www.centennialcoal.com.au
Committee Environment and Community Update 9 th March 2015 - - PowerPoint PPT Presentation
Committee Environment and Community Update 9 th March 2015 - - PowerPoint PPT Presentation
Charbon Community Consultative Committee Environment and Community Update 9 th March 2015 www.centennialcoal.com.au Websites Centennial Coal Home Page http://centennialcoal.com.au/ Charbon Environment Page
Websites
- Centennial Coal Home Page
– http://centennialcoal.com.au/
- Charbon Environment Page
– http://centennialcoal.com.au/Environment/Charbon.aspx
2
Water Management
- 6 Licenced Discharge Points (LDPs):
– Require frequent inspections & sampling during discharge; – Submitted application to EPA September 2013 to add 3 new LDPs to EPL 528;
- Charbon required to undertake additional water quality monitoring & submit to EPA;
- November 2014 received a revised EPL with 3 additional LDPs.
- Since last CCC meeting (15/09/2014 – 09/03/2015) ≈ 450 mm rainfall
- [Long-term annual average ≈ 684 mm – from BoM station at Rylstone;
- 4 Exceedances of EPL528 for TSS & Turbidity from LDP003 & LDP005.
Exceedances covered by Condition L2.5 of EPL528; all other conditions were below license limits.
3
LDP002 LDP003 LDP004 LDP005 LDP006 Discharges: 5 6 1 30 1 Exceedances: 0 2 2
Water Management
4
LDP002 & LDP003
5
- LDP002:
- OC & UG workshops;
- 8-Trunk stockpile area;
- LDP003:
- SOC;
- 8-Trunk OC;
- “Roche Pad” stockpile
area;
- LDP004:
- CHPP
- LDP005:
- 2/3 Trunk Coal Handling
Area
- LDP006:
- Haystack
LDP002
Results:
- pH (6.5-8.5):
Min: 7.6 Max: 8.4
- TSS (50mg/L):
Min: 2 Max: 16
- Turbidity (50NTU):
Min: 2 Max: 29.1
- Oil & Grease (10mg/L): <2
LDP003
Results:
- pH (6.5-8.5):
Min: 7.3 Max: 7.6
- TSS (50mg/L):
Min: 2 Max: 182
- Turbidity (50NTU):
Min: 3.7 Max: 489
- Oil & Grease (10mg/L): <2
LDP004
Results:
- pH (6.5-8.5):
8
- TSS (50mg/L):
4
- Turbidity (50NTU):
2.2
- Oil & Grease (10mg/L): <2
LDP005
12 Sep 2014
Results:
- pH (6.5-8.5):
Min: 7.2 Max: 7.9
- TSS (50mg/L):
Min: <2 Max: 128
- Turbidity (50NTU):
Min: 2.4 Max: 607
- Oil & Grease (10mg/L): <2
LDP006
Results:
- pH (6.5-8.5):
7.6
- TSS (50mg/L):
11
- Turbidity (50NTU):
7.9
- Oil & Grease (10mg/L): <2
Environmental Management
- Monitoring: data for dust has shown that the mine has been in
compliance consistently for > 12 months:
- HVAS 2014 – 2015 (to date): *Compliant.
- Depositional Dust 2014: *Compliant
- 2x depositional dust exceedances (Feb & Apr) due to contamination by organic matter;
- 1x depositional dust exceedance (May) due to contamination – deemed to be non-
mining related. In any case, location where DDG located is on property with whom Charbon holds a negotiated agreement which removes limits including dust.
- All 2015 results to date have been in compliance.
- Dust PRP: *Now Complete
- Condition U3 Report Submitted to EPA on 14 April 2014;
- Comments received from EPA on 13 June 2014; a report addressing these was
submitted on 30 July 2014;
- Condition U1 & U2 Reports Submitted to EPA on 15 August 2014.
11
Depositional Dust – 2014 Results
12
Dust – HVAS 2014 Results
13
Environmental Management
- Noise Management:
– Quarterly noise monitoring conducted during December 2014, March 2015 showed the mine to be in compliance; – Minimal operation occuring onsite during December 2014 monitoring. – Implemented new noise mitigation strategy for the Southern and Western Outlier mining areas.
- Reduced Equipment Fleet, Operations dictated by weather conditions.
– 2 x Noise complaints received on the 17th and 18th February 2015. EPA monitored at affected residence and results were below the noise criteria of
- 35dB. Charbon was compliant with 2010 Consent Conditions and as such no
further action was required. Charbon will continue to adopt the noise mitigation strategies to maintain compliance and best practice.
14
Environmental Management
- Reporting to Corporate, State & Federal Governments:
– Website data uploaded within 14 days of start of month; – Dust PRP Reports to satisfy Conditions U1, U2 and U3 of EPL 528, submitted to EPA; – AEMR due 31st March 2015. – MOP/Closure Plan due 29th May 2015 (DRE). – Consent modification underway (DPE).
15
Environmental Management
- Subsidence management – on-going;
- Land management, including:
– Seeding of Southern Open-cut rehabilitation - October 2014; – Weed Spraying (2015 - extensive program)
- Review of Site Management Plans, on-going;
- EPBC Approval Conditions – on-site Compensatory Habitat;
– Positive Covenant placed over on-site Compensatory Habitat Areas; – Gifting process to NSW NPWS as a SCA *Finalised Dec 2014;
16
Rehabilitation
17
- Planned 2015 Rehab – Blue;
- Western outlier has had bulk
refilling of mine void with
- verburden;
- Requires further shaping and
cover with clay and top-soil;
On-going Rehab. of SOC
18
October 2015
On-going Rehab. of SOC
Q4 2012
On-going Rehab. of SOC
June 2013
On-going Rehab. of SOC
May 2014
On-going Rehab. of SOC
September 2014
On-going Rehab. of SOC
September 2014
On-going Rehab. of SOC
24
8th March 2015
On-going Rehab. of SOC
25
Past Rehab. Areas
2 6 2 1 4
Future Rehab. Challenges
27
- Since last CCC meeting there has been two (2) complaints.
Sponsorship
- Various community groups, facilities and events, including:
– Charity Golf days; – Kandos Gardens Fair; – Kandos/Rylstone Show (major sponsor); – Kandos Street Machine; – Local schools and sporting clubs; – Men's Shed; – Rylstone Street-feast 2014; – Rylstone/Kandos Show; – UNSW Engineering Scholarship.
Partnerships
- Central Tablelands Local Land Services (formally HNCMA);
- Lithgow Community Nursery
28
Community
Questions?
29