www.centennialcoal.com.au
Newstan Colliery CCC Presentation 28 th February 2012 - - PowerPoint PPT Presentation
Newstan Colliery CCC Presentation 28 th February 2012 - - PowerPoint PPT Presentation
Newstan Colliery CCC Presentation 28 th February 2012 www.centennialcoal.com.au Operation Update www.centennialcoal.com.au Project Execution 2 nd Continuous Miner (CM) commenced in the Main West panel in December (joins 1 st CM in South
www.centennialcoal.com.au
Operation Update
Project Execution
- 2nd Continuous Miner (CM) commenced in the
Main West panel in December (joins 1st CM in South West panel).
- 3rd panel in Main East to commence approx May
2012.
- 7 day operation for underground approx May
2012.
- Manning has and will increase to match
aforementioned changes.
- Further Projected Execution elements ongoing.
3
Mine Plan
4
Working Area Plan
5
www.centennialcoal.com.au
Project Update
Main West Modification
7
- Environmental Assessment submitted in June
2011
- Final Response to Submissions provided in
December 2011
- Draft consent conditions received February 2012
- Approval from the Planning and Assessment
Commission to be received.
Subsidence Management Plan (SMP) Application
8
- Newstan has recommenced mining within the boundary of the existing
development consent (DA 73-11-98).
- A Subsidence Management Plan (SMP) is required for initial longwalls
to be submitted to the NSW Trade and Investment for approval.
- Environmental, infrastructure and subsidence assessments are
progressing.
- Anticipate submission of SMP application in May 2012. SMP
application required to be advertised.
- Consultation with land and infrastructure owners has been
progressing.
Newstan Project - Background
9
- Newstan Colliery – Care and Maintenance in 2009
- Exploration drilling programme commenced in 2008 within the southern areas of Newstan’s
mining and exploration leases – completed drilling in 2011
- Internal pre-feasibility and feasibility investigations have occurred
- Lodged a Preliminary Environmental Assessment in April 2008. The Part 3A has been
scrapped and this document is no longer valid.
- Newstan Project now split into two separate projects:
– Newstan Colliery (Newstan) – Extension of Mining Project – Northern Coal Services (NCS) – Coal Logistics Project
- Request for Environmental Assessment Requirements (EARs also known as DGRs) made
Jan 2012. Briefing Papers submitted Feb 2012
Newstan Extension of Mining Project
10
- Expand the underground mining operations utilising a combination
continuous miner and longwall mining methods.
- Extract up to 4.5 Mtpa (Currently approved to extract 4 Mtpa, an
increase of 0.5 Mt to cater for spikes in some years of production plan).
- Utilise and upgrade the existing surface infrastructure of the Newstan
and Awaba Collieries.
- Construct a new Men and Materials drift at the Awaba Colliery
Surface Site.
- Increase manning to 350 employees (Currently approved for 320
employees)
Newstan Extension of Mining Project
11
- Install and operate additional surface infrastructure for gas drainage, greenhouse gas
capture and abatement, ventilation, support buildings, electrical reticulation, water reticulation, water management, communications and other services;
- Continue to operate the underground water management systems of both the
Newstan and Awaba Collieries;
- Operate the Awaba Colliery surface water management system including all existing
discharge points;
- Ability to transfer water between the Newstan Colliery, Awaba Colliery and Mandalong
Mine water management system (currently options being investigated for a regional solution to manage water);
- Continue to utilise the existing ‘ballast borehole’ site and services compound at
Awaba; and
- Undertake ongoing exploration drilling activities.
- NOTE: Surface water management, noise and air quality issues at the Newstan
Colliery Surface Site will be addressed in the Coal Logistics Project EIS.
NCS Coal Logistics Project
12
- Upgrade the surface infrastructure at Newstan to enable the ability to
handle and process of up to 8 Mtpa through the CPP (Washery) and Product Handling Facility (Currently approved to process 4 Mtpa);
- Ability to transport up to 8 Mtpa of coal from the Newstan Product
Handling Facility through the Newstan Colliery rail loading facilities by train to the Port of Newcastle or Port Kembla (Currently approved to export 3 Mtpa);
- Based on current and expected future contracts, the current plans are;
– The Washery will be upgraded from its current capacity of 4Mtpa ROM to 6Mtpa ROM – The Product Handling Facility will be upgraded from 3Mtpa to 8Mtpa capacity (this currently consist of both train handling for around 5Mtpa export and truck handling for around 3Mtpa domestic). – This may alter if contracts change.
NCS Coal Logistics Project
13
- Increase the coal stockpile capacity at the Newstan Colliery Surface Site;
- Operate coal handling facilities at Cooranbong;
- Transport reject material to the Newstan reject areas or the LMCC owned Hawkmount
Quarry via private haul roads;
- Construct and operate a coal crushing facility at the Mandalong Mine - Cooranbong
Entry Site that has previously been approved but not yet constructed;
- Manage surface water at the Newstan Colliery Surface Site, the Mandalong Mine –
Cooranbong Entry Site, the Mandalong Mine private haul and the LMCC owned Hawkmount Quarry;
- Transfer water between the Newstan Colliery, the Awaba Colliery, the Hawkmount
Quarry and the Mandalong Mine water management system;
- Undertake locomotive refuelling and servicing on site;
- Continue the construction of the Newstan Southern Reject Area to RL60;
- Provide employment for up to 100 personnel
Consultation to date
14
- Briefing Papers distributed to CCC members and
relevant government agencies.
- Landowners within potential subsidence areas
notified of Project.
- Ongoing consultation with Newstan CCC
- Ongoing consultation with relevant Aboriginal
groups
- Ongoing consultation with landowners,
infrastructure owners and relevant government departments.
EIS Process
15
- Detailed investigations for both Projects will be required and will
include:
– Subsidence assessments – Infrastructure impact assessments – Ecology assessments – Heritage assessments (European and Aboriginal) – GHG, air and noise assessments – Surface water and groundwater assessments – Social and economic assessments – Traffic assessments
- As part of the EIS we will assess all possible risks. Risks are
identified through consultation with government and stakeholders. Centennial will work with consultants to determine were identified risks can be avoided, minimised or mitigated.
www.centennialcoal.com.au
Water Management
Newstan By-Wash Dam
Water Management
Centennial Coal’s Newstan mine has more than 130years of history. With this history comes the challenge of ensuring practises of the past, which were once acceptable, are replaced with the highest environmental standards. Over many years Newstan has worked diligently with the EPA in order to achieve this. However, at times the solutions that best deliver positive environmental
- utcomes for Newstan are frustrated by the regulatory regime it works
under and lengthy approval timelines. Centennial’s Newstan mine has committed significant financial resources to minimising current and future risks of pollution incidents.
17
Water Management
Below are some examples of these activities.
– Undertaken a complete review of the way water is managed at Newstan – Increased the separation of clean and dirty water at Newstan – Increased the capacity of surface water storages at Newstan – Consulted with the EPA to seek an increase in the volume of water discharged from Newstan through regulated and monitored control points – Investigating and committing to the installation of a Clean Water Plant at Newstan to treat all water discharged from the mine.
Centennial Coal is committed to the highest environmental standards and will continue to work with the EPA to ensure Newstan continues to deliver a positive economic, social and environmental contribution to the local community.
18
Final Pollution Control Dam Expansion
- Newstan commenced the expansion of the FPCD (on left as you exit site)
from 16ML to 50ML in April 2011, with the expansion scheduled to be completed by April 2012 (depending on weather)
- Once completed the expanded dam will reduce the likelihood of dirty water
discharges to LT Creek from LDP002.
19
SREA Clean Water Diversion Drain
20
Completed diversion drain Diversion drain following a rain event
www.centennialcoal.com.au
Noise Management
22
New Locomotive Trial – January 2011
Centennial is purchasing new quieter trains. It should only require 3 trains to haul loads rather than the current 6.
Proposed Noise Bund Wall at Rail Loop
23
Proposed Noise Cladding of the Washery
24
www.centennialcoal.com.au
Sponsorships & Donations
Our sponsorship ethos
26
Local Sponsorships:
- Centennial views sponsorships as an investment in the communities
where we do business. We support:
- ‘grass-roots’ community based organisations in the areas in which we
- perate with a priority on those activities which promote community
engagement by our workforce
- local parochialism (western side of Lake Macquarie)
- We don’t support cheque book diplomacy.
27
Our community activities and support
Sporting activities and organisations Education Cultural festivals Community
- rganisations
The process
Step one
- Community group submits sponsorship proposal to
Centennial Coal
Step two
- Consultation between Centennial’s relevant
- peration and External Affairs
Step three
- Level of support is agreed, consultation with the
community organisation begins
Step four
- Centennial works with the community organisation
to deliver the agreed level of support
28
Voluntary Planning Agreements (VPA)
- A VPA forms part of the conditions of consent when the Department of Planning
grants an approval for a project. The project proponent may/must enter into a VPA with the Local Government Area in which its project is proposed. How the VPA is structured will be negotiated between the Proponent and the Council and will have a clear link between the project and its potential impacts on the local area.
- In the case of a project like the Newstan Lochiel Project, Lake Macquarie City Council
would negotiate with Centennial Coal and both parties will agree on the terms of the VPA.
- The NSW Government is currently reviewing the VPA process to ensure there is a
transparent and consistent approach to avoid any perceived conflicts of interest. An
- utcome to this review is expected in the second half of this year.
- As a member of the community or a community group now is the time to start
identifying local projects that could be a beneficiary of a VPA and work with the Council to gain community consensus. This will ensure, for example, projects linked to LT Creek are recognised as a high priority by Council and are supported by the community and could therefore benefit from any future VPA.
29
- Below is an example of the most recent VPA Centennial Coal
negotiated with Mid-western Regional Council for a continuation of mining project at the Charbon Colliery located near Rylstone and Kandos.
- Charbon’s 2010 Voluntary Planning Agreement:
– $210k contribution toward the Carwell Creek Bridge (paid August 2011) – $50k community facilities contribution (one off payment) – $0.01 per ROM tonne per annum – annual community payment (approx. $12k annually) – the above 2 payments can only be used in the Rylstone, Kandos, Clandulla and Charbon communities – $75k road maintenance bond
30
Voluntary Planning Agreements (VPA)
Newstan Community Hotline Newstan Community Hotline 1800 247 662
31