m4 junctions 3 to 12 smart motorway
play

M4 Junctions 3 to 12 Smart Motorway Nationally Significant - PowerPoint PPT Presentation

M4 Junctions 3 to 12 Smart Motorway Nationally Significant Infrastructure Project Slough Borough Council Cabinet Members Tuesday 10 th March 2015 18.00 18.30 Chalvey Community Centre, The Green, Chalvey, Slough Theale Hayes What are we


  1. M4 Junctions 3 to 12 Smart Motorway Nationally Significant Infrastructure Project Slough Borough Council Cabinet Members Tuesday 10 th March 2015 18.00 – 18.30 Chalvey Community Centre, The Green, Chalvey, Slough

  2. Theale Hayes

  3. What are we doing • Making the M4 a “smart motorway” between junction 3 and 12 Why are we doing this • To help relieve congestion by using technology to vary speeds • Allowing the hard shoulder to be used as a running lane at all times to create additional capacity • Provide better information for drivers • Smart motorways deliver these benefits at a significantly lower cost than conventional motorway widening and with less impact on the environment during construction.

  4. ITS • New signs/gantries to be installed • New LED carriageway lighting, where required • Information and Communications Technology equipment • Removal of some existing gantries

  5. Highway Works • Carriageway widening at junctions to accommodate slip roads and areas where there is no existing hard shoulder • Realignment of the motorway at Thames Bray Bridge and Windsor Branch Railway • Emergency Refuge Areas (ERAs) within the existing highway verges at approx. 2.5km intervals • 4 lane carriageways between J3 and J4 and J5 and J12 • 5 lane carriageways between Junction 4 and Junction 4b • New low noise road surface course throughout Hard Shoulder Discontinuities Preventing Widening

  6. Traffic Management • Introduction of variable mandatory speed limits Infrastructure • New drainage systems within the central reserve and highway verge Environment • Construction of noise barriers, where required • Replacement planting/landscaping Temporary Works • Temporary construction compounds and lay-down areas • Temporary crane hard standing areas and site accesses

  7. Structures • Replacement of 11 overbridges, to include some off-line reconstruction • Widening of 5 underbridges including Thames Bray and Windsor Rail Bridge • A Rigid Concrete Barrier (RCB) within the central reserve • Retaining walls where required Proposed Lake End Road Bridge, Slough

  8. M4 J3 – 12 Smart Motorway DCO Programme

  9. Next Steps • Submission of Development Consent Order (DCO) application to the Planning Inspectorate (PINS) – due March 2015 • PINS have 28 days to review application and accept or reject it • If accepted we enter the pre-examination period during which interested parties can register and PINS determine the examination timetable • The examination will last up to 6 months • PINS issue a recommendation to the Secretary of State (SoS) within 3 months and the SoS then has 3 months to issue a decision • Post-decision there is an opportunity for challenge

  10. Contact Details Highways Agency Project Manager, Lynne Stinson, c/o Highways Agency, The Cube, 199 Wharfside Street, Birmingham, B1 1RN email – lynne.stinson@highways.gsi.gov.uk tel – 0121 678 8350

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend