DRAFT DRAFT Option Comparison Option Comparison Alignment of - - PowerPoint PPT Presentation

draft draft
SMART_READER_LITE
LIVE PREVIEW

DRAFT DRAFT Option Comparison Option Comparison Alignment of - - PowerPoint PPT Presentation

All Tunnel Alignment All Tunnel Alignment & Option Comparisons & Option Comparisons Presented to: Presented to: BDCP Steering Committee BDCP Steering Committee December 3, 2009 December 3, 2009 DRAFT DRAFT Option Comparison


slide-1
SLIDE 1

All Tunnel Alignment All Tunnel Alignment & Option Comparisons & Option Comparisons Presented to: Presented to: BDCP Steering Committee BDCP Steering Committee

December 3, 2009 December 3, 2009

DRAFT DRAFT

slide-2
SLIDE 2

Option Comparison Option Comparison

  • Alignment of Options

Alignment of Options

  • Major Features

Major Features

  • Comparison Tables

Comparison Tables

  • Pros & Cons

Pros & Cons

  • Mitigation

Mitigation – – Environmental Environmental – – Cost Cost

DRAFT DRAFT

slide-3
SLIDE 3

Alignment Alignment Comparison Comparison

DRAFT DRAFT

slide-4
SLIDE 4
  • 40 miles of canals
  • 4 short tunnels
  • 8 siphons
  • 630-acre forebay
  • 5 intake facilities with fish

screens along the Sacramento River

  • 6 pump stations

ICF ICF -

  • East

East

DRAFT DRAFT

slide-5
SLIDE 5

ICF ICF -

  • West

West

  • 38 miles of canals
  • 17 miles of tunnels
  • 12 siphons
  • 580-acre forebay
  • 5 intake facilities along the

Sacramento River

  • 6 pump stations

DRAFT DRAFT

slide-6
SLIDE 6

All Tunnel Option All Tunnel Option

  • Approximately 43 miles of tunnels
  • 35 miles twin bore 33’

ID

  • 8 miles single bore 23’

and 33’ ID intake tunnels

  • 750-acre Intermediate Forebay
  • 630-acre Byron Tract Forebay
  • 5 intake facilities along the

Sacramento River

  • 6 pump stations
  • Surge Towers
  • Gravity Bypass System

DRAFT DRAFT

slide-7
SLIDE 7

Typical Canal Cross Section Typical Canal Cross Section

DRAFT DRAFT

slide-8
SLIDE 8

M-30 By-Pass Sur Túnel Norte, Madrid EPB Shield – 15.200 m diameter

DRAFT DRAFT

slide-9
SLIDE 9

Tunnel Boring Machine (TBM) Diameter Development Tunnel Boring Machine (TBM) Diameter Development

DRAFT DRAFT

slide-10
SLIDE 10

Major Features Major Features

DRAFT DRAFT

slide-11
SLIDE 11

Comparisons Comparisons

– – Intakes Intakes – – Fish Screens Fish Screens – – Footprint Footprint – – Annual Energy Cost Annual Energy Cost – – TDH TDH – – Construction Power Construction Power – – Conventional Equipment Conventional Equipment – – O & M O & M – – Schedule Schedule

DRAFT DRAFT

slide-12
SLIDE 12

Footprint Footprint

DRAFT DRAFT

slide-13
SLIDE 13

Annual Energy and TDH Annual Energy and TDH

DRAFT DRAFT DRAFT DRAFT

slide-14
SLIDE 14

Construction Power & Truck Construction Power & Truck Hours Hours

DRAFT DRAFT

slide-15
SLIDE 15

Operations & Maintenance Operations & Maintenance

DRAFT DRAFT

slide-16
SLIDE 16

Construction Schedule Construction Schedule

DRAFT DRAFT

slide-17
SLIDE 17

Engineering and Construction Engineering and Construction Pros and Cons Pros and Cons

DRAFT DRAFT

slide-18
SLIDE 18

Conveyance Land Costs Conveyance Land Costs

  • Does not include state and federal owned land in footprint.
  • Does not include any cost for acquiring subsurface

easements for tunnels

DRAFT DRAFT

slide-19
SLIDE 19
  • Acre tallies exclude state and federal land

Acre tallies exclude state and federal land

  • Unit land costs from Chap. 8 common assumptions

Unit land costs from Chap. 8 common assumptions

  • Costs include 7.3% adder for due diligence and other transaction

Costs include 7.3% adder for due diligence and other transaction costs costs

  • Acreage categories: native veg., field crop, truck crop, orchard

Acreage categories: native veg., field crop, truck crop, orchard, vineyard, semi , vineyard, semi-

  • ag

ag, non , non-

  • residential urban, residential urban

residential urban, residential urban

  • Avg

Avg land cost depends on mix of acreage in footprint land cost depends on mix of acreage in footprint

  • Residential structures priced at county average

Residential structures priced at county average

  • Assumes land acquired thru Fee

Assumes land acquired thru Fee-

  • Title. Easements would have lower unit cost
  • Title. Easements would have lower unit cost
  • Estimate does not consider price dynamics (land prices could get

Estimate does not consider price dynamics (land prices could get bid up) bid up)

  • Estimate does not consider extraordinary transaction costs

Estimate does not consider extraordinary transaction costs

  • Estimate does not include contingency

Estimate does not include contingency

  • Preliminary estimate for comparative purposes only

Preliminary estimate for comparative purposes only --

  • - land costs for surface alignments

land costs for surface alignments 3 3-

  • 4 times greater than for tunnel

4 times greater than for tunnel

Conveyance Land Cost Notes Conveyance Land Cost Notes

DRAFT DRAFT

slide-20
SLIDE 20
  • Habitats, agricultural lands, and developed lands based on DFG 2

Habitats, agricultural lands, and developed lands based on DFG 2007 007 Vegetation Cover Survey as interpreted into the SAIC BDCP Natura Vegetation Cover Survey as interpreted into the SAIC BDCP Natural l Communities GIS Data Layer. Communities GIS Data Layer.

  • Effects on habitats calculated based on conveyance and associate

Effects on habitats calculated based on conveyance and associated d facilities footprints provided by DWR engineers. facilities footprints provided by DWR engineers.

  • Permanent disturbance assumed for canal, intake facilities, pump

Permanent disturbance assumed for canal, intake facilities, pump stations, stations, reservoirs. reservoirs.

  • Temporary disturbance assumed for siphons, pipelines, borrow and

Temporary disturbance assumed for siphons, pipelines, borrow and spoils spoils areas, and work areas. areas, and work areas.

  • Tunnels were assumed to have no impact.

Tunnels were assumed to have no impact.

Environmental Impact Environmental Impact Evaluation Methods Evaluation Methods

DRAFT DRAFT

slide-21
SLIDE 21

Environmental Impacts Environmental Impacts

In acres (unless otherwise indicated); P = permanent, T = tempor In acres (unless otherwise indicated); P = permanent, T = temporary ary

DRAFT DRAFT

West Alignment East Alignment Tunnel Sensitive Habitats

Riparian 23 P 51 T 36 P 31 T 15 P 1 T Alkali Wetland 37 P 79 T 8 P 0 T 8 P 0 T Tidal Marsh 0 P 6 T 11 P 2 T 6 P 0 T

Grassland

280 P 400 T 390 P 330 T 200 P 150 T

Agricultural Land

7,000 P 9,600 T 7,300 P 9,000 T 2,100 P 3,900 T

Built Environment

Developed lands 194 224 26 Transportation (crossings) 20 roads 18 roads Navigation (siphons) 12 water courses 8 water courses

West Alignment East Alignment Tunnel Sensitive Habitats

Riparian 23 P 51 T 36 P 31 T 15 P 1 T Alkali Wetland 37 P 79 T 8 P 0 T 8 P 0 T Tidal Marsh 0 P 6 T 11 P 2 T 6 P 0 T

Grassland

280 P 400 T 390 P 330 T 200 P 150 T

Agricultural Land

7,000 P 9,600 T 7,300 P 9,000 T 2,100 P 3,900 T

Built Environment

Developed lands 194 224 26 Transportation (crossings) 20 roads 18 roads Navigation (siphons) 12 water courses 8 water courses

slide-22
SLIDE 22

Giant Garter Snake Habitat Impacts Giant Garter Snake Habitat Impacts

(P = permanent, T = temporary) (P = permanent, T = temporary)

DRAFT DRAFT

slide-23
SLIDE 23

Rough Mitigation Land Costs Rough Mitigation Land Costs

Assumptions: 1) Habitat impacts mitigated through proposed BDCP restoration of tidal marsh/aquatic and riparian habitats are not included in impact total 2) Assumed two acres of mitigation land for every acre of permanent impact and one acre of mitigation land for every acre of temporary impact – general assumption without taking into consideration habitat function 3) Land acquisition cost of $10,000 per acre

DRAFT DRAFT

slide-24
SLIDE 24

Cost Cost

These Numbers are Preliminary and Subject to Change These Numbers are Preliminary and Subject to Change

DRAFT DRAFT

slide-25
SLIDE 25

Questions & Answers Questions & Answers