Offshore Wind Energy – The Installation Challenge
- Prof. Dr. Martin Skiba
Director Wind Energy Offshore RWE Innogy GmbH Nomura Offshore Wind Seminar London, 22 January 2010
Offshore Wind Energy The Installation Challenge Prof. Dr. Martin - - PowerPoint PPT Presentation
Offshore Wind Energy The Installation Challenge Prof. Dr. Martin Skiba Director Wind Energy Offshore RWE Innogy GmbH Nomura Offshore Wind Seminar London, 22 January 2010 Which steps have to be taken to construct an offshore windfarm?
Director Wind Energy Offshore RWE Innogy GmbH Nomura Offshore Wind Seminar London, 22 January 2010
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 2
Example of Rhyl Flats offshore wind farm
2002: Met Mast Installation May - Jul 2008: Installation of foundations Apr - Oct 2009: Turbine Installation Inter array cable laying Aug - Nov 2008: Export Cable Laying Jun - Sept 2007, Apr - Oct 2008: Scour Protection (preparing seabed for installation)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 3
Getting to the point:
water and high altitude…
do not meet market requirements
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 4
Challenge Health & Safety:
Offshore installation works combine three extremely challenging types of work: > work at sea > work at great heights > heavy lifting works
1) Source: Offshore injury, ill health and incident statistics 2007/2008, Health & Safety
Executive Hazardous Installations Directorate Offshore Division, UK
RWE Innogy approach: > Strict health and safety procedures > Health, Safety & Environment (HSE) group of professionals looking after RWE Innogy staff and our subcontractors > Head of HSE with 35 years of offshore experience Major offshore incidents in UK (RIDDOR reportable)1)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 5
Challenge Weather:
5 10 15 20 25 30 J a n u a r y F e b r u a r y M a r c h A p r i l M a y J u n e J u l y A u g u s t S e p t e m b e r O c t
e r N
e m b e r D e c e m b e r
1 12 hours installation windows per month at 1.5 m significant wave height and maximum wind speed of
10 m/s, statistical values for German North Sea
Average days with good weather1 > Winter months offer a significantly lower number of days with adequate conditions and seriously impede installation works > This makes installation works extremely time critical > Bad weather can significantly delay the entire project > Delays do not only result in increased installation costs, but also in foregone revenues from power generation
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 6
Challenge Component Weight:
weight: ca. 250 t plus transition piece ca. 180 t height: ca. 30 m material: steel turbine: 3.6 MW weight:
height:
material: concrete turbines: 5/6 MW Gravity Foundations weight:
height:
material: steel turbines: 5/6 MW Jackets Monopiles
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 7 Rotor diameter Hub height Source: Bundesverband Windenergie, BTM Consult – World Market Update 2008 (March 2009).
105 m 90 m 3,000 kW
2005
135 m 126 m 6,000 kW
2008
100 m 70 m 1,500 kW
2000
78 m 50 m 40 m 30 m Hub height 46 m 30 m 20 m 15 m Rotor diameter 600 kW 250 kW 80 kW 30 kW Nominal capacity
1995 1990 1985 1980
Challenge Component Weight:
> The REpower 5M Facts:
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 8
Challenge Component Logistics:
RWE Innogy’s Offshore Wind Projects Inch Cape Triton Knoll North Hoyle Gwynt y Môr Rhyl Flats Greater Gabbard Nordsee Ost Innogy Nordsee 1 Tromp Binnen Thornton Bank Projects in operation or under construction Projects consented or in development Bristol Channel Dogger Bank
RWE Innogy project pipeline: 0.76 GW installed by 2013 Project pipeline of 9.7 GW (pro rata) and 6.4 GW (accounting view) as of December 2009, incl. UK Round 3 Critical mass reached to contemplate alternative logistic supply strategy
Example Gwynt y Môr: 576 MW capacity, 160 turbines
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 9
Challenge Installation Vessels:
A2Sea – Sea Jack A2Sea – Sea Worker MPI – Resolution Smit – Lisa Siemens – Titan 2 Jack-Up Barge BV – JB114
Dong Dong
55 x 32 m 73 x 40 m 54 x 34 m 130 x 38 m 91 x 33 m 55 x 32 m Vessel dimensions 40 m 33 m >40 m 35 m 35 m 40 m
<5.0 MW 3.6 MW 3.6 MW 3.6 MW 5-6 MW 3.6 MW
JB114/JB115 Lisa Titan 2 Resolution Sea Jack Sea Worker Vessel name Jack Up Barge BV Smit Siemens MPI A2Sea Operating Company
Market after A2Sea deal: > A2Sea, the company with the most expertise, assets and manpower, is no longer available. It built 60% of operational offshore wind farms, and was bought by DONG > 40% of market assets are no longer available
Centrica
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 10
Challenge Installation Vessels:
m 5 m 10 m 15 m 20 m 25 m 30 m 35 m 40 m 45 m 50 m 0.0 MW 1.0 MW 2.0 MW 3.0 MW 4.0 MW 5.0 MW 6.0 MW
Turbine size Water depth
Offshore wind projects (online or under construction) RWE Offshore wind projects (online or under construction) Planned RWE Offshore wind projects
Future Offshore Wind Farms RWE Innogy Existing Offshore Wind Farms
Centrica Dong Dong
Maximum conditions for current installation vessels
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 11
Our approach:
Seabreeze Programme:
> Construction of 2 self propelled Jack-Up vessels > Specially designed for turbines in the 5 to 6 MW class… > and deepwater environment: possibility to be used in water depth > 45 meters (using leg extensions) > Less exposed to weather conditions
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 12
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 13
Biomass Wind Onshore Wind Offshore Hydro New Applications
Overview Business Area Focus and Strategy > Established in February 2008 > Bundling renewables activities and competencies across RWE Group – Focus on capacity growth in commercially mature renewable technologies, i.e. wind, biomass and hydro – Research & Development and Venture Capital to drive the development of emerging technologies, e.g. solar, geothermal, marine > European focus > Asset portfolio of 2.1 GW capacity in operation and 0.5 GW under construction mainly located in United Kingdom, Germany, Spain, Netherlands, Italy and France (Accounting view + PPA as at Q3 2009) > Project pipeline of 18.9 GW capacity of wind, hydro and biomass (Accounting view + PPA as at Q3 2009)
RWE Innogy
Key technology for capacity growth Focus on organic growth Focus markets include Germany, UK, Spain, Italy, Netherlands, France and Central- and South-Eastern Europe Key technology for capacity growth Organic growth strategy leveraging strong position in UK Focus markets include UK, Germany and Netherlands Run-of-river projects and storage plants Development of hydro power projects Focus areas are South- Eastern Europe and Turkey Development of biomass plants Regional focus on RWE core markets and Central- and South- Eastern Europe Driving innovative renewable technologies towards commercial stage through Venture Capital and R&D and proving large scale commercial feasibility by
plants
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 14
GER UK Spain Portugal France Switzerland Czech Republic
RWE Innogy1) operational capacities: Accounting View2) + Power Purchase Agreements, Q3 2009 20 20 Czech Republic 23 23 Switzerland 413 12 401 Spain 1 1 Solar 232 2321) Netherlands 4 4 Biogas 871 94 356 4161) Germany 417 602) 69 2884) [1355)] UK 65 45 20 France 16 16 Portugal 2,057 60 1146) 521 1,357 Total RWE Innogy Total Offshore Wind Biomass Hydro Onshore Wind In MWel
NL BE
1) Essent contributed 232 MW onshore wind assets in the Netherlands and 405 MW
in Germany as of September 30, 2009.
2) Capacity with <50% RWEI ownership is consolidated to 0 MW, capacity with 50%
is consolidated to 50% of capacity, and capacity with >50% RWEI ownership is consolidated to 100% of capacity.
3) Capacity equal to share of ownership. 4) 288 MW = 92 MW Innogy wholly owned assets + 196 MW of Zephyr assets. RWE
Innogy operates 483 MW, of this 391 MW (331 MW onshore/60 MW offshore) is
MW onshore, 196 MW is 100% contracted to RWE npower through PPAs (power purchase agreements). The remaining 92 MW is onshore and 100% owned by RWE Innogy and 100% contracted to RWE npower through a PPA. The offshore capacity of 60 MW is 100% contracted to RWE npower through a PPA.
5) An additional capacity of 135 MW is contracted to the NFPA (Non-Fossil
Fuel Purchasing Agency, est. 1989 to support renewables by offering long term PPAs and new projects were typically contracted in this way until the introduction of the Renewables Obligation in 2002).
6) Including 32 MW of biomass/fossil mix, 14 MW of fossil capacity.
New Applications Hydro Onshore Wind Biomass Offshore Wind 17 15 2 Portugal RWE Innogy1) operational capacities: Pro Rata View3) + Power Purchase Agreements, Q3 2009 20 20 Czech Republic 23 23 Switzerland 407 <1 10 397 Spain 1 1 232 2321) Netherlands 2 2 850 92 339 4161) Germany 417 602) 69 2884) [1355)] UK 65 45 20 France 8 8 Belgium 2,039 68 1126) 501 1,355 Total RWE Innogy
(as of 30 September 2009)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 15
Project pipeline by technology & status (electricity generation capacity in GW)
Note: Pipeline status 1 – Permitted projects: all permits (including grid) in place, but not yet under construction Pipeline status 2 – Unconsented projects: RWEI has rights to the project, e.g. land agreements Pipeline status 3 – Prospects: identified sites with a known MW capacity, initial discussion on agreements
18.9
Total Pipeline Pipeline Status 3
10.4
Pipeline Status 2
7.2
Pipeline Status 1
1.3
Under Construction
0.5
In Operation
2.1 Onshore Wind Offshore Wind Biomass Hydro New Applications
1) For pipeline projects no power purchase agreement (PPA) is assumed. Therefore pipeline projects with
<50% RWEI ownership are consolidated to 0MW, pipeline projects with 50% are consolidated to 50% of capacity, and pipeline projects with >50% RWE Innogy ownership are consolidated to 100% of capacity.
2) For pipeline projects no power purchase agreement (PPA) is assumed. Pipeline capacity equal to share
17.2
Total Pipeline Pipeline Status 3
9.3
Pipeline Status 2
6.5
Pipeline Status 1
1.3
Under Construction
0.5
In Operation
2.0
Accounting View + Power Purchase Agreements1) Pro Rata View + Power Purchase Agreements2)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 16
Capacity growth targets (in GW, pro rata)
Value oriented growth strategy > Objective is profitable growth of renewables business > We want to increase our capacity to 4.5 GW in operation or under construction by 2012 and exceed 10 GW by 2020 – Strong organic growth (incl. development
acquisitions – Average investments of at least € 1 bn p.a. – Value creation in line with RWE's strict investment criteria > We will be operating in markets we know –
> Innovative renewable technologies offer additional growth options
1) Composed of 1,100 MW capacity in operation and 211 MW under construction (pro rata). 2) Composed of 1,271 MW capacity in operation and 470 MW under construction (pro rata). 3) Composed of 2,039 MW capacity in operation (incl. 637 MW Essent, which was consolidated as of Sept 30, 2009) and 482 MW under construction (pro rata). 4) Minimum annually generated electricity to be achieved from 2013 onwards on the basis of the 4.5 GW target.
2 4 6 8 10 12 Assets in operation or under construction Assets under construction Assets in operation Essent Assets in operation RWE Innogy
1.72) 2.53) 4.5 > 10 Dec 2008 Sept 2009 2020 2012
15 TWh/a4)
Dec 2007 1.31)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 17
… generation capacity … electricity generation … country (electricity generation) … support mechanism (electricity generation) RWE Innogy target portfolio by …
Hydro Offshore Wind Biomass Onshore Wind Hydro Offshore Wind Biomass Onshore Wind Germany UK Netherlands Other Certificate Other Power Price only Italy Spain Premium Tariff Feed-In Tariff
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 18
European Market Features
> Maturing technology with high rate of innovation, but limited track record > Current land grap for offshore wind pipeline > Main growth countries are Germany and the UK > Few suppliers with proven technology > Technology with relatively high generation cost per MWh but existing support mechanisms provide attractive remuneration > Large scale projects often funded through partnerships models
Opportunities
> Wind resource better than onshore (load factors 35%+) > Attractive growth opportunities & industrial scale projects > Technology progress with significant cost reduction potential > Strong political support reduces regulatory risks
Challenges
> Tight supply situation across the value chain > Relative to onshore wind, high maintenance risks far out at sea: safety, costs, access, technology > Limited best practice track record available make it a skill game
RWE Innogy Strengths
> Secure key value chain technologies (e.g. turbines, vessels) > Recruit best offshore experts available > Stepwise approach from “nearshore” to “farshore” to minimise risks
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 19
United Kingdom 150 MW1)
Offshore wind capacity
RWE Innogy presence
1) Owned by Zephyr Investments Ltd which is 1/3 owned by RWE Innogy UK. The 60 MW capacity is 100% contracted to RWE npower through PPAs (power purchase agreements).
Markets and operations Technology & markets
> Immature market: 1.5 GW installed offshore wind capacity in EU-27 in 2008 > Strong market growth in medium to long term – Time horizon depends on technical progress and development of approval procedures > Significant technological challenges remain especially in offshore foundations and structures > Trends: Technical hurdles overcome, allocation
RWE Innogy's assets
(Accounting view + PPA)
> 150 MW offshore wind farm (North Hoyle1), Rhyl Flats) in operation and 252 MW (Greater Gabbard) under construction > 27% stake in Belgian offshore wind project Thornton Bank - 30 MW of planned total capacity
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 20
“Pioneer” Phase Commercial 2015 + X
RWE Innogy Offshore Projects
Princess Amalia (Q7) Burbo Bank Samso Belwind Robin Rigg Lynn & Inner Dowsing Lillgrund Barrow Egmond aan Zee Beatrice Field Kentish Flats Scroby Sands Arklow Bank
North Hoyle
Nysted Horns Rev
Innogy Nordsee 1
London Array Nordergründe
Nordsee Ost
Sheringham Shoal Lincs Rødsand II Côte d'Albâtre Baltic 1 Bard Offshore 1
Greater Gabbard
Thanet Gunfleet Sands Horns Rev 2
Rhyl Flats
Alpha Ventus
Thornton Bank Gwynt y Môr
Global Tech 1 Amrum Bank West Dan-Tysk Sandbank 24
Triton Knoll
Hochseewindpark De Dreiht Gode Wind Butendiek Albatros
5 10 15 20 25 30 35 40 45 50 10 20 30 40 50 60 70 80 90 100 Shore Distance [km] Water Depth [m]
UK Round 3 East Coast
Hochsee Windpark Nordsee
Planned OWF
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 21
> Total generation capacity 60 MW > 30 Vestas V 80 turbines with 2 MW each (10 km2) > 7 km off the North Wales coast > Shallow water: 7 – 11 m (LAT) > Operational since 2003 - first commercial
> Total project costs of £ 80 m
Nov 2003 First power generation Sept – Dec 2003 Offshore cable works Aug 2003 – Mar 2004 Wind turbines Aug – Oct 2003 Export cables Jul – Aug 2003 Transition pieces Jun – Aug 2003 Boat landings Apr – Jul 2003 Wind turbine foundations
North Hoyle Construction Diary
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 22
> 90 MW (25 turbines Siemens 3.6 MW) > 8 km off the coast > Water depth around 15 m > Wind farm area 10 km2 > Fully consented in December 2002, construction started in August 2008,
> Total investment € 280 m
(Under construction)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 23
> 504 MW (RWE Innogy with 50% share) > 140 Siemens turbines 3.6 MW with monopiles (147 km2) > Shore distance 25 - 47 km, 24 - 34 m water depth > Installation start in 2009, installation in two stages > First generation early in 2011, fully operational in late 2011 > Investment of around £ 1.3 bn (excl. grid connection)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 24
> Capacity of 576 MW > 160 Siemens turbines with each 3.6 MW capacity (124 km2) > 13 km off the coast of North Wales > Water depth 12 - 28 m > Application submitted in 2005 > Consent received 3rd December 2008 > Consent for grid connection received > Installation planned in three stages in 2011 – 2014
(Operating)
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 25
> 35 km north from Helgoland > Capacity 288 MW > 48 x 6 MW REpower turbines (34 km2) > Water depth about 22 - 26 m > Building permission since June 2004 > Offshore construction to commence in September 2011, first generation in 2012, full commissioning in 2013 > Stable wind conditions proven by metering mast in operation since April 2005 > Grid connection point: Brunsbüttel > 90 km sea cable / 45 km land cable > Voltage level: 150 kV/AC
Nordsee Ost
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 26
> Capacity of approx. 1,000 MW > Approx. 165 turbines REpower 6M > German Bight, 40 km off shore of the Isle Juist, water depth 26 – 34 m; area 146 km² > Nearly 4,000 full load hours > Preferred area according to German regulations > Consent expected in 2009 > Soil investigation 2009 > Expected fully operational in 2016 > Investment of approx. € 2.8 bn > Annual CO2 reduction of approx. 3.1 million tonnes
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 27
> Capacity up to 300 MW (RWE Innogy with 26.7% share) > 29 km off Belgian coast in around 20 m water depth (service port: Oostende) > To be equipped with 60 REpower turbines of 5 MW class > First six turbines with 5 MW capacity each already installed by June 2009 (market leading warranty package) – another four project phases due to follow by 2013 > Around 1,000 GWh annual electricity generation (equals
> Gravity base foundations – concrete basis, constructed on land, floated to sea and filled with sand to secure
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 28
>
Sub location of Tromp (red area)
>
295 MW capacity (59 turbines with 5 MW capacity each)
>
Size of 33 km2
>
Cable distance to shore 75 km
>
Water depth 21 – 31 m
>
Consent received in November 2009
>
Construction planned to commence in 2012/2013 – fully operational in 2015
>
Soil type (fine-medium w. sand, slip sand); Foundation: Gravity
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 29
>
Located 14 km from North Devon and 18 km South Wales
>
Maximum capacity 1, 500 MW (250 x 6 MW turbines)
>
Consent programmed for Q1 2013
>
Grid connection secured in North Devon
>
Overall area size of 333 km2
>
Water depth 29 - 53 m
>
Wind speed of 9.6 m/s
>
RWE Innogy is sole developer - opportunity to partner at consent or sooner with Crown Estate consent
RWE Innogy | Nomura Offshore Wind Seminar 22 January 2010 PAGE 30
>
UK Round 3 site development by Forewind consortium (RWE Innogy, SSE, Statoil and Statkraft with 25% each)
>
Development of 9,000 MW capacity
capacity 12,000 MW)
>
Zone development plan: four tranches
>
Consent from 2013 onwards
>
First turbine installation planned for 2017 at the earliest
>
Distance to shore 125 km
>
Overall area size of 8,640 km2
>
Water depth 18 - 50 m
>
Wind speed of 10.2 m/s