G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA S CHOOL B UILDING C OMMITTEE MEETING A PRIL 06, 2020 Raymond Design Associates M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 1. Progress Report DPI coordinated the submission of the


slide-1
SLIDE 1
  • G. H. MITCHELL ELEMENTARY SCHOOL

BRIDGEWATER, MA

SCHOOL BUILDING COMMITTEE MEETING

APRIL 06, 2020

Raymond Design Associates

slide-2
SLIDE 2

School Building Committee| April 06, 2020 2

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

1. Progress Report

  • DPI coordinated the submission of the Design Development documents to MSBA on March 16th. MBSA reviewed

the DD submission and issued their review comments on March 30th. The District has 14 days in which to respond to MSBA’s comments.

  • RDA and DPI, representatives from the School District have been meeting virtually as a working group to solicit

feedback on the current design.

  • RDA and their consultant met virtually with the Conservation Commission and representatives form other Town

Departments to review permitting requirement for the project.

  • RDA and their consultants are continuing with the development of the 60% Construction Documents as noted in

the MSBA design review template.

slide-3
SLIDE 3

School Building Committee| April 06, 2020 3

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

2. Schedule and Milestones:

  • Demolition of Existing School

April 2020 – August 2020

  • Bid demo package

April 15 – April 30

  • Review/Award demo package

May 04 – May 19,

  • Demo existing building

May 19 – August 30

  • 60% Construction Documents (60% CD)

March 2020 – June 2020

  • MSBA 60% CD Submission

June 05, 2020

  • 90% Construction Documents (90% CD)

June 2020 – August 2020

  • MSBA 90% CD Submission

August 28, 2020

  • 100% Construction (Bid) Documents

September – October 2020

  • Bidding and Award

October – November 2020

  • Construction

December 2020 – July 2022

slide-4
SLIDE 4

School Building Committee| April 06, 2020 4

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

3. Upcoming Meetings

  • School Building Committee Meeting #36

April 6th, 2020

  • Building Interiors Interior Spaces – Cafeteria, Gym, Music, Maker Space, Art
  • Interior Finishes - Materials
  • Site – Traffic, Parking, Deliveries, Snow Storage
  • Permitting Update
  • Demo Logistics Review & Schedule
  • School Building Committee Meeting #37

April 27h, 2020

  • Building Interiors Interior Spaces – Admin, Nurse, Typical Classroom, ELS, SPED
  • Interior Finishes - Materials
  • Site – Play Areas, Lighting and Site Improvements
  • Exterior Elevations and Materials
  • Electrical and Technology
  • Plumbing and Bathroom Fixtures
  • School Building Committee Meeting #38

May 4th, 2020

  • School Building Committee Meeting #39

June 1st, 2020

slide-5
SLIDE 5

School Building Committee| April 06, 2020

4. Project Budget

5

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

Project Budget (PFA November 2019) Current Project Budget

(subject to MSBA BRR approval)

Committed Amount

(under contract)

Amount Paid to Date

(entered to Pro Pay)

Balance to Finish

(Current Project Budget vs. Paid to Date)

Feasibility Study

$800,000 $800,000 $725,524 $701,840 $98,160

Administration

$145,000 $145,000 $0 $0 $145,000

Owners Project Manager

$2,050,000 $2,050,000 $2,050,000 $102,000 $1,948,000

Architecture & Design

$6,250,000 $6,250,000 $6,250,000 $1,005,469 $5,244,531

Construction

$64,679,981 $64,679,981 $0 $0 $64,679,981

  • Misc. Project Cost

$475,000 $475,000 $0 $0 $475,000

FF & E

$2,460,000 $2,460,000 $0 $0 $4,760,000

Contingency

$3,740,019 $3,740,019

  • $3,740,019

TOTALPROJECT BUDGET $80,600,000 $80,600,000 $9,025,524 $1,809,309 $78,790,691

slide-6
SLIDE 6

School Building Committee| April 06, 2020 6

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

4. Project Budget PFA Budget $80,600,000 The MSBA reimbursement rate for this project is: 59.28% Amount Submitted to MSBA – Pro Pay 1-9 $1,809,309 Amount Reimbursed by MSBA to date – Pro Pay 1-9 $1,068,154 There are currently no Pay Pay submission under review at MSBA

slide-7
SLIDE 7

School Building Committee| April 06, 2020 7

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

Module 6 Reference Description 6B.1 Basic Project Information – Enrollment, GSF area, Project Type, Delivery Method 6B.2.1 OPM Submittal Review and Coordination 6A.2.1

  • OPM’s recommendation
  • OPM’s evaluation of design
  • Commissioning Consultants Review
  • Districts response to MSBA Design Development comments

6A.2.2 Project Schedule 6A.2.3 Project Scope and Budget

  • OPM Construction Cost estimate
  • OPM Reconciliation of the OPM/Designer Construction Cost estimate
  • Update Construction Estimate Comparison Form
  • Updated Total Project Budget

6. MSBA Module 6 Detailed Design – 60% Construction Documents Submission

slide-8
SLIDE 8

School Building Committee| April 06, 2020 8

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

Module 6 Reference Description 6B.3.1 Designer Deliverables

  • Updated Work Plan
  • Basis of Design Narratives – Architectural, Structural, Civil, MEP +FP
  • Building Code Analysis
  • List of Proprietary Items
  • Interior Material and Color Selections
  • Engineering Calculations – Structural, Energy Model, LLC, HVAC, Electric Load
  • Security and Visual Requirements – Entrance Design, Classroom Locksets, Interior Visibility, alternative Entry Locations
  • Facility & Maintenance – Training, HVAC, BMS, Lighting, Controls, Cleaning, Access
  • Quality Control Narratives – Coordination of Spec & Drawings, Filed Sub Bid Work, Equipment & Power

6B.3.2 Updated Space Summary – Explanation of Deviations

  • DESE Re Submission (IF REQUIRED)

6B.3.3 Project Approvals – State & Local Approvals, Utility Company Coordination

6. MSBA Module 6 Detailed Design – Design Development Submission

slide-9
SLIDE 9

School Building Committee| April 06, 2020 9

MITCHELL ELEMENTARY SCHOOL | BRIDGEWATER MA

Module 6 Reference Description 6B.3.4 Designer Construction Cost Estimate 6B.3.5 60% Construction Documents Drawings 6B.3.6 60% Construction Documents Project Manual

6. MSBA Module 6 Detailed Design – Design Development Submission