- G. H. MITCHELL ELEMENTARY SCHOOL
BRIDGEWATER, MA
COMMUNITY PRESENTATION
JANUARY 10, 2019
Raymond Design Associates
R ECAP | P RELIMINARY D ESIGN P ROGRAM (PDP) P RELIMINARY E VALUATION - - PowerPoint PPT Presentation
G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA C OMMUNITY P RESENTATION J ANUARY 10, 2019 Raymond Design Associates R ECAP | P RELIMINARY D ESIGN P ROGRAM (PDP) P RELIMINARY E VALUATION E DUCATIONAL P ROGRAM E VALUATION OF O PTIONS
BRIDGEWATER, MA
JANUARY 10, 2019
Raymond Design Associates
Community Meeting | January 10, 2019 2
PRELIMINARY EVALUATION
June – August 2018 Evaluation of conditions of the existing building and site June – August 2018 Initial Space Summaries for current and required square-footage June – August 2018 Preliminary evaluation of alternate site options on available Town or District-owned site within Bridgewater July – September 2018 Visioning Workshops and Educational Program development July – August 2018 Tours of other School projects (both MSBA and non-MSBA funded) August – October 2018 Grade configuration study (PreK-2 and PreK-3)
EDUCATIONAL PROGRAM EVALUATION OF OPTIONS PDP SUBMISSION
August – October 2018 Preliminary Evaluation of Options “Base Repair” Systems and Code Updates Only “Renovation” Updates to interior spaces No addition/expansion “Addition/Renovation” Interior reconfiguration with addition/expansion “New Construction” Demolition of existing and complete new construction November 2, 2018 PDP was submitted to the MSBA for review and comments December 2018 MSBA responded with requests for additional information January 2019 Project team responded to MSBA with additional documentation
Community Meeting | January 10, 2019 3
The purpose of the Preferred Schematic Report is to summarize the process and conclusions of the Preliminary and Final Evaluation of Alternatives and to substantiate and document the District’s selection and recommendation of a preferred solution. The Report should clearly identify any changes incorporated by the District based on further evaluations and
Community Meeting | January 10, 2019 4
The SBC has received some questions and comments regarding the possibility of utilizing the existing Middle School (old High School) and current High School locations. A total of six possible options were studied and
BRIDGEWATER MIDDLE SCHOOL (166 MT. PROSPECT STREET)
Police + Fire Departments BRIDGEWATER-RAYNHAM REGIONAL HIGH SCHOOL (415 CENTER STREET)
Community Meeting | January 10, 2019 5
The Architect’s team of consultants have conducted multiple tests and surveys of the existing site at 500 South Street. Preliminary reports include the following:
site's buildable portion
Current conceptual options for both Addition/Renovation or New Construction include significant sitework to ensure proper water management and drainage.
Community Meeting | January 10, 2019 6
**Assumes all criteria on the Option Comparison Matrix are weighted equally.
Community Meeting | January 10, 2019 7
Modifications to meet educational program. Option A3 has site improvements and significant reconfiguration.
1 STORY @ SOUTH STREET / 2 STORIES @ REAR 127,804 SF 258 PARKING SPACES 26 BUS QUEUE / 78 PARENT QUEUE 97,100 SF PLAYFIELD 19,090 SF PLAYGROUND 27,550 SF HARD SURFACE PLAY
Community Meeting | January 10, 2019 8
Challenges:
entrances
grade levels Does NOT address
Opportunities:
Community Meeting | January 10, 2019 9
A “comprehensive” or “hybrid” addition/renovation plan, including reconfiguration of interior spaces and expansion to meet educational program. Structural lateral loading criteria meets either the
current 9th Edition of the MA State Building Code.
* meeting 6th Ed. is acceptable
1 STORY @ SOUTH STREET / 2 STORIES @ REAR 145,800 SF 258 PARKING SPACES 26 BUS QUEUE / 78 PARENT QUEUE 97,100 SF PLAYFIELD 19,090 SF PLAYGROUND 27,550 SF HARD SURFACE PLAY
Community Meeting | January 10, 2019 10
Challenges:
Opportunities:
Community Meeting | January 10, 2019 11
New construction options allow for multiple building positioning & configurations. All options meet educational vision and program,
configuration, security, circulation, and expansion needs.
2 STORIES @ SOUTH STREET / 3 STORIES @ REAR (except C4 is 1 story @ SW) 132,213 SF 260-305 PARKING SPACES 26 BUS QUEUE / 80 PARENT QUEUE 97,100 SF PLAYFIELD 19,090–22,090 SF PLAYGROUND 16,5090-27,550 SF HARD SURFACE PLAY
Community Meeting | January 10, 2019 12
Challenges:
(2 story @ South St / 3 story @ rear)
Opportunities:
Community Meeting | January 10, 2019 13
New construction options allow for multiple building positioning & configurations. All options meet educational vision and program,
configuration, security, circulation, and expansion needs.
2 STORIES @ SOUTH STREET / 3 STORIES @ REAR (except C4 is 1 story @ SW) 132,213 SF 260-305 PARKING SPACES 26 BUS QUEUE / 80 PARENT QUEUE 97,100 SF PLAYFIELD 19,090–22,090 SF PLAYGROUND 16,5090-27,550 SF HARD SURFACE PLAY
Community Meeting | January 10, 2019 14
Challenges:
(2 story @ South St / 3 story @ rear)
Opportunities:
Community Meeting | January 10, 2019 15
Study Option GSF
(Gross Square Feet)
2018/2019 Construction Cost Benchmarks 2018/2019 Total Project Cost Benchmarks Estimated Costs - Mitchell Project
(Town share % after MSBA reimbursement)
Renovation Option A3
127,804 $39 - $42 M $49 - $52 M $27 - $29 M
(Town share = approx. 55%)
Renovation/Addition Option B1/B2
145,800 $65 - $73 M $81 - $91 M $45 - $50 M
(Town share = approx. 55%)
New Construction Option C1.2
132,213 $70 - $73 M $87 - $91 M $48 - $50 M
(Town share = approx. 55%)
New Construction Option C6
132,213 $70 - $73 M $87 - $91 M $48 - $50 M
(Town share = approx. 55%)
Community Meeting | January 10, 2019 16
$- $100,000.00 $200,000.00 $300,000.00 $400,000.00 $500,000.00 $600,000.00 $700,000.00 $800,000.00 $900,000.00 $1,000,000.00 $1,100,000.00 $1,200,000.00 $1,300,000.00 $1,400,000.00 $1,500,000.00 $1,600,000.00 $1,700,000.00 $1,800,000.00 $1,900,000.00 $2,000,000.00 $2,100,000.00 $2,200,000.00 $2,300,000.00 $2,400,000.00 $2,500,000.00 $2,600,000.00 $2,700,000.00 $2,800,000.00 2 4 6 8 10 12 14 16 18 Old HS Remodel BMS BMS Roof Mitchell Williams Land New HS* New HS* Additional New HS* Yearly Total
Community Meeting | January 10, 2019 17
OLD HIGH SCHOOL / BRIDGEWATER MIDDLE SCHOOL REMODEL
BRIDGEWATER MIDDLE SCHOOL ROOF
MITCHELL SCHOOL RENOVATIONS
WILLIAMS SCHOOL ADDITION/RENOVATION
LAND FOR THE NEW B-R REGIONAL HIGH SCHOOL
NEW B-R REGIONAL HIGH SCHOOL PROJECT
ADDITIONAL BOND FOR THE NEW B-R REGIONAL HS
Community Meeting | January 10, 2019 18
0.00 100,000.00 200,000.00 300,000.00 400,000.00 500,000.00 600,000.00 700,000.00 800,000.00 900,000.00 1,000,000.00 1,100,000.00 1,200,000.00 1,300,000.00 1,400,000.00 1,500,000.00 1,600,000.00 1,700,000.00 1,800,000.00 1,900,000.00 2,000,000.00 2,100,000.00 2,200,000.00 2,300,000.00 2,400,000.00 2,500,000.00 2,600,000.00 2,700,000.00 2,800,000.00 2,900,000.00 FY 2018 Ending Balance FY 2019 Ending Balance FY 2020 Ending Balance FY 2021 Ending Balance FY 2022 Ending Balance FY 2023 Ending Balance FY 2024 Ending Balance FY 2025 Ending Balance FY 2026 Ending Balance FY 2027 Ending Balance FY 2028 Ending Balance FY 2029 Ending Balance FY 2030 Ending Balance FY 2031 Ending Balance FY 2032 Ending Balance FY 2033 Ending Balance FY 2034 Ending Balance FY 2035 Ending Balance FY 2036 Ending Balance FIRE REFUND 12/1/11 2011 School Project Refunding 2014 School Refunding 2014 Refunding Police Building FIRE STATION ROOF REHAB MEMORIAL BUILDING REHAB ACADEMY BUILDING (TOWN HALL) RENOVATIONS Land Acquisition for Hogg Farm (2011_GOB_00002) 2012 Fire Ambulance (under 2012_MPL_00001) 2012 Fire Engine (under 2012_MPL_00001) 2014 Refunding Department Equipment 2014 Refunding Highway Equipment
Community Meeting | January 10, 2019 19
285,759 385,759 485,759 585,759 685,759
Average Household per FY2019
Residential Property Value - Additional Taxes per year
Scenarios of Debt Impact on Bridgewater Tax Rate *based on FY 2019 Tax Recap/Levy Documentation
Borrowing Amount Interest Rate P & I Year One (25 Year Note) Per $1,000 of Value 40,000,000 5% 3,288,000 36,000,000 34,000,000 5% 5% 2,959,200 2,794,800 $1.0802 $0.9722 $0.9182 $309 $278 $262 $741 $667 $630 $354 $446 $417 $375 $525 $472 $633 $569 $538 $521 $656 $791 $926 45,000,000 5% 3,699,000 $1.2152 $347 $469 $590 $712 $833 50,000,000 5% 4,110,000 $1.3502 $386
Community Meeting | January 10, 2019 20
2019 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
“Module 3”: Feasibility Study “Module 4”: Schematic Design FEB 20th
PSR Submission to MSBA
APR 10th
MSBA Board of Directors Meeting to approve PSR Begin Schematic Design Phase
AUG 28th
MSBA Board of Directors Meeting to approve PSBA
FALL
Town Vote to approve Funding
JUL 10th
Schematic Design Submission to MSBA
JAN 10th
Community Presentations 10:00am + 7:00pm
JAN 28th
BSBC to choose Preferred Schematic Design
“Module 5”: Funding DEC 11th
MSBA Board of Directors Meeting to approve PFA
Community Meeting | January 10, 2019 21
Community Meeting | January 10, 2019 22
Community Meeting | January 10, 2019 23