1. Progress Report
the DD submission and issued their review comments on March 30th. The District has 14 days in which to respond to MSBA’s comments.
feedback on the current design.
Departments to review permitting requirement for the project.
the MSBA design review template.
School Building Committee| April 06, 2020 3
2. Schedule and Milestones:
April 2020 – August 2020
April 15 – April 30
May 04 – May 19,
May 19 – August 30
March 2020 – June 2020
June 05, 2020
June 2020 – August 2020
August 28, 2020
September – October 2020
October – November 2020
December 2020 – July 2022
School Building Committee| April 06, 2020 4
3. Upcoming Meetings
April 6th, 2020
April 27h, 2020
May 4th, 2020
June 1st, 2020
School Building Committee| April 06, 2020
4. Project Budget
5
Project Budget (PFA November 2019) Current Project Budget
(subject to MSBA BRR approval)
Committed Amount
(under contract)
Amount Paid to Date
(entered to Pro Pay)
Balance to Finish
(Current Project Budget vs. Paid to Date)
Feasibility Study
$800,000 $800,000 $725,524 $701,840 $98,160
Administration
$145,000 $145,000 $0 $0 $145,000
Owners Project Manager
$2,050,000 $2,050,000 $2,050,000 $102,000 $1,948,000
Architecture & Design
$6,250,000 $6,250,000 $6,250,000 $1,005,469 $5,244,531
Construction
$64,679,981 $64,679,981 $0 $0 $64,679,981
$475,000 $475,000 $0 $0 $475,000
FF & E
$2,460,000 $2,460,000 $0 $0 $4,760,000
Contingency
$3,740,019 $3,740,019
TOTALPROJECT BUDGET $80,600,000 $80,600,000 $9,025,524 $1,809,309 $78,790,691
School Building Committee| April 06, 2020 6
4. Project Budget PFA Budget $80,600,000 The MSBA reimbursement rate for this project is: 59.28% Amount Submitted to MSBA – Pro Pay 1-9 $1,809,309 Amount Reimbursed by MSBA to date – Pro Pay 1-9 $1,068,154 There are currently no Pay Pay submission under review at MSBA
School Building Committee| April 06, 2020 7
Module 6 Reference Description 6B.1 Basic Project Information – Enrollment, GSF area, Project Type, Delivery Method 6B.2.1 OPM Submittal Review and Coordination 6A.2.1
6A.2.2 Project Schedule 6A.2.3 Project Scope and Budget
6. MSBA Module 6 Detailed Design – 60% Construction Documents Submission
School Building Committee| April 06, 2020 8
Module 6 Reference Description 6B.3.1 Designer Deliverables
6B.3.2 Updated Space Summary – Explanation of Deviations
6B.3.3 Project Approvals – State & Local Approvals, Utility Company Coordination
6. MSBA Module 6 Detailed Design – Design Development Submission
School Building Committee| April 06, 2020 9
Module 6 Reference Description 6B.3.4 Designer Construction Cost Estimate 6B.3.5 60% Construction Documents Drawings 6B.3.6 60% Construction Documents Project Manual
6. MSBA Module 6 Detailed Design – Design Development Submission