www.centennialcoal.com.au
Newstan Colliery – CCC Presentation
15th August 2019
Newstan Colliery CCC Presentation 15 th August 2019 - - PowerPoint PPT Presentation
Newstan Colliery CCC Presentation 15 th August 2019 www.centennialcoal.com.au Awaba Environment & Community Update March 2019 August 2019 www.centennialcoal.com.au Introduction Awaba Colliery Wilton Road , Awaba. Regulatory
www.centennialcoal.com.au
15th August 2019
www.centennialcoal.com.au
March 2019 – August 2019
Introduction
Awaba Colliery – Wilton Road , Awaba. Awaba Colliery Part 3A approval was converted to a State Significant Development Consent. This occurred in November and there are no implications to the operation as a result of this transition.
3
Regulatory Instrument Change Project Approval 10_0038 No Environment Protection Licence 443 No CCL746 No MPL 327 No MPL 328 No
Awaba Environmental Monitoring
than 4.0 g/m2/month during the reporting period.
4
Awaba Environmental Management
5
to the requirements of the EPA Clean-Up Notice (Awaba Seepage) received in April 2016:
Centennial and the EPA are still working towards a final outcome and Centennial is responding to the EPA’s request for further information.
Summary of Compliance
meeting.
6
Additional Bollards at Freemans Drive
7
Additional bollards and cabling have been installed on Freemans Drive to help deter access.
Awaba Solar Panel Project
Development Consent for the installation of 200kw of portable solar panels on the Awaba hardstand area.
solar for installation of a stage 1, 100kW system.
for approval to connect to the power supply.
8
www.centennialcoal.com.au
March 2019 – August 2019
Introduction
Newstan Colliery – Miller Road , Fassifern.
10
Regulatory Instrument Change Development Consent DA 73-11-98 MOD8 No Development Consent SSD5145 No Environment Protection Licence 395 No CCL746 No CCL727 No MPL 327 No MPL 328 No
Newstan on Care & Maintenance
Continued with care and maintenance activities, focused on maintaining the mine infrastructure and keeping the mine safe.
– Focus on underground roof support maintenance. – Repairing roads. – Maintaining and improving dewatering infrastructure. – Improving the quality of goaf seals.
11
www.centennialcoal.com.au
March 2019 – August 2019
Project Overview
3
– Bord and pillar mining using combination of first workings, partial and total extraction – Extraction of up to 4 Mtpa over a 15 year mine life. – In-seam gas drainage with captured gas transferred to a gas flaring facility at the Awaba Colliery Surface Site – Men and materials access from the Newstan Colliery Surface site – Utilisation of ventilation shafts at the Newstan Colliery Surface Site and Awaba Colliery Surface Site – Operational workforce of up to 320 personnel – Peak construction workforce of up to 50 personnel
Note operational implementation may result in less than approved limits identified above
Project Area
14
Significant resources remain to the south and east of our proposed mining area
Mine Design
1
environmental features
extraction adopted to minimise subsidence impacts enabling adaptive management strategies to be implemented as mining progresses
associated with the Awaba workings in the overlying Great Northern seam
Mining Zones
16
Surface Infrastructure
1
Colliery Surface Site
biodiversity offset costs
proposed mining area and close to existing ventilation infrastructure
Awaba Surface Site
18
Approval Process
5
WE ARE HERE
Environmental Assessments
6
area and determine the condition
– Subsidence – Groundwater and surface water – Terrestrial and aquatic ecology – Air quality and greenhouse gas – Noise and vibration – Traffic and transport – Aboriginal and historic heritage – Visual – Socio-economic
Environmental Impact Statement
7
mitigation, management, monitoring and offset measures will be identified to enhance the project’s benefits and address any impacts
www.centennialcoal.com.au
March 2019 – August 2019
Newstan Environmental Monitoring
(limit of 711mg/l).
4.0 g/m2/month during the reporting period.
Development Consent criteria during the reporting period.
There were no exceedances of the Development Consent noise limit criteria.
23
Summary of Compliance
meeting.
relation to noise exceedances in Q2 2018.
– 1 x PIN received for exceedance of noise criteria – 1 x PIN received for the real time noise monitor not providing consistently reliable results
Unit to ensure compliance with the Development Consent requirements.
24
Southern Rejects Emplacement Area
holding fine rejects.
facilities we operate
coal from Centennial’s Mandalong mine
reject management plan. This occurs under strict environmental conditions and subject to various planning and environmental
years and will be capped and rehabilitated to natural landform once it reaches its maximum design capacity.
25
Southern Rejects Emplacement Area
effective management of tailings. The area is being filled and progressively shaped, capped and revegetated to a natural state.
and course reject from Centennial’s Lake Macquarie operations. It was designed by external consultants who have particular expertise in the design and management of reject storage facilities.
26
Photos of SREA from Dave Baker to be included in this slide and the following slide.
SREA - Technical
meeting all government requirements.
regularly inspect the SREA to ensure the site is managed safely and all regulatory conditions are met.
monitor and identify any changes to the dam wall and surrounds.
27
SREA – is safe
tailings and coarse reject from Centennial’s Lake Macquarie operations. Reject has been managed at the Newstan site since 1950’s, nearly 70 years ago.
Act (NSW), and as such, is subject to additional external scrutiny and audit by regulators.
28
www.centennialcoal.com.au
Newstan Pumped Hydro Storage Project CCC Update
File Name: Banpu Introduction to CMPHES
15 August 2019
Why does the NSW Government want pumped hydro?
Source:
Where does Pumped Storage fit in
Source:
What is Pumped Hydro
32
the top of a hill it can store energy
be passed through a turbine to produce electricity
a dam at the bottom of the hill, it can be pumped back up the hill again to create stored energy for use at a later time
hydro energy storage (PHES)
NSW future energy generation and transmission
Pumped Storage 9GW
What is Newstan Colliery proposing - CMPHES
34
electricity
What is the current status, next steps and timing Current status
Program (NSW EEP) for funding to assist progress the concept of an 8.5 MW Coal Mine Pumped Hydro Energy Storage System (CMPHES)
initiatives to support an orderly transition to a clean, reliable and affordable energy future.
Renewable Energy technologies
What is the current status, next steps and timing Next Steps and timing
financial feasibility assessment
Approval application would commence including formal consultation with relevant stakeholders