Belwind 1 + Northwind 165MW + 216 MW Offshore Windfarm 2 Overview - - PowerPoint PPT Presentation

belwind 1 northwind 165mw 216 mw offshore windfarm 2
SMART_READER_LITE
LIVE PREVIEW

Belwind 1 + Northwind 165MW + 216 MW Offshore Windfarm 2 Overview - - PowerPoint PPT Presentation

Belwind 1 + Northwind 165MW + 216 MW Offshore Windfarm 2 Overview Belwind I: Northwind: 55 WTG Vestas V90 + 1 72 WTG Vestas V90 + 1 OHVS OHVS ca. 48km off Zeebrugge ca. 37km off Zeebrugge 17km 14,5km


slide-1
SLIDE 1

Belwind 1 + Northwind 165MW + 216 MW Offshore Windfarm

slide-2
SLIDE 2

2

slide-3
SLIDE 3

3

Overview

Belwind I:

  • 55 WTG Vestas V90 + 1

OHVS

  • ca. 48km off Zeebrugge
  • 17km²
  • 52km export cable
  • 550 GWh ~ 160.000 ton CO2

~ 160.000 household

  • construction 2009-2010
  • ± 650 mio EUR

Northwind:

  • 72 WTG Vestas V90 + 1

OHVS

  • ca. 37km off Zeebrugge
  • 14,5km²
  • 43km export cable
  • 875 GWh ~ 235.000 ton CO2

~ 230.000 household

  • construction 2013-2014
  • ± 750 mio EUR
slide-4
SLIDE 4

4

Belwind vessels

slide-5
SLIDE 5

5

Northwind vessels

slide-6
SLIDE 6

6

OHVS

BW: Trafo 33/150 kV NW: Trafo 33/220 kV

  • Main + auxillary transformers
  • HV + MV switchgear
  • Power-SCADA
  • Automation
  • Generator/UPS
  • Fire Fighting
  • HVAC
  • ...
slide-7
SLIDE 7

7

O&M Organisation

Board of directors Management Team CEO COO CLO CFO Asset & Production Manager

Electrical infra. Package WTG Package Civil Package

Cables Foundations OHVS + BS 55 WTG

slide-8
SLIDE 8

8

WTG Package

Long term contract with Vestas

  • Competent and trained technicians/experts
  • Access to knowledge database
  • Spare part availability

 15 year full covering service agreement Availability guarantees Revenue sharing model 2 contract managers

  • Monitor availability
  • Maintain a downtime database
  • Define red flags
  • Steering in priorities

1 site manager

  • Safe working
  • Quality of work
  • Audit and inspections
  • Technical queries
slide-9
SLIDE 9

9

Electrical Package

2 OHVS 1 Booster Station

Maintenance performed by CG with long-term contract

  • Steering of production 24/7
  • Emergency standby 24/7
  • Bundle activities of specialist partners

2 contract managers

  • Contract responsible
  • Follow-up preventive maint.
  • Define adaptive maintenance
  • Control corrective maintenance
  • Spare part management
  • Continuous Improvement

1 site manager

  • Safe working
  • Quality of work
  • Audit and inspections
  • Technical queries
slide-10
SLIDE 10

10

Civil Package

129 Foundations

  • Paint
  • Cathodic protection
  • Diving + ROV
  • Grout + bearings
  • Mechanical
  • Scour protection

± 100 km of infield cable ± 100 km of export cable

  • Specialized contractor parties are hired
  • Aim to build long term relationships
  • Follow the market

1 manager

  • Inspections and trending
  • Maintenance planning
  • Coordination of activities
  • Ownership of data
  • Survey planning and trending
  • Contingency portfolio
slide-11
SLIDE 11

11

BoP threats

  • External corrosion
  • Below water (CP)
  • Splash zone
  • Above water
  • Internal corrosion
  • Vibrations: macro (fatigue)
  • Vibrations: micro (bolts, nuts, ...)
  • Scour protection
  • Appendages (cranes, nav lights, ...)
  • Cable damage
  • ...
slide-12
SLIDE 12

12

BoP monitoring

  • Vibration
  • Corrosion: types, speed
  • Drivetrain monitoring
  • Grout analysis
  • Survey: MBE, SSS, ROV, …
  • O&M optimization
slide-13
SLIDE 13

Thanks for your attention! Questions?