- G. H. MITCHELL ELEMENTARY SCHOOL
BRIDGEWATER, MA
TOWN COUNCIL PRESENTATION
AUGUST 6, 2019
Raymond Design Associates
S CHEMATIC D ESIGN | N EW C ONSTRUCTION STUDY OPTION C6.1 On April - - PowerPoint PPT Presentation
G. H. M ITCHELL E LEMENTARY S CHOOL B RIDGEWATER , MA T OWN C OUNCIL P RESENTATION A UGUST 6, 2019 Raymond Design Associates R ECAP | P ROJECT TO D ATE Fall, 2019: April July 2019: Anticipated town-wide February 2015: Development of
BRIDGEWATER, MA
AUGUST 6, 2019
Raymond Design Associates
Town Council Presentation | August 6, 2019 2
February 2015: Roof Collapse at Mitchell Elementary School followed by sprinkler system pipe failure that led to flooding of “Central Wing” November 2017 – May 2018: Public procurement, Interviews, Selections, and MSBA approvals for hiring of Owner’s Project Manager and Architect April – July 2019: Development of schematic design and cost estimates Community Workshops and Public Presentations to gather input and comments on the new Mitchell School design January 14, 2016: Statement of Interest submitted to Massachusetts School Building Authority (MSBA) February 15, 2017: MSBA voted Mitchell ES into Eligibility Period. June 10, 2017: Bridgewater voters approve $800,000 to fund Feasibility Study June 2018 – April 2019: Study of location/site options (7 sites studied), grade configuration options (PreK – 2 or PreK-3), and existing conditions of building and site at 500 South Street.
MSBA approval and invitation to Schematic Design phase. August 2019: Anticipated MSBA Board of Directors meeting to receive approval of Schematic Design. Next step, Funding the Project! Fall, 2019: Anticipated town-wide ballot to vote for funding design/construction of the new Mitchell Elementary School
We Are Here
Town Council Presentation | August 6, 2019 3
On April 10, 2019 the MSBA Board of Directors approved the Preferred Option (C6.1) and invited the project to proceed in to the Schematic Design Phase
http://bridgewaterschoolproject.com/why-build-option-c6-1/
Town Council Presentation | August 6, 2019 4
meet educational program
spaces
Security / Centralized Admin
and after school programs
Town Council Presentation | August 6, 2019 5
Town Council Presentation | August 6, 2019 6
Town Council Presentation | August 6, 2019 7
Town Council Presentation | August 6, 2019 8
(approx. 302)
circulation
areas
(approx. 63 cars can queue on- site)
(right turn only)
benches in playgrounds
Town Council Presentation | August 6, 2019 9
Town Council Presentation | August 6, 2019 10
entrance
volleyball court with 120 bleacher seats
seating for 375 (one of the largest meeting spaces in town)
between Cafeteria and Gym to allow for expanded or programs
and outdoor learning spaces
Town Council Presentation | August 6, 2019 11
MITCHELL SCHOOL – NEW CONSTRUCTION Option C6.1 FEASIBILITY STUDY (OPM, Designer, Environmental, Site, Other)
$800,000
CONSTRUCTION (Demo, Foundation, Shell, Interiors, Mechanical-Electrical-Plumbing & Fire Protection, Fixtures, Sitework)
$64,679,981
ADMINISTRATION, OPM, ARCHITECT, FF&E, OTHER MISC. (Legal, Printing, Advertising, Utility, Permitting, Moving, Inspections)
$11,380,000
CONTINGENCY (Owners and Construction Contingency)
$3,740,019
TOTALPROJECT
$80,600,000
MSBA Reimbursement Rate w/ Incentives for Eligible Costs 59.28%
Example ineligible costs: legal fees, advertising, printing, moving, permits, utility costs Example capped costs: Construction Cost ($333/SF), Furniture, Fixtures and Equipment ($2,400/student), Site costs (8% max)
Estimated MSBA “Effective” Reimbursement Rate of Total Project Costs 41.97% Anticipated MSBA Reimbursement
$33,828,113 Anticipated Town Share $46,771,887
Town Council Presentation | August 6, 2019 12
regulations.
Maximum Total Facilities Grant.
District must:
secure local authorization and funding within 120 days of the MSBA Board's vote.
Town Council Presentation | August 6, 2019 13
invitation”. In a typical year, the MSBA receives more than 80 statements of interest and invites less than 15 districts in to their eligibility period. There is no guarantee that the district would receive another invitation to eligibility.
in the future based on MSBA funding capacity and future changes to policy.
Boston region at a 4.42% annual increase from January 2018 to January 2019. Any future project is estimated to have a greater construction cost due to industry-wide cost increases.
Town Council Presentation | August 6, 2019 14
Town Council Presentation | August 6, 2019 15