Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR - PowerPoint PPT Presentation

West Community Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR Time Item Topic 5:30pm 1 Welcome, introductions and apologies and actions from previous meeting 5:40pm 2 Project Update Tea break 6:45pm 3 7.00pm 4


  1. West Community Liaison Group 7 November 2018

  2. Introduction JIM WILLIAMSON - CHAIR

  3. Time Item Topic 5:30pm 1 Welcome, introductions and apologies and actions from previous meeting 5:40pm 2 Project Update Tea break 6:45pm 3 7.00pm 4 Presentation of project videos and photos 7.10pm 5 Member feedback and questions 7.25pm 6 Action summary and close 7.30pm 7 Meeting close

  4. WGTA Update ANTHONY HAVERS WEST GATE TUNNEL AUTHORITY

  5. Caretaker conventions • Issued by the Department of Premier and Cabinet • Started: 6pm on Tuesday, 30 Oct 2018 • End: When the election result is clear • Guidelines on handling government business during the 2018 State Election period • Available on Department of Premier and Cabinet's website at www.dpc.vic.gov.au/caretaker

  6. Cycling, Walking and Pedestrian Update Charles Fairbairn CPBJH Joint Venture

  7. 7 More than a road Reducing conflicts between trucks + local road users • 14km of new + improved walking + cycling paths • 2.5km elevated veloway 9 hectares of new open space including parks + wetlands

  8. New and upgraded paths to make cycling safer

  9. New and upgraded paths to make cycling safer • New off-road path between Fogarty Avenue and Hyde Street • A new bridge over Whitehall Street will create a link between Yarraville Gardens and the Maribyrnong River • Upgraded cycling facilities along Hyde Street from Somerville Road • A new bridge over Footscray Road and a new pedestrian and cycling bridge at Dynon Road

  10. Construction Update Charles Fairbairn CPBJH Joint Venture

  11. 11 Current and upcoming works Williamstown Road interchange Temporary noise walls / Rosala Avenue walking and cycling bridge Fogarty Avenue / The Avenue Millers Road Freeway widening and Temporary noise walls / interchange temporary noise walls Muir Street walking and cycling bridge

  12. 12 Williamstown Road interchange

  13. 13 Williamstown Road interchange continued November/December • Building the permanent inbound exit ramp at Williamstown Road • Removal of existing noise wall – end of Williamstown Road inbound exit ramp • Widening the inbound bridge (freeway) over Williamstown Road • Excavation of the shaft for the sewer relocation works across Williamstown Road interchange • Widening the West Gate Freeway centre median Williamstown Road freeway bridge widening works (looking West)

  14. 14 Williamtown Road interchange continued November/December Williamstown Road bridge widening (over freeway) • Night time closures of the West Gate Freeway to jack up the existing bridge beams and replace the bearings • Night time closures of Williamstown Road to lift new concrete beams into place • Concrete pour to join the existing bridge to the newly constructed bridge Traffic switch late November • The inbound carriageway will be switched onto newly constructed lane on the approach to Williamstown Road bridge over the freeway

  15. 15 Fogarty Avenue

  16. 16 Fogarty Avenue continued November – mid 2019 • Temporary noise wall installation • Temporary noise walls will be installed on Fogarty Avenue between the Hockey Club and Wembley Avenue • Existing noise walls will be removed once temporary noise walls installed • Temporary noise walls will remain in place until construction of the new noise walls are complete Installing foundations for the noise walls

  17. Fogarty Avenue / The Avenue November/December Fogarty Avenue • 66kV relocation works are ongoing • Stormwater drainage started in late October (completed in stages) – deeper and wider trenches required • Current stage - closure of Fogarty Avenue / The Avenue until end of November Newport Rail bridge (The Avenue) Preparatory works to start in late November including: • Vegetation removal • Setting up traffic barriers • Piling and excavation works Trenching works on Fogarty Avenue

  18. South of the West Gate Freeway November/December • Piling works for new permanent noise • walls between Williamstown Road (Melbourne Road) and Newport Rail line • Piling works for new Muir Street walking and cycling bridge • Installation of temporary noise wall between Williamstown Road (Melbourne Road) and the Newport Rail line continuing Temporary noise walls

  19. 19 Millers Road interchange

  20. 20 Millers Road interchange continued November/December Widening Millers Road underneath the freeway • New southbound lane underneath the freeway • Work switches to building the additional northbound lane later this year Building temporary and permanent ramps • Millers Road temporary inbound and outbound exit ramps • Millers Road permanent inbound entry ramp Tree removal • Millers Road outbound exit ramp and sections along Beevers Street Beevers Street • 66kv relocation works still in planning phase

  21. 21 Millers Road interchange continued Walking and cycling bridge – Rosala Paringa Road works began in late Avenue / Richards Court September • • Setting up site in reserve near Buchanan Road Long-term closure of Paringa Road from Millers through to Primula Avenue Road • • Piling works for foundation of walking and cycling Gas and telecommunication relocations bridge underway • Rosala Avenue pedestrian overpass will remain open during these works Installation of temporary noise walls • Adjacent to residential fences from the reserve near Buchanan Road through to Millers Road • Millers Road outbound exit ramp and sections along Beevers Street Long term closure of Paringa Road from Millers Road

  22. 22 West Gate Freeway - Chambers Road to Grieve Parade

  23. 23 West Gate Freeway - Chambers Road to Grieve Parade November/December • Local road closures • Temporary and new noise walls • Widening works in this area require • Installing a temporary noise wall between some temporary road closures to be Freemans Road and Chambers Road put in place between: • Removing the existing noise wall following • Freemans Road; the installation of the temporary noise wall • Misten Avenue; • Foundations for the new permanent noise • Rosala Avenue; and wall with piling starting early next year • Irwin Avenue. Access to all properties will be maintained although some properties will experience changes to the way they access their property.

  24. 24 Postponed works • 220kv power line works, monopole installation and Muir Street pedestrian overpass • Temporary closure of the pedestrian overpass connecting Muir Street and Fogarty Avenue has been postponed • Enabling the safe relocation of high voltage power lines • Working with AusNet on determining the best time to complete these works.

  25. Keeping communities informed SEPTEMBER 2018 OCTOBER 2018 101 incoming 79 incoming 8 door 8 door calls and calls and knocking knocking emails emails events events 3 notifications 8 notifications 8 face to face delivered to 8 face to face delivered to meetings 1130 meetings 350 properties properties

  26. 26 Who are we hearing from? Millers Road Fogarty Avenue 11% of enquires 11% of enquires Other queries relate to Williamstown Road Beevers Street property condition surveys 7% of enquires 8% of enquires and traffic updates

  27. Employment and learning opportunities Outcome to 31 Group Commitment Comment October 2018 230 CPBJH JV 400 – 600 Women 525 181 AJJV 114 subcontractors Significant opportunity in construction roles 100 – 150 Retrenched automotive workers 10 yet to commence People seeking asylum and new migrants The achievement is 300% of the stretch 35 – 50 142 (less than 52 weeks) target People who identify as Aboriginal or Torres 80 -90 40 Strait Islander 30 – 40 People living with disability 13 10 – 15 Students in juvenile detention (SWPL) Yet to commence Students from disadvantaged backgrounds 20 – 25 Yet to commence (SWPL)

  28. Presentation of project videos and photos DAVID CLEMENTS TRANSURBAN

  29. West Gate Freeway 10+ km New inbound Extensive works to remove Relocating 25 gantries + exit ramp of traffic safety barriers utilities 78 light poles 29

  30. West Gate Freeway West Gate Freeway Widening works underway

  31. West Gate Freeway Tunnels Getting ready to ship first TBM

  32. THANK YOU

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.