Relation with Other Contractual ADR Construction Work Contracts - - PowerPoint PPT Presentation

relation with other contractual adr
SMART_READER_LITE
LIVE PREVIEW

Relation with Other Contractual ADR Construction Work Contracts - - PowerPoint PPT Presentation

Compulsory Adjudication Effects, Procedure & Inter- Relation with Other Contractual ADR Construction Work Contracts Procurement of Materials and Labour Contracts Construction Consultancy Contracts Contracts Carried Out


slide-1
SLIDE 1

Compulsory Adjudication – Effects, Procedure & Inter- Relation with Other Contractual ADR

slide-2
SLIDE 2
  • Construction Work Contracts
  • Procurement of Materials and Labour Contracts
  • Construction Consultancy Contracts
  • Contracts Carried Out Wholly/Partially in Malaysia
  • Applies to Payment Disputes Arising After

15 April 2014

slide-3
SLIDE 3
  • DEC’s Payment Claims to Employer
  • Payment Claims by Domestic Sub-Cons
  • Payment Claims by Nominated Sub-Cons
  • Payments Claims by Material Supplier
  • Payment Claims by Labour Supplier
  • Payment Claims by Design Consultants
  • Payment Claims by Project Management Co.
slide-4
SLIDE 4
  • Building less than 4 storey high and
  • nly for occupation with Natural

Persons

  • Government Urgent/Emergency

Construction Works

  • Government National Security

Facilities

  • Government Contracts below

RM20million: Modified Application

  • Minister of Works future Exemptions?
slide-5
SLIDE 5

Payment Claim: Progress or Final

  • Non-Payment of Certified Sums by Due

Date

  • Non-Certification + Non-Payment by Due

Date

  • Under-Certification + Non-Payment by Due

Date

  • Non-Valuation or Under-Valuation + Non-

Payment of Variations, Loss & Expense & Other Claims

slide-6
SLIDE 6
  • LAD Deductions - EOT becomes part of the Dispute
  • Incorrect Quantities/Percentage of Works Completed
  • Incorrect Method of Measurement
  • Contractual Set-Offs or Equitable Set-Offs
  • Not Variation or Value of Variation
  • No Right to Loss & Expense – Liability & Quantum:

EOT could become part of Dispute

  • No Right to Other Claims – Liability & Quantum
  • Termination – if related to Final Account
slide-7
SLIDE 7
  • Option of Party Having Payment Claim
  • Use Statutory Adjudication Process; or
  • Use Contractual ADR Process; or
  • Use Court for Litigation (danger of stay of court

proceedings due to preference of contractual ADR Process)

  • If Party opts for Statutory Adjudication Process:

the Other Party cannot Avoid

  • Cannot Contract to make CIPAA Inapplicable
slide-8
SLIDE 8
  • Option to Party Making Payment Claim
  • Prefer Statutory Adjudication
  • Enforcement Rights Clear & Strong
  • Cheaper than Contractual Adjudication
  • Prefer Contractual Adjudication
  • Faster : PAM Adjudication : 21 + 7 days from acceptance of

appointment by Adjudicator

  • Intention to Set-Off without Actual Set-Off: No Non-

Payment – No Choice but to Use Contractual Adjudication

  • Contractual Adjudication Condition Precedent to

Arbitration – No Choice if wish to Preserve Right to Arbitration

slide-9
SLIDE 9
  • Temporary Dispute Resolution Process
  • Quick : 95- 105 working days (4 months)
  • Cheap: Scale Fee for Adjudicator
  • RM100,000 dispute: Fee is RM5,760
  • RM1million dispute: Fee is RM18,697
  • RM5million dispute: Fee is RM48,262
  • Over RM5million dispute: Fee is RM50,000
  • Binding until Overturned by Arbitration or Court
  • Temporary: Dissatisfied Party Can Re-Open in Arbitration or

Court

  • If Arbitration only when Project Completed (same for Court

Implicitly): Adjudication Resolves Dispute Temporarily During Works

slide-10
SLIDE 10
  • Payment Claim from DEC or Suppliers/Sub-Cons – must

contain (compulsory):

  • The Amount Claimed
  • The Relevant Provision of the Contract
  • The Cause of Action: why entitled to the Claim
  • Description of Works/Services related to Claim
  • Statement that Claim is made under CIPAA 2012

Example : Attachment A

  • Hand delivered, left or sent to usual place of business
  • r as agreed under Contract
slide-11
SLIDE 11
  • Payment Response (Attachment B)
  • 10 working days (14 days unless public holidays)
  • If Admit whole or partial – enclose payment
  • If Dispute – reasons for dispute (unclear whether can’t

expand reasons later)

  • Safer to reserve right on any other dispute
  • Not Compulsory
  • If unsure of disputes: don’t respond
  • Can later raise any dispute
  • Tactically better to respond if certain of disputes:

Allows Claimant to decide on Adjudication

slide-12
SLIDE 12
  • Only after the 10 working days for Payment Response

Expires (copy to KLRCA)

  • day 15 after Payment Claim received by Other Party
  • Refer to Dispute: By Reference to Payment Claim and

Payment Response

  • Refer to Remedy : Amount Claimed Which is Not

Admitted

  • Nomination of Single Adjudicator: Best to Enquire with

Nominee on:

  • Conflict of Interest
  • Availability & Ability
slide-13
SLIDE 13

Parties to Agree – within 10 w.days from service of Notice of Adjudication

  • Freedom of Choice/ KLRCA Panel or Accredited?

If Agreed

  • Inform Adjudicator + Notice of Adjudication
  • Adjudicator: 10 working days to
  • Propose & Negotiate Terms (outside of CIPAA Scale)
  • Accept Appointment
  • If not Accept, Parties to Agree Another: 10 working days
slide-14
SLIDE 14

If Not Agreed

  • Request KLRCA to Appoint
  • KLRCA has 5 working days to Appoint & Inform
  • Adjudicator: 10 working days to
  • Propose & Negotiate Terms (outside of CIPAA Scale)
  • Accept Appointment
  • If not Accept, Parties to Agree Another (10 working days)
  • r KLRCA to Re-appoint (5 working days)
slide-15
SLIDE 15

Adjudicator’s Declaration when Accepting Appointment

  • no conflict of interest;
  • independence;
  • impartiality;
  • ability to act within time;
  • will avoid incurring unnecessary expenses
  • will comply with principles of natural justice;
  • no justifiable doubts on impartiality & independence
slide-16
SLIDE 16

10 working days from Adjudicator’s Acceptance of Appointment To Adjudicator & Other Party & KLRCA (without docs)

  • Claim & Remedy (Attach Payment Claim)
  • Nature & Description of Dispute
  • Attach Payment Response
  • Supporting Narratives with cross-reference to documents

which support Payment Claim

  • Supporting Narratives to Counter Payment Response

with cross-reference to documents

  • All Relevant Documents
slide-17
SLIDE 17

10 working days from receipt of Adjudication Claim To Adjudicator & Other Party & KLRCA (without docs)

  • Brief Outline of Defences (Attach Payment

Response)

  • Nature & Description of Defences
  • Supporting Narratives with cross-reference to documents

which establish each defence

  • All Relevant Documents
slide-18
SLIDE 18

5 working days from receipt of Adjudication Response To Adjudicator & Other Party & KLRCA (without docs)

  • Brief Outline of Reply to Defences
  • Nature & Description of Replies
  • Supporting Narratives with cross-reference to documents

which establish each reply and attacks each defence

  • All Relevant Documents
slide-19
SLIDE 19
  • Up to Adjudicator when to Fix (Possible before

Fifth/Sixth/Seventh Step)

  • Decision must be 45 working days after Seventh

Step (Parties can extend by agreement – Request?)

  • Adjudicator decides Procedure
  • Inquisitorial not Adversarial??
  • Ask for Experts (Party or Own)
  • Set out very tight timetable for any procedure
  • Ask for limited information / resubmission of

narratives with limited pages & limited documents

slide-20
SLIDE 20
  • Proper Inquisitorial: Proactive Adjudicator
  • List of Interrogatories on Facts, Contract & Law
  • List of Queries on Documents & Interpretation
  • Request for Affirmed Statements or Memorials
  • Questioning by Adjudicator of Pertinent Personnel
  • Physical Inspection/Expert Hot –Tubbing/Own Expert
  • Limited & Controlled Cross-Examination
  • Adversarial-Inquisitorial: Non-Proactive Adjudicator
  • To decide simply based on Adjudication Claim, Response

& Reply

  • Up to Parties to Satisfy
slide-21
SLIDE 21
  • Try to get to the truth but with limited time
  • Try to get the job done, quality secondary
  • Fees so small, just guess on entitlements
  • Pro-Claiming Party since CIPAA is to ensure cash-

flow not affected in Project

  • Factual Minded v Legal Minded
  • Apply Burden of Proof or Misplace the Burden
  • Decision right or wrong cannot be challenged
slide-22
SLIDE 22

>45 w.days = Void & Adjudicator no fees = result: re-commence adjudication? Evidence Act not apply Reasoned Decision Slip Rule Consolidation only on Parties agreement Cost to follow Event & Quantum fixed (Parties prior agreement on Cost void (Tolent clauses)) Confidentiality

slide-23
SLIDE 23

No kompetenz-kompetenz Discretion to Proceed whilst Setting Aside Application is made to High Court Subject to Stay by High Court

slide-24
SLIDE 24

Can be referred concurrently to

  • Adjudication
  • Arbitration
  • Court

Adjudication proceeds unless Arbitration or Court decides earlier – Decision temporary binding Ignored Other Contractual Dispute Resolution Processes such DAB in FIDIC or Expert Determination? What effect?

slide-25
SLIDE 25

Temporary Binding subject to:-

  • Setting Aside by High Court
  • Stay by High Court
  • Settlement by Parties
  • Final Decision by Arbitration or Court

Setting Aside

  • Fraud/Bribery/No Natural Justice/ Lack of

Independence or Impartiality/ No Jurisdiction

slide-26
SLIDE 26

Stay

  • Pending Setting Aside
  • Pending Final Decision of Arbitration or

Court

  • Discretion on Terms of Stay including

deposit of adjudicated amount with KLRCA No Review

slide-27
SLIDE 27

Res Judicata on Response for next Payment Claim? No for Continuing Matters (delays etc) Dangers of Piece-Meal Issue by Issue Adjudications which can reverse effect of prior Adjudications Dangers of Differing Number of Adjudicators for same Project (different contractual interpretations) Events Post Decision giving rise to a right of Set-off is Lost?

slide-28
SLIDE 28

Application to Enforce in High Court

  • No Procedural Rules as yet
  • Court may determine Post-Decision Interest

Suspension or Slowing Down

  • Needs 14 days prior notice
  • Entitled to EOT and Loss & Expense
  • Resume within 10 working days of Payment
  • What happens if Set Aside/Stayed – No EOT?
slide-29
SLIDE 29

Direct Payment from Principal

  • May Make Written Request
  • Once Principal satisfied Adjudicated Sums

not paid and there is money due and payable by Principal = Principal shall Pay Concurrent exercise of all Remedies

slide-30
SLIDE 30

Adjudication = Temporary Binding Arbitration = Binding (subject to Court again) Issues in Dispute ventilated Twice Time for : KLRCA Fast Track Arbitration Rules?

  • Same as Adjudication except maximum 140 days & Final

Time for : Opting out of Section 42 Arbitration Act 2005 (no setting aside etc by High Court)

slide-31
SLIDE 31

Default Provisions if No Terms on Payment

  • Monthly or on Delivery Invoice
  • Within 30 days from Invoice

Pay When and If Paid: Void – Effect on NSC contracting

  • Not Pay When Certified by Employer and Up to Value

Certified

  • Not Certified when Paid & Then Pay When Certified?
slide-32
SLIDE 32

STATUTORY ADJUDICATION

Payment Claim Payment Response Adjudication Notice

10 W. Days

Adjudicator Agreed Adjudicator Disagreed

+10 W. Days

Request KLRCA Adjudicator Notification

No time No time

KLRCA Appoint Adjudicator Fees & Terms

+5 W. Days +10 W. Days

If Not Agreed Process Repeated Adjudicator Fees & Terms

+10 W. Days

slide-33
SLIDE 33

If Not Agreed Process Repeated Adjudicator Fees & Terms Adjudicator Acceptance

Same time

Adjudication Claim Adjudication Response

+10 W. Days +10 W. Days

Adjudication Reply Adjudication Decision Delay (Void) Re-Commence

+5 W. Days +45 W. Days [> time agreed by parties]

Time & Manner of Payment

slide-34
SLIDE 34

Due (Unpaid) High Court Enforcement Order to Enforce Enforcement Direct Payment Notice Principal’s Notice to Losing Party Losing Party Prove Payment Principal Direct Payment Notice to Suspend/Slow Actual Suspend/Slow Resume Works If Paid

+10 W. Days If No Prove +10 W. Days +14 Days

EOT + Loss & Expense

Delay