western bay of plenty district council
play

Western Bay of Plenty District Council Te Puna West Wastewater - PowerPoint PPT Presentation

Western Bay of Plenty District Council Te Puna West Wastewater Community Meetings 21 22 April 2015 PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU Reticulation Options Assessed Reticulation of all properties in Te Puna West to


  1. Western Bay of Plenty District Council Te Puna West Wastewater Community Meetings 21 – 22 April 2015 PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  2. Reticulation Options Assessed • Reticulation of all properties in Te Puna West to Omokoroa Transfer Pipeline • Reticulation of all properties in Te Puna West and construction of a new treatment plant • Partial reticulation for properties that cannot comply with OSET plan and construction of a new treatment plant • Upgrade of all septic tanks to AWTS units and the construction of a centralised disposal field to take the treated waste PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  3. Preferred Reticulation Option • Reticulate all properties within the Te Puna West reticulation zone • Each property will have a grinder pump onsite • Wastewater will be pumped to ‘Omokoroa transfer pipeline’ • Wastewater is treated and disposed of at Tauranga City Council’s wastewater treatment plant (Chapel Street) PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  4. Area to be reticulated PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  5. Omokoroa Transfer Pipeline PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  6. Grinder Pump PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  7. Total Scheme Cost (including GST) Total Cost Onsite Property Cost (grinder pump, electrical, $1,669,800 drain laying, boundary connection etc.) Financial Contribution (to Omokoroa Pipe Line) $673,992 Scheme Cost – Reticulation and pump station $1,973,400 Total $4,317,192 PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  8. Proposed Funding Model (including GST) Land owner cost - Onsite Costs $11,500 - $13,800 - Financial Contribution $5,106 _____________________________________________ Total land owner cost $16,606 - $18,906 PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  9. Proposed Funding Model District Wide Uniform Annual Charge • Annual charge to each property • Based on current rates model (2016/2017) - $851 • Will cover: – Scheme Costs; $13,800 - $16,100 per property – Operational Costs; maintenance of pumps, pumping to Omokoroa transfer pipeline, disposal costs to Tauranga City Council PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  10. Grinder Pump Ownership and Maintenance Property owner funds and owns the grinder pump unit. Owner maintains unit. Property owner funds grinder pump and transfers it to Council. Unit maintained as scheme costs – (covered by the UAC.) Owner pays for the power in both cases Non-standard units – no transfer to Council PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  11. Expected Timeframes • By 30 April submissions to Councils draft LTP requesting Council proceed with Te Puna West community wastewater scheme • By Friday 1 st May – Feedback form returned to Council • By December 2015 – property owner commitment to proceed, formal Council approval, design detail and final estimate • 2016/2017 – scheme construction PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  12. Please remember to return your feedback forms to Western Bay of Plenty District Council by Friday the 1 st May. PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

  13. Questions? PEOPLE PLAN PROGRESS TE KAUNI HERA O TE HAUAURU

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend