policies for a rising bay
play

Policies for a Rising Bay Project Steering Committee Meeting #4 March - PowerPoint PPT Presentation

The Policies for a Rising Bay Project Steering Committee Meeting #4 March 29, 2016 Welcome & Meeting Objectives Describe case studies and present key points of the policy analysis to develop a shared understanding of how current BCDC


  1. The Policies for a Rising Bay Project Steering Committee Meeting #4 March 29, 2016

  2. Welcome & Meeting Objectives Describe case studies and present • key points of the policy analysis to develop a shared understanding of how current BCDC laws and policies apply to the case-study solutions Discuss key policy questions that • arise out of the case study analysis Discuss equity recommendations • with the Environmental Justice Subcommittee

  3. What have we been up to? • Developed Airport and Contaminated Lands Case Studies & Analysis • BCDC Sta ff Discuss Case Studies • Environmental Justice Subcommittee Meeting

  4. Project Progress 4. Guidance 1. Scoping 2. Policy analysis 3. Case studies (Summer / (Winter 2015) (Summer 2015) (Spring 2016) Fall 2016) • Guidance on the application of existing fill policies • Explore policy alternatives for Commission consideration

  5. Overarching Policy Goals • Facilitate projects with multiple benefits that emphasize nature-based adaptation solutions wherever feasible and that are adaptable in a dynamic estuary; • Promote equitable management of the Bay to increase resilience in vulnerable communities; • Preserve, restore, and enhance Bay ecosystem diversity; and • Support sustainable development, economic health, and quality of life of the Bay Area.

  6. Agenda • Welcome, Introductions & Announcements • Airport Case Study • Discussion • Contaminated Lands Case Study • Discussion • Report Back • Environmental Justice Subcommittee Meeting

  7. The Policies for a Rising Bay Project Case Studies & Analysis Miriam Torres

  8. Case Study Changes • Goal: focus on key policy issues • Case study description is similar to a Notice of Preparation • Policy analysis is modeled after a comment letter

  9. Airport Case Study • Purpose: Fortify perimeter to meet current flood risk standards and make the airport resilient to 2050

  10. Project Proposal • Address height deficiencies and gaps in perimeter dike • Install new embankments and deep cement-soil mix walls, and underground rock columns • Maintenance & Adaptive Management – Additional riprap – Explore onsite protection and collaboration with neighbors

  11. Probable Environmental Impacts • Air Quality • Biological Resources • Geology and Soils • Hydrology and Water Quality • Land Use and Planning • Noise and Vibration

  12. Policy Issues • Shoreline Protection – Consideration of sea level rise combined with flooding from storms

  13. Policy Issues • Environmental Justice – Airport can flood from neighboring land uses by 2050 – Integration with current or planned shoreline protection

  14. Policy Issues • Adaptive Management – Raising dike heights over time

  15. Discussion

  16. Contaminated Lands Case Study • Purpose: Improve a closed landfill’s shoreline protection to meet current flood risk standards and be resilient to 2050

  17. Project Proposal • Replace degraded concrete revetment. • Install engineered graded rocky revetment topped with riprap. • Maintenance & Adaptive Management – Semi-annual monitoring as required by RWQCB. – Raise revetment height with supplementary graded material to protect until 2100 (if needed). – Cuto ff slurry wall to protect groundwater against saltwater intrusion (if needed).

  18. Probable Environmental Impacts • Air Quality • Biological Resources • Geology and Soils • Hazards and Hazardous Materials • Hydrology and Water Quality • Land Use and Planning • Noise and Vibration

  19. Policy Issues • Shoreline Protection – Project is designed to be resilient to mid- century, and adaptable beyond 2050 – Project should meet sound engineering criteria – Applicant should consider using innovative SLR adaptation strategies

  20. Policy Issues • Environmental Justice – Assess consequences of upgraded revetment on adjacent land uses – Discuss e ffi cacy of proposal and alternatives to prevent discharge of pollutants due to changing groundwater levels, flow direction and rates, and salinity as sea level rises – Protection should be integrated with current or planned adjacent shoreline protection measures

  21. Policy Issues • Adaptive Management – Risk assessment and best available SLR projection should be used in adaptive management plan – Monitoring and Adaptive management plan should demonstrate how project will prevent pollutants from entering Bay

  22. Discussion

  23. Report Back

  24. Next Steps • Draft Summary Report: Guidance and Recommendations • Steering Committee Meeting #5 in May • Final Summary Report

  25. Environmental Justice Subcommittee Agenda Overview of 3/21 Meeting Discussion – Subcommittee Members Provide Feedback Sea Level Rise and Fill-related Impacts on Environmental Justice Communities • How BCDC could address potential impacts with existing policies • Policy changes that may be necessary to address potential impacts • Other ways BCDC has influence over equity and environmental justice Next Steps

  26. Sea Level Rise and Fill-related Impacts on Environmental Justice Communities • How BCDC could address potential impacts with existing policies • Policy changes that may be necessary to address potential impacts • Other ways BCDC has influence over equity and environmental justice

  27. Next Steps

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend