

equity and environmental justice

slide-27
SLIDE 27

Next Steps