M4 Junctions 3-12 Smart Motorway Planning Inspectorate Introductory - - PowerPoint PPT Presentation

m4 junctions 3 12 smart motorway planning inspectorate
SMART_READER_LITE
LIVE PREVIEW

M4 Junctions 3-12 Smart Motorway Planning Inspectorate Introductory - - PowerPoint PPT Presentation

M4 Junctions 3-12 Smart Motorway Planning Inspectorate Introductory Meeting 14 February 2014 514451-MUH-00-ZZ-PP-DC-300131-1F Scheme overview and objectives Smart Motorways Scheme details Environmental Impact Nationally Significant


slide-1
SLIDE 1

M4 Junctions 3-12 Smart Motorway Planning Inspectorate Introductory Meeting 14 February 2014

514451-MUH-00-ZZ-PP-DC-300131-1F

slide-2
SLIDE 2

Scheme details Nationally Significant Infrastructure Project

Scheme overview and objectives

Smart Motorways Environmental Impact Programme

2

slide-3
SLIDE 3

Scheme Objectives

  • Relieving congestion and smoothing the flow of traffic
  • Improving journey times and journey time reliability
  • Maintaining safety levels for all road users
  • Supporting economic development within the region

3

slide-4
SLIDE 4

Scheme Overview

  • Developer – Highways Agency
  • Designer – Alliance
  • URS
  • Halcrow Hyder JV
  • Mouchel
  • Legal advice – Being appointed

4

slide-5
SLIDE 5

Scheme Overview

  • Approximately 32 miles length
  • Current traffic - average 130,000 vehicles per day
  • Suffers severe congestion and above average accident rate

5

slide-6
SLIDE 6

Scheme details Nationally Significant Infrastructure Project

Smart Motorways

Scheme overview and objectives Environmental Impact Programme

6

slide-7
SLIDE 7
  • Variable speed limits
  • All Lane Running
  • Signs and gantries
  • Full CCTV coverage
  • Emergency refuge areas

Key features of Smart Motorways

7

slide-8
SLIDE 8

8

  • Cost of Smart Motorways

is lower than traditional widening

  • Lower environmental

impact than traditional widening

  • Safety will be as existing
  • r improved

Why Smart Motorways?

slide-9
SLIDE 9

Nationally Significant Infrastructure Project Smart Motorways Environmental Impact Programme Scheme overview and objectives

Scheme details

9

slide-10
SLIDE 10

Scheme details

Mainline works include:

  • Gantries and

associated technology

  • Drainage works
  • Central reserve

hardening and concrete barrier

  • Pavement widening in

central reserve and widened slip roads

  • Emergency Refuge

Areas

  • Bridge works

10

slide-11
SLIDE 11

Scheme details

Bridge works between Junctions 4 to 8

  • Existing motorway hard shoulder discontinuities
  • 11 overbridges to be replaced with larger span structures
  • Online or offline
  • 6 underbridges to be widened to accommodate 4 lanes

11

slide-12
SLIDE 12

Scheme details Nationally Significant Infrastructure Project Smart Motorways Programme Scheme overview and objectives

Environmental Impact

12

slide-13
SLIDE 13

Environmental Impact

Initial Environmental Assessment indicates minimal impact.

  • Physical works minimised
  • Low impact on watercourses, habitats, landscape etc.
  • Technology regulates traffic flows – easing some vehicle emissions

Main risks:

  • Air quality
  • Visual impact
  • Noise

Currently undertaking screening exercise to determine requirement for statutory Environmental Impact Assessment

13

slide-14
SLIDE 14

Scheme details Smart Motorways Environmental Impact Programme Scheme overview and objectives

Nationally Significant Infrastructure Project

14

slide-15
SLIDE 15

Nationally Significant Infrastructure Project

 Scheme is an alteration to the highway  Scheme is wholly in England  Secretary of State is the highway authority  Area of development is greater than 15 Hectares

Therefore the scheme is a NSIP and a Development Consent Order is required

15

slide-16
SLIDE 16

Development Consent Order

Main legal powers required in DCO:

  • Compulsory acquisition
  • Alterations to streets
  • Stopping up of streets
  • Variable mandatory speed limits
  • Temporary stopping up of streets (including M4)
  • Temporary land and access rights

16

slide-17
SLIDE 17

Scheme details Smart Motorways Environmental Impact Nationally Significant Infrastructure Project Scheme overview and objectives

Programme

17

slide-18
SLIDE 18

M4 J3-12 Scheme Programme – Key Dates

  • Request PINS to adopt screening opinion – March 2014
  • Phase 1 consultation (non statutory – pre SoCC) – March 2014
  • Draft SoCC consultation – April 2014
  • Draft application submission – July 2014
  • Phase 2 consultation (post SoCC) – Sept 2014
  • Submit application – Late 2014/ Early 2015
  • Acceptance Stage – ends Early 2015
  • Pre Examination Stage – ends April/ May 2015
  • Examination Stage – ends Oct/ Nov 2015
  • Decision Stage - ends April/ May 2016
  • Post Decision Stage – ends May/ June 2016
  • Construction– 2016 to 2021

18

slide-19
SLIDE 19

Highways Agency Project Manager Lynne.stinson@highways.gsi.gov.uk HA Assistant Project Manager Adam.lloyd@highways.gsi.gov.uk Lands and Orders Lead James.Cuthbert@urs.com 19

slide-20
SLIDE 20

Thank you

20