wapp erera forum dakar presented by babatunde adeyemo
play

WAPP ERERA Forum Dakar Presented by : Babatunde Adeyemo Director - PowerPoint PPT Presentation

WAPP ERERA Forum Dakar Presented by : Babatunde Adeyemo Director ICC POWER SUPPLY SITUATION MEGAWATTS 1,000 2,000 3,000 4,000 5,000 6,000 7,000 Installed capacity Electricity Supply in West Africa 0 BENIN BURKINA FASO COTE D'IVOIRE


  1. WAPP ERERA Forum Dakar Presented by : Babatunde Adeyemo Director ICC

  2. POWER SUPPLY SITUATION

  3. MEGAWATTS 1,000 2,000 3,000 4,000 5,000 6,000 7,000 Installed capacity Electricity Supply in West Africa 0 BENIN BURKINA FASO COTE D'IVOIRE THE GAMBIA GHANA Average capacity available GUINEA GUINEA-BISSAU LIBERIA MALI NIGER NIGERIA SENEGAL SIERRA LEONE TOGO

  4. Status of Power Supply in ECOWAS 2 : Supply Sources 2 Import + Others Hydro 5% Thermal 31% GWh 64% 40,000 30,000 20,000 Thermal Import + Others Hydro 10,000 - Burkina Faso Gambia Ghana Liberia Mali Togo Benin Guinea Guinea Bissau Nigeria Senegal Cote d'Ivoire Sierra Leone

  5. Status of Power Supply in ECOWAS 3 : Demand-Supply Balance GWh Met Unmet 54% 46% 50,000 40,000 30,000 Met 38,370 20,000 Unmet 10,000 7,773 3,004 1,800 661 688 860 841 674 170 16 16 56 - Cote d'Ivoire Burkina Faso Liberia Mali Nigeria Senegal Sierra Leone Togo Benin Gambia Ghana Guinea Guinea Bissau

  6. Status of Power Supply in ECOWAS 4 : Causes of Shortages  Technical Causes  Obsolete & unreliable equipment; Inadequate maintenance; Operations inefficiencies; Insufficient Capacity; and, Non-availability of primary energy sources.  Financial Factors  Low user tariffs; Low collection rates; and, Inadequate financial standing of utilities.  Institutional Issues  Planning & implementation responsibility; Bureaucracy in decision-making; Sensitivity of tariffs to low income/wage levels; and, volatile petroleum prices limiting fuel purchases.

  7. Criteria for Viable Regional Options  Economic Consideration:  A viable sub-regional supply option must be economically cost competitive (lower cost) when compared with local alternatives

  8. Prevailing Situation  Inadequate/Non Existent Transmission Interconnections in ECOWAS Member States and also between ECOWAS Member States;  Inadequate Generation Capacity in ECOWAS Member States resulting in Power Shortages;  Inability of ECOWAS Member States to raise the necessary financing to implement the require projects to alleviate the situation.

  9. WAPP PRIORITY PROGRAM

  10. Coastal Trans Backbone Sub-program Inter-Zonal Trans Sub-program North-core Trans Sub-program OMVG/OMVS Development Sub-program LSG System Redevelopment Sub-program MALI SENEGAL NIGER GAMBIA GUINEA BISSAU BURKINA FASO NIGERIA GUINEA BENIN SIERRA CÔTE TOGO LEONE D’IVOIRE GHANA LIBERIA Implementation Road Map

  11. Implementation of Priority Projects - Status  All project have been developed and funded  North Corridor Project – Nigeria – Niger – Benin – Togo – Burkina Faso  CLSG – Cote d’Ivoire - Liberia - Sierra Leone - Guniea  Commissioning of Mali- Cote d’Ivoire Interconnection will link WAPP Zone ‘A’ and Zone ‘B’  Most projects will be concluded by 2017

  12. IMPLEMENTATION OF WAPP POWER PLANTS

  13. Implementation Strategy  In order to implement the projects on a fast-track basis, Private Participation would be required;  Private Participation will bring the needed capital to bridge the financing gap;  Setting-up a Special Purpose Company (SPC) to manage and operate the project .  Key Considerations in selecting SPC structure & PPP model  Create financial leverage for stakeholder utilities  Create an efficient borrowing platform that will provide comfort for potential private capital providers.  Facilitate proper allocation of risks between the public and the private sector

  14. WAPP Power Plants  Build three (3) plants at locations with access to natural gas.  400 MW combined cycle plant at Maria Gleta in Benin.  400 MW combined cycle plant at Aboadze in Ghana.  150 MW combined cycle plant within OMVS (To utilize new gas fields being developed in Mauritania)

  15. Implementation Strategy  Project being implemented using the PPP model  Two sites at Maria Gleta in Benin and Domunili in Ghana to be developed simultaneously  Sithe Global (USA) has been selected as the developer for the Maria Gleta and Domunili plants  Joint Implementation Committee in place  Expected completion in 2017

  16. UPDATED ECOWAS MASTER PLAN

  17. a Plan optimal de 15-16/07/2011 17 développement

  18. 27/08/11 18

  19. Phases of Investment  Phases for the project development planned to met the regional demand :  Phase 1: 2017 - 2019  Phase 2: 2019 - 2021  Phase 3: 2021 - 2023 Plan optimal de 15-16/07/2011 19 développement

  20. Phasing of the Priority Investments & Sequence (1) Décidés Phase 1 Phase 2 Phase 3 Charbon 875 MW (Sénégal) Interconnexion Kayes Gouina (OMVS) –Tambacounda Eolien 200 MW (Sénégal-Gambie) Balassa- Badoumbé Koukoutamba- Interconnexion Ghana- Interconnexion Linsan- Interconnexion Linsan- Boureya Burkina Faso Mali Manantali (1er terne) Manantali (2nd terne) Kaléta (Guinée) Digan Projet OMVG Grand-Kinkon Souapiti Amaria Bumbuna Projet CLSG (+ Mount Coffee) Kassa Projet Tiboto Félou (OMVS) Plan optimal de Solaire 150 MW (Mali) 15-16/07/2011 20 développement

  21. Phasing of the Priority Investments & Sequence 2 Décidés Phase 1 Phase 2 Phase 3 Interconnexion Ségou-Ferkessedougou Fomi-Boundiali Projet Fomi Projet Soubré Projet Dorsale Côtière CC Togo Aboadze (Ghana) Adjaralla (Togo) Maria Gleta (Bénin) Bolgatanga- Axe 330kV Nord-Sud Ougadougou Ghana Solaire 150 MW Burkina Faso Projet Corridor Nord Projet Salkadamna Réseau 760kV Mambilla Zungeru Dorsale Médiane Eolien 300 MW Nigeria Nord Renforcement Bénin Nigéria Plan optimal de 6894 M$ 5726 M$ 5724 M$ 5887 M$ 15-16/07/2011 21 développement

  22. 27/08/11 22

  23. Energy Mix Strategy  Economic development of hydroelectric plants and reinforced regional interconnections to the N-1 criteria  Study Recommendation:  Need for energy mix  Objective to have 10% renewable energy (not hydro) = Ambitious but realizable Limited impact limité on total of developement (+2%)  Renewable energy (Solar and Wind) requires political will and policy at State level  10% Renewable in 2020 Plan optimal de 15-16/07/2011 23 développement

  24. Energy Mix - Outlook Mix Energétique en termes d'énergie produite 100% 90% 80% EOLIEN 70% SOLAIRE BIOMASSE 60% AUTRES 50% DIESEL OIL 40% HFO 30% CHARBON GAZ NATUREL 20% HYDRO 10% 0% 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 24

  25. REGIONAL MARKET DEVELOPMENT

  26. . MECARDOS Consultant Market Road Map Market Model for WAPP Market Rules 6. Training Recommendations 5. Implementation & Training Manual & Recommendations

  27. JUSTIFICATION FOR THE REGIONAL MARKET • There is a political decision and instruments for the development of the regional market Politi itical cal • Resources are complementary in the region which Will lling ngnes ness suggests strongly the benefits of an integration in a regional market (oil and gas in the east mainly and hydro in the west) • There are trades already ongoing in the region which demonstrates the capacity and willingness of Regional gional countries to trade Planning nning • There is infrastructure being developed for regional trading

  28. LEGAL FRAMEWORK FOR REGIONAL MARKET Economic nomic The ECOWAS Treaty  Coope peration tion The ECOWAS Energy Protocol  Energy gy Act Establish legal framework for securing competitive market Unbundling of the large Utilities  Reform orms Separation of generation / retail from monopoly business  (main grid and distribution) in Nigeria, Ghana, Senegal Regul ulation tion Supplementary Act A/SA.2/1/08 Establishing the ECOWAS  Regional Electricity Regulatory Authority ERERA Regi gional onal Articles of Agreement of the West African Power Pool  Pl Planning nning Organisation and Functions (October 2005) (WAPP)

  29. Minimum Requirement for the Regional Market • Open access to the spare capacity in the transmission systems Technical hnical • Agreement on a method for payment of wheeling Requir uirement ement services • Operation Rules Market et • Trading Rules Governance ernance • Regional Regulations

  30. MARKET DESIGN

  31. PRINCIPLES FOR MARKET DESIGN Training Plan.  Cooperation  Respect national regulations  Gradualism  Facilitate infrastructure expansion (generation  Transparency and transmission)  non discrimination  Rules easy to understand and easy to implement  Competitiveness  Access to transmission infrastructure  Environmental sustainability  Converging standards

  32. STRUCTURE OF MARKET DESIGN  The description of each Market Phase is made in an ordered manner following the next structure:  Market phase general description (introduction)  Conditions precedent to pass from one Phase to the following  Market Participants  Transactions in the market  The role of the regional Market Operator during the Phase  The role of the domestic TSOs during the Phase  The regional transmission network  Planning and regional projects

  33. Implementation Plan

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend