G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA S CHOOL B UILDING C OMMITTEE MEETING A PRIL 06, 2020 Raymond Design Associates M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 1. Progress Report DPI coordinated the submission of the


  1. G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA S CHOOL B UILDING C OMMITTEE MEETING A PRIL 06, 2020 Raymond Design Associates

  2. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 1. Progress Report • DPI coordinated the submission of the Design Development documents to MSBA on March 16 th . MBSA reviewed the DD submission and issued their review comments on March 30 th . The District has 14 days in which to respond to MSBA’s comments. • RDA and DPI, representatives from the School District have been meeting virtually as a working group to solicit feedback on the current design. • RDA and their consultant met virtually with the Conservation Commission and representatives form other Town Departments to review permitting requirement for the project. • RDA and their consultants are continuing with the development of the 60% Construction Documents as noted in the MSBA design review template. School Building Committee| April 06, 2020 2

  3. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 2. Schedule and Milestones: • Demolition of Existing School April 2020 – August 2020 • Bid demo package April 15 – April 30 • Review/Award demo package May 04 – May 19, • Demo existing building May 19 – August 30 • 60% Construction Documents (60% CD) March 2020 – June 2020 • MSBA 60% CD Submission June 05, 2020 • 90% Construction Documents (90% CD) June 2020 – August 2020 • MSBA 90% CD Submission August 28, 2020 • 100% Construction (Bid) Documents September – October 2020 • Bidding and Award October – November 2020 • Construction December 2020 – July 2022 School Building Committee| April 06, 2020 3

  4. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 3. Upcoming Meetings • April 6 th , 2020 School Building Committee Meeting #36 • Building Interiors Interior Spaces – Cafeteria, Gym, Music, Maker Space, Art • Interior Finishes - Materials • Site – Traffic, Parking, Deliveries, Snow Storage • Permitting Update • Demo Logistics Review & Schedule • April 27 h , 2020 School Building Committee Meeting #37 • Building Interiors Interior Spaces – Admin, Nurse, Typical Classroom, ELS, SPED • Interior Finishes - Materials • Site – Play Areas, Lighting and Site Improvements • Exterior Elevations and Materials • Electrical and Technology • Plumbing and Bathroom Fixtures • School Building Committee Meeting #38 May 4 th , 2020 • June 1 st , 2020 School Building Committee Meeting #39 School Building Committee| April 06, 2020 4

  5. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 4. Project Budget Current Project Committed Amount Amount Paid to Date Balance to Finish Project Budget (under contract) (entered to Pro Pay) Budget (Current Project Budget vs. Paid ( PFA November 2019) to Date) (subject to MSBA BRR approval) Feasibility Study $800,000 $800,000 $725,524 $701,840 $98,160 Administration $145,000 $145,000 $0 $0 $145,000 Owners Project $2,050,000 $2,050,000 $2,050,000 $102,000 $1,948,000 Manager Architecture & Design $6,250,000 $6,250,000 $6,250,000 $1,005,469 $5,244,531 Construction $64,679,981 $64,679,981 $0 $0 $64,679,981 Misc. Project Cost $475,000 $475,000 $0 $0 $475,000 FF & E $2,460,000 $2,460,000 $0 $0 $4,760,000 Contingency $3,740,019 $3,740,019 - - $3,740,019 $78,790,691 TOTALPROJECT BUDGET $80,600,000 $80,600,000 $9,025,524 $1,809,309 School Building Committee| April 06, 2020 5

  6. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 4. Project Budget PFA Budget $80,600,000 The MSBA reimbursement rate for this project is: 59.28% Amount Submitted to MSBA – Pro Pay 1-9 $1,809,309 Amount Reimbursed by MSBA to date – Pro Pay 1-9 $1,068,154 There are currently no Pay Pay submission under review at MSBA School Building Committee| April 06, 2020 6

  7. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 6. MSBA Module 6 Detailed Design – 60% Construction Documents Submission Module 6 Reference Description 6B.1 Basic Project Information – Enrollment, GSF area, Project Type, Delivery Method 6B.2.1 OPM Submittal Review and Coordination • 6A.2.1 OPM’s recommendation • OPM’s evaluation of design • Commissioning Consultants Review • Districts response to MSBA Design Development comments 6A.2.2 Project Schedule 6A.2.3 Project Scope and Budget • OPM Construction Cost estimate • OPM Reconciliation of the OPM/Designer Construction Cost estimate • Update Construction Estimate Comparison Form • Updated Total Project Budget School Building Committee| April 06, 2020 7

  8. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 6. MSBA Module 6 Detailed Design – Design Development Submission Module 6 Reference Description 6B.3.1 Designer Deliverables • Updated Work Plan • Basis of Design Narratives – Architectural, Structural, Civil, MEP +FP • Building Code Analysis • List of Proprietary Items • Interior Material and Color Selections • Engineering Calculations – Structural, Energy Model, LLC, HVAC, Electric Load • Security and Visual Requirements – Entrance Design, Classroom Locksets, Interior Visibility, alternative Entry Locations • Facility & Maintenance – Training, HVAC, BMS, Lighting, Controls, Cleaning, Access • Quality Control Narratives – Coordination of Spec & Drawings, Filed Sub Bid Work, Equipment & Power 6B.3.2 Updated Space Summary – Explanation of Deviations • DESE Re Submission (IF REQUIRED) 6B.3.3 Project Approvals – State & Local Approvals, Utility Company Coordination School Building Committee| April 06, 2020 8

  9. M ITCHELL E LEMENTARY S CHOOL | B RIDGEWATER MA 6. MSBA Module 6 Detailed Design – Design Development Submission Module 6 Reference Description 6B.3.4 Designer Construction Cost Estimate 6B.3.5 60% Construction Documents Drawings 6B.3.6 60% Construction Documents Project Manual School Building Committee| April 06, 2020 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.