G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA S CHOOL B UILDING C OMMITTEE MEETING M AY 4, 2020 Raymond Design Associates M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 1. Progress Report Bid for the Early Demolition Package were


slide-1
SLIDE 1
  • G. H. MITCHELL ELEMENTARY SCHOOL

BRIDGEWATER, MA

SCHOOL BUILDING COMMITTEE MEETING

MAY 4, 2020

Raymond Design Associates

slide-2
SLIDE 2

School Building Committee| May 04, 2020 2

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

1. Progress Report

  • Bid for the Early Demolition Package were received on April 29th.
  • RDA and DPI, representatives from the School District have been meeting virtually as a working group to solicit

feedback on the current design.

  • RDA and their consultants are continuing with the development of the 60% Construction Documents as noted in

the MSBA design review template.

slide-3
SLIDE 3

School Building Committee| May 04, 2020 3

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

2. Schedule and Milestones:

  • Demolition of Existing School

April 2020 – August 2020

  • Bid demo package

April 15 – April 29

  • Review/Award demo package

April 29 – May 19

  • Demo existing building

May 19 – August 30

  • 60% Construction Documents (60% CD)

March 2020 – June 2020

  • 60 % CD Construction Cost Estimates

May 08 – May 29

  • MSBA 60% CD Submission

June 05

  • 90% Construction Documents (90% CD)

June 2020 – August 2020

  • MSBA 90% CD Submission

August 28, 2020

  • 100% Construction (Bid) Documents

September – October 2020

  • Bidding and Award

October – November 2020

  • Construction

December 2020 – July 2022

slide-4
SLIDE 4

School Building Committee| May 04, 2020 4

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

3. Upcoming Meetings

  • School Building Committee Meeting #38

May 4th, 2020

  • Review Floor Plans and Space Summary
  • Exterior Elevations & Materials
  • Approval of Demolition Contract Award
  • School Building Committee Meeting #39

June 1st, 2020

  • Review 60% Reconciled Construction Cost Estimates
  • Approve 60% CD Submission to MSBA
  • School Building Committee Meeting #40

June 15th, 2020

  • School Building Committee Meeting #41

June 29th, 2020

  • School Building Committee Meeting #42

July 13th, 2020

slide-5
SLIDE 5

School Building Committee| May 04, 2020

4. Project Budget

5

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

Project Budget (PFA November 2019) Current Project Budget

(subject to MSBA BRR approval)

Committed Amount

(under contract)

Amount Paid to Date

(entered to Pro Pay)

Balance to Finish

(Current Project Budget vs. Paid to Date)

Feasibility Study

$800,000 $800,000 $725,524 $701,840 $98,160

Administration & OPM

$2,195,000 $2,195,000 $2,050,000 $142,200 $2,052,800

Architecture & Design

$6,250,000 $6,329,600 $6,329,600 $1,660,015 $4,669,585

Construction

$64,679,981 $64,679,981 $0 $0 $64,679,981

  • Misc. Project Cost

$475,000 $475,000 $0 $0 $475,000

FF & E

$2,460,000 $2,460,000 $0 $0 $2,460,000

Contingency

$3,740,019 $3,660,419

  • $3,660,419

TOTALPROJECT BUDGET $80,600,000 $80,600,000 $9105,143 $2,504,054 $78,095,946

slide-6
SLIDE 6

School Building Committee| May 04, 2020 6

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

4. Project Budget PFA Budget $80,600,000 The MSBA reimbursement rate for this project is: 59.28% Amount Submitted to MSBA – Pro Pay 1-10 $2,504,055 Amount Reimbursed by MSBA to date – Pro Pay 1-9 $1,068,154 ProPay #10 is currently under review at MSBA

slide-7
SLIDE 7

School Building Committee| May 04, 2020 7

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

5. Early Demolition Bids Bids for the demolition of the existing George H. Mitchell Elementary School were received electronically on April 29,

  • 2020. Bids are available for public review at biddocsonline.com. Below is a summary of the bids received:
  • 1. JR Vinagro Corporation

$563,000

  • 2. JDC Demolition

$746,000

  • 3. Costello Dismantling

$747,000

  • 4. American Environmental

$774,500

  • 5. Dagle Electrical Construction

$866,668

  • 6. Southern Middlesex Industries

$916,666

  • 7. S&R Corporation

$933,775

  • 8. Lambrian Construction

$937,000

  • 9. Select Demo Services

$967,090 The budget for the demolition package is $1,250,000

slide-8
SLIDE 8

School Building Committee| May 04, 2020 8

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

5. Early Demolition Bids A review of the documentation submitted by JR Vinagro notes:

  • JR Vinagro’s current DCAMM Certificate of Eligibility is based on 20 project evaluations
  • The average evaluation is 95
  • JR Vinagro have 0 evaluations under 80
  • JR Vinagro’s single project limit is $11,501,000
  • JR Vinagro’s aggregate project limit is $50,000,000

Daedalus Projects has previously worked with JR Vinagro, most recently on the Sharon Town Hall Demolition project. JR Vinagro appears to be an eligible and responsible bidder. As low bidder Daedalus Projects recommends the District enter into a contract for the demolition of the existing George H. Mitchell Elementary School with JR Vinagro in accordance with their bid submitted April 29, 2020, in the amount of $583,000.