1. Progress Report
feedback on the current design.
the MSBA design review template.
School Building Committee| May 04, 2020 3
2. Schedule and Milestones:
April 2020 – August 2020
April 15 – April 29
April 29 – May 19
May 19 – August 30
March 2020 – June 2020
May 08 – May 29
June 05
June 2020 – August 2020
August 28, 2020
September – October 2020
October – November 2020
December 2020 – July 2022
School Building Committee| May 04, 2020 4
3. Upcoming Meetings
May 4th, 2020
June 1st, 2020
June 15th, 2020
June 29th, 2020
July 13th, 2020
School Building Committee| May 04, 2020
4. Project Budget
5
Project Budget (PFA November 2019) Current Project Budget
(subject to MSBA BRR approval)
Committed Amount
(under contract)
Amount Paid to Date
(entered to Pro Pay)
Balance to Finish
(Current Project Budget vs. Paid to Date)
Feasibility Study
$800,000 $800,000 $725,524 $701,840 $98,160
Administration & OPM
$2,195,000 $2,195,000 $2,050,000 $142,200 $2,052,800
Architecture & Design
$6,250,000 $6,329,600 $6,329,600 $1,660,015 $4,669,585
Construction
$64,679,981 $64,679,981 $0 $0 $64,679,981
$475,000 $475,000 $0 $0 $475,000
FF & E
$2,460,000 $2,460,000 $0 $0 $2,460,000
Contingency
$3,740,019 $3,660,419
TOTALPROJECT BUDGET $80,600,000 $80,600,000 $9105,143 $2,504,054 $78,095,946
School Building Committee| May 04, 2020 6
4. Project Budget PFA Budget $80,600,000 The MSBA reimbursement rate for this project is: 59.28% Amount Submitted to MSBA – Pro Pay 1-10 $2,504,055 Amount Reimbursed by MSBA to date – Pro Pay 1-9 $1,068,154 ProPay #10 is currently under review at MSBA
School Building Committee| May 04, 2020 7
5. Early Demolition Bids Bids for the demolition of the existing George H. Mitchell Elementary School were received electronically on April 29,
$563,000
$746,000
$747,000
$774,500
$866,668
$916,666
$933,775
$937,000
$967,090 The budget for the demolition package is $1,250,000
School Building Committee| May 04, 2020 8
5. Early Demolition Bids A review of the documentation submitted by JR Vinagro notes:
Daedalus Projects has previously worked with JR Vinagro, most recently on the Sharon Town Hall Demolition project. JR Vinagro appears to be an eligible and responsible bidder. As low bidder Daedalus Projects recommends the District enter into a contract for the demolition of the existing George H. Mitchell Elementary School with JR Vinagro in accordance with their bid submitted April 29, 2020, in the amount of $583,000.