overview of the planning act 2008 process
play

Overview of the Planning Act 2008 Process By Kay Sully Senior Case - PowerPoint PPT Presentation

Overview of the Planning Act 2008 Process By Kay Sully Senior Case Manager Information about the application process for Nationally Significant Projects The Planning Inspectorate The Planning Inspectorate (PINS) is an agency of Department


  1. Overview of the Planning Act 2008 Process By Kay Sully Senior Case Manager Information about the application process for Nationally Significant Projects

  2. The Planning Inspectorate • The Planning Inspectorate (PINS) is an agency of Department of Communities and Local Government (DCLG). • PINS Project Team: - provide advice to applicants, communities, Local Authorities and others about how to take part in the process; - support the Examining Authority in the running of the examination. • Examining Authority: Information about the application process for Nationally Significant Infra - examines the application; - makes a recommendation to the Secretary of State. Information about the application process for Nationally Significant Projects

  3. Planning Act 2008: New, Novel and Different Planning Act 2008 Localism Act 2011 National Policy Statements (NPS) IPC abolished ‘Single consents’ regime 2008 Act regime largely unchanged Early engagement Parliamentary approval of NPSs Statutory timetable Secretary of State (SoS) decisions in all cases Inquisitorial process Growth and Infrastructure Act 2013 Openness policy Some amendments to the 2008 Act Advice and guidance Information about the application process for Nationally Significant Infra regime including reducing the scope of Special Parliamentary Procedure Extends the regime optionally, to certain business and commercial projects – No NPS Information about the application process for Nationally Significant Projects

  4. The Development Consent Process Information about the application process for Nationally Significant Infra Information about the application process for Nationally Significant Projects

  5. Pre Application • Depending on the elements this duration can vary although on average it is expected to take 1-3 years • PINS encourage developers to share drafts of application documents for review: Draft DCO, Explanatory Memorandum, Book of Reference, Statement of Reasons (if compulsory acquisition), Consultation Report and plans • PINS outreach programme explains the process and roles Information about the application process for Nationally Significant Infra to different groups along with assisting parties to work collaboratively, particularly during the pre-application stage Information about the application process for Nationally Significant Projects

  6. Pre-application Work for Developers • Total application: No shocks, no surprises! • Environmental screening and scoping, PEI and ES • Consultation with prescribed bodies (s42) and landowners (s44) • Consultation with the community (SoCC and s47) Information about the application process for Nationally Significant Infra • Draft DCO • Limited scope for amending applications post submission Information about the application process for Nationally Significant Projects

  7. Acceptance • This begins when the developer submits the application to PINS • PINS had 28 days to decide whether the application meets the standards to proceed to Examination • During this stage, adequacy of consultation views from the relevant local authorities will be requested Information about the application process for Nationally Significant Infra Information about the application process for Nationally Significant Projects

  8. Pre-Examination • The public will be able to register with the PINS and provide a summary of their views of the application in writing • Examining Authority appointed; initial assessment of principal issues made and draft examination timetable • This Preliminary meeting – procedural meeting held to discuss how the Examination will be conducted Information about the application process for Nationally Significant Infra Information about the application process for Nationally Significant Projects

  9. Examination • Primarily undertaken by Written Representations • However, Hearings may be held to supplement the written process. These include: - Open Floor; - Issue-Specific; and - Compulsory Acquisition Information about the application process for Nationally Significant Infra Information about the application process for Nationally Significant Projects

  10. Recommendation / Decision • Examining Authority recommendation within 3 months • Secretary of State decision within 3 months • The applicant and all Interested Parties will be informed of the decision by PINS Information about the application process for Nationally Significant Infra Information about the application process for Nationally Significant Projects

  11. ……..Any Questions? Email address: kaysully@infrastructure.gsi.gov.uk Direct line: 0303 444 5056 Information about the application process for Nationally Significant Infra Website: http://infrastructure.planningportal.gov.uk/ Information about the application process for Nationally Significant Projects

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend