observations from the instrumentation of a micropiled and
play

Observations From The Instrumentation of a Micropiled and Tied Back - PowerPoint PPT Presentation

Observations From The Instrumentation of a Micropiled and Tied Back Reticulated Grid Walter E. Vanderpool, P.E. Senior Geotechnical Engineer Terracon Consultants, Inc. Site: The C2K Theatre at the Palazzo 370 kN wall load at the


  1. Observations From The Instrumentation of a Micropiled and Tied Back Reticulated Grid Walter E. Vanderpool, P.E. Senior Geotechnical Engineer Terracon Consultants, Inc.

  2. � Site: The C2K Theatre at the Palazzo � 370 kN wall load at the crest of a 15.3 m excavation � Theatre construction concurrent with excavation and tower construction

  3. � Site excavation began 9/1/04 � Theatre construction began 11/25/04 � Secant pile installation began 12/6/04 � Underpinning installed 12/11/04 � Secant piling complete 12/16/04 � Theatre structure frame complete 3/14/05

  4. 40 N 35 30 Northing (m) 25 20 15 Secant Piles Micropiles Bonded Tie Back VW Strain Gauge 10 Inclinometer Piezometer 5 Tower shafts 0 0 5 10 15 20 25 30 35 40 45 50 55 60 65 Easting (m) • Reticulated group plan • Tieback locations • VW gauge locations • Foundation shafts for cantilevered tower • Micropile locations

  5. 635 Secant Piles Viewing West FF 631.5 m VW Strain Gauge 630 Inclinometer Bonded Tie Back 625 Mat Caliche Layers Elevation (m MSL) Micropiles 620 SG 616.2 m Piezometer 615 610 605 15 20 25 30 35 40 45 50 55 60 Northing (m) • Reticulated group profile • Reticulated tieback intersections • VW gauge locations • Cemented beds • Micropile locations • Piezometer location • Tieback locations

  6. 632 Micropile, Relative Drilling Resistance, 1=very soft/loose, 3=very stiff/very dense and partially cemented, 630 5=strongly cemented 629.4 m MSL 628 626 Elevation (m MSL) 624 622 620 618 616 614 Relative Drilling Resistance, count=103 612 0 1 2 3 4 5 Drilling Resistance Rating • Relative top-drive hammer drilling resistance • Measured by rate of advance • Subjectively interpreted relative to geotechnical logging

  7. � Flush grout injection drilling � VW strain gauge � Insertion by fiberglass rod

  8. � Inclinometer at P1-015NS � Piezometer at P1-013S � Cemented layer at approximately elevation 626.5 m to 625 m MSL

  9. � Notch at tower cantilever � Theatre wall 36.3 m - wide by 32 m - high by 457mm - thick � Carbonate precipitate at tie- backs

  10. � Tower shaft group at cantilever

  11. 2250 2000 1750 M6, 6 1500 1250 1000 750 M8, 2 Gauge Microstrain Mat 500 Theatre M4, 10 M1,5 Fill Construction 250 M4, 17 Placed 0 -250 M4,17 -500 M2, 8 Curing -750 M1, 11 -1000 12/4/2004 0:00 1/29/2005 0:00 3/26/2005 0:00 5/21/2005 0:00 7/16/2005 0:00 9/10/2005 0:00 11/5/2005 0:00 12/31/2005 0:00 Date & Time • Micropile strain history • Installation 12/04 through completion 1/06 • VW strain gauge data record

  12. 60 40 Mat Placed 20 0 -20 Wall Construction Mat Fill Placed -40 M6, 6 -60 Gauge Microstrain -80 (see Figure 10) M4,17 -100 M1, 5 -120 M4, 17 M1, 11 -140 Grout Curing (see Figure 9) -160 M2, 8 -180 M8, 2 -200 12/9/2004 0:00 12/23/2004 0:00 1/6/2005 0:00 1/20/2005 0:00 2/3/2005 0:00 2/17/2005 0:00 3/3/2005 0:00 3/17/2005 0:00 3/31/2005 0:00 4/14/2005 0:00 Date & Time • Initial tension during curing and • Theatre construction excavation to subgrade 1/05 – 3/05 12/11/04 – 12/18/04 • Fill placement • Mat placement 12/24 3/14/05 – 3/20/05

  13. -66 -67 -68 -69 Gauge Microstrain -70 -71 M4, 17 -72 2/9/2005 18:00 2/10/2005 6:00 2/10/2005 18:00 2/11/2005 6:00 2/11/2005 18:00 2/12/2005 6:00 Date & Time • Forming and concrete placement load/unload at interior location on mat

  14. 110 105 100 Gauge Microstrain 95 M2, 8 90 5/19/2005 5:00 5/19/2005 7:00 5/19/2005 9:00 5/19/2005 11:00 5/19/2005 13:00 5/19/2005 15:00 Date & Time • Tieback stressing effects • 15 Tiebacks at Level -1 stressed

  15. • Hourly data by IPI • Inclinometer data record system 8/05 – 12/05 • Weekly record 4/05 to 8/05 and 2/06 not included

  16. 634 Secant Pile P1- 013,S F. F. 631.5 m 632 O. G. 630.3 m 630 628 626 Groundwater head (m) 624 622 Tieback Grouting 620 (see Figure 14) 618 S. G. 616.2 m 616 614 612 610 Shaft Drilling Head (m MSL) 608 11/9/2004 1/4/2005 3/1/2005 4/26/2005 6/21/2005 8/16/2005 10/11/2005 12/6/2005 0:00 0:00 0:00 0:00 0:00 0:00 0:00 0:00 Date and Time • Head rise during tieback grouting • Piezometer data record • Head drop during drilled shaft 12/04 – 1/06 construction

  17. 620.0 Secant Pile P1- 013, S 619.5 619.0 618.5 Groundwater head (m MSL) 618.0 617.5 617.0 616.5 616.0 615.5 Head (m MSL) 615.0 7/1/2005 11:00 7/1/2005 12:00 7/1/2005 13:00 7/1/2005 14:00 7/1/2005 15:00 7/1/2005 16:00 7/1/2005 17:00 Date and Time • Tieback grout placement at Level – 2

  18. Elastic Analyses vs. Observations 0 M6,6 Secant pile tip elevation -50 610.1 m MSL M4,17 Excavation subgrade M1,11 M8,2 M6,6 616.2 m MSL M2,8 Vertical Stress (kPa) -100 M1,5 Embedded strain M2,8 gauge depths (D/B) M4,17 Line 1 Line 22 M8,2 36.3 m -150 Row M1 14.8 m B=10.1 m -200 M5,1 30.8 m Row 4.9 m M8 M1,17 PLAN (sketch) 2.7 m 2.7 m -250 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 Depth (D/B) - D/B 0=629.3 m MSL, D/B 2=609.1 m MSL • Boussinesq elastic analyses by superposition • Instrumented micropile locations and depths

  19. Ground/Micropile Load Sharing Pre-Excavation, April 1, 2004 D/L D/B 4/1/05 Boussinesq Tributary Stress Location Load Stress (kPa) Area Ratio % (kN) (m^2) M1,5 0.30 0.5 -41.08 -67.5 1.62 37.6 % M1,11 0.66 1.1 -52.41 -36.7 1.62 88.3 % M1,17 0.30 0.5 -55.05 -58.7 1.62 50.9 % � 37.6% to 88.3% M5,1 0.57 0.8 -42.62 -43.2 1.96 50.4 % at perimeter � 5.6% to 73.2% at 1 st interior row N2,2 0.66 1.1 -50.32 -34.0 2.02 73.2 % M2,8 0.30 0.5 -14.02 -67.4 3.70 5.6 % � 10.9% to 11.8% M2,14 0.30 0.5 -69.93 -67.3 3.70 28.1 % near middle of M2,20 0.30 0.5 -50.00 -72.0 4.18 16.6 % mat (row 4) M8,2 0.47 0.5 -64.71 -50.9 2.70 47.0 % � 17.1% at back edge of mat M4,10 0.60 0.8 -26.55 -43.3 5.64 10.9 % (row 6) M4,17 0.37 0.5 -32.94 -49.4 5.64 11.8 % � Prior to stressing M6,6 0.58 0.8 -30.26 -33.4 5.62 17.1 %

  20. Ground/Micropile Load Sharing Post Construction January 31, 2006 D/L D/B 1/31/06 Boussinesq Tributary Stress Location Load Stress (kPa) Area Ratio % (kN) (m^2) M1,5 0.30 0.5 -22.77 -67.5 1.62 20.8 % � After tieback M1,11 0.66 1.1 -68.56 -36.7 1.62 115.5 % stressing M1,17 0.30 0.5 -25.22 -58.7 1.62 26.6 % � 20.8% to 115.5% M5,1 0.57 0.8 -56.18 -43.2 1.96 66.4 % at perimeter � 6.7% to 184% N2,2 0.66 1.1 -59.43 -34.0 2.02 86.1 (tension) at 1 st M2,8 0.30 0.5 -16.60 -67.4 3.70 6.7 % M2,14 0.30 0.5 -198.27 -67.3 3.70 79.6 % interior row M2,20 0.30 0.5 -87.14 -72.0 4.18 29.0 % � 11.4% to 83.0% M8,2 0.47 0.5 252.84 -50.9 2.70 184 % * (tension) near middle of mat M4,10 0.60 0.8 201.22 -43.3 5.64 83.0 %* (row 4) M4,17 0.37 0.5 -31.71 -49.4 5.64 11.4 % � 139.5% (tension) at back of mat M6,6 0.58 0.8 261.76 -33.4 5.62 139.5 %* (row 6)

  21. CONCLUSIONS � The micropiles accumulated 10 to 90 percent of the load as it was applied in proportion to the relative stiffness between the soils and the micropiles. � Instrumented micropiles responded with strains consistent with their location within the group and the forces applied. � The micropiles provided confinement and resistance to axial deformation during tieback stressing. � Tie back stressing caused micropiles to act in tension at the tieback bond zone.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend