Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR - - PowerPoint PPT Presentation
Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR - - PowerPoint PPT Presentation
West Community Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR Time Item Topic 5:30pm 1 Welcome, introductions and apologies and actions from previous meeting 5:40pm 2 Project Update Tea break 6:45pm 3 7.00pm 4
JIM WILLIAMSON - CHAIR
Introduction
Time Item Topic 5:30pm 1 Welcome, introductions and apologies and actions from previous meeting 5:40pm 2 Project Update 6:45pm 3 Tea break 7.00pm 4 Presentation of project videos and photos 7.10pm 5 Member feedback and questions 7.25pm 6 Action summary and close 7.30pm 7 Meeting close
ANTHONY HAVERS WEST GATE TUNNEL AUTHORITY
WGTA Update
Caretaker conventions
- Issued by the Department of Premier and Cabinet
- Started: 6pm on Tuesday, 30 Oct 2018
- End: When the election result is clear
- Guidelines on handling government business during the 2018 State
Election period
- Available on Department of Premier and Cabinet's website at
www.dpc.vic.gov.au/caretaker
Charles Fairbairn CPBJH Joint Venture
Cycling, Walking and Pedestrian Update
More than a road
7
Reducing conflicts between trucks + local road users
- 14km of new +
improved walking + cycling paths
- 2.5km elevated
veloway 9 hectares of new open space including parks + wetlands
New and upgraded paths to make cycling safer
New and upgraded paths to make cycling safer
- New off-road path between Fogarty
Avenue and Hyde Street
- A new bridge over Whitehall Street will
create a link between Yarraville Gardens and the Maribyrnong River
- Upgraded cycling facilities along Hyde
Street from Somerville Road
- A new bridge over Footscray Road and
a new pedestrian and cycling bridge at Dynon Road
Charles Fairbairn CPBJH Joint Venture
Construction Update
Current and upcoming works
11
Fogarty Avenue / The Avenue Williamstown Road interchange Millers Road interchange Temporary noise walls / Muir Street walking and cycling bridge Freeway widening and temporary noise walls Temporary noise walls / Rosala Avenue walking and cycling bridge
Williamstown Road interchange
12
Williamstown Road interchange continued
- Building the permanent inbound exit ramp at
Williamstown Road
- Removal of existing noise wall – end of
Williamstown Road inbound exit ramp
- Widening the inbound bridge (freeway) over
Williamstown Road
- Excavation of the shaft for the sewer relocation
works across Williamstown Road interchange
- Widening the West Gate Freeway centre
median
Williamstown Road freeway bridge widening works (looking West)
November/December
13
Williamtown Road interchange continued
14
Williamstown Road bridge widening (over freeway)
- Night time closures of the West Gate Freeway to jack up the existing bridge
beams and replace the bearings
- Night time closures of Williamstown Road to lift new concrete beams into place
- Concrete pour to join the existing bridge to the newly constructed bridge
Traffic switch late November
- The inbound carriageway will be switched onto newly constructed lane on the
approach to Williamstown Road bridge over the freeway
November/December
Fogarty Avenue
15
Fogarty Avenue continued
- Temporary noise wall installation
- Temporary noise walls will be installed on
Fogarty Avenue between the Hockey Club and Wembley Avenue
- Existing noise walls will be removed once
temporary noise walls installed
- Temporary noise walls will remain in place
until construction of the new noise walls are complete November – mid 2019
Installing foundations for the noise walls
16
Fogarty Avenue / The Avenue
November/December
Fogarty Avenue
- 66kV relocation works are ongoing
- Stormwater drainage started in late
October (completed in stages) – deeper and wider trenches required
- Current stage - closure of Fogarty
Avenue / The Avenue until end of November Newport Rail bridge (The Avenue) Preparatory works to start in late November including:
- Vegetation removal
- Setting up traffic barriers
- Piling and excavation works
Trenching works on Fogarty Avenue
South of the West Gate Freeway
November/December
- Piling works for new permanent noise
- walls between Williamstown Road
(Melbourne Road) and Newport Rail line
- Piling works for new Muir Street walking
and cycling bridge
- Installation of temporary noise wall
between Williamstown Road (Melbourne Road) and the Newport Rail line continuing
Temporary noise walls
Millers Road interchange
19
Millers Road interchange continued
Widening Millers Road underneath the freeway
- New southbound lane underneath the freeway
- Work switches to building the additional northbound lane later this year
Building temporary and permanent ramps
- Millers Road temporary inbound and outbound exit ramps
- Millers Road permanent inbound entry ramp
Tree removal
- Millers Road outbound exit ramp and sections along Beevers Street
Beevers Street
- 66kv relocation works still in planning phase
November/December
20
Millers Road interchange continued
Walking and cycling bridge – Rosala Avenue / Richards Court
- Setting up site in reserve near Buchanan Road
through to Primula Avenue
- Piling works for foundation of walking and cycling
bridge
- Rosala Avenue pedestrian overpass will remain
- pen during these works
Installation of temporary noise walls
- Adjacent to residential fences from the reserve
near Buchanan Road through to Millers Road
- Millers Road outbound exit ramp and sections
along Beevers Street
Paringa Road works began in late September
- Long-term closure of Paringa Road from Millers
Road
- Gas and telecommunication relocations
underway
Long term closure of Paringa Road from Millers Road
21
West Gate Freeway - Chambers Road to Grieve Parade
22
West Gate Freeway - Chambers Road to Grieve Parade
23
- Local road closures
- Widening works in this area require
some temporary road closures to be put in place between:
- Freemans Road;
- Misten Avenue;
- Rosala Avenue; and
- Irwin Avenue.
Access to all properties will be maintained although some properties will experience changes to the way they access their property.
- Temporary and new noise walls
- Installing a temporary noise wall between
Freemans Road and Chambers Road
- Removing the existing noise wall following
the installation of the temporary noise wall
- Foundations for the new permanent noise
wall with piling starting early next year
November/December
Postponed works
- 220kv power line works, monopole
installation and Muir Street pedestrian
- verpass
- Temporary closure of the pedestrian
- verpass connecting Muir Street and
Fogarty Avenue has been postponed
- Enabling the safe relocation of high
voltage power lines
- Working with AusNet on determining
the best time to complete these works.
24
Keeping communities informed
101 incoming calls and emails 3 notifications delivered to 1130 properties 8 face to face meetings 8 door knocking events 79 incoming calls and emails 8 notifications delivered to 350 properties 8 face to face meetings 8 door knocking events
SEPTEMBER 2018 OCTOBER 2018
Who are we hearing from?
26
Fogarty Avenue 11% of enquires Millers Road 11% of enquires Williamstown Road 8% of enquires Beevers Street 7% of enquires
Other queries relate to property condition surveys and traffic updates
Employment and learning opportunities
Group Commitment Outcome to 31 October 2018 Comment Women 400 – 600 525 230 CPBJH JV 181 AJJV 114 subcontractors Retrenched automotive workers 100 – 150 10 Significant opportunity in construction roles yet to commence People seeking asylum and new migrants (less than 52 weeks) 35 – 50 142 The achievement is 300% of the stretch target People who identify as Aboriginal or Torres Strait Islander 80 -90 40 People living with disability 30 – 40 13 Students in juvenile detention (SWPL) 10 – 15 Yet to commence Students from disadvantaged backgrounds (SWPL) 20 – 25 Yet to commence
DAVID CLEMENTS TRANSURBAN
Presentation of project videos and photos
29
West Gate Freeway
10+ km
- f traffic safety barriers
New inbound
exit ramp
Relocating
utilities
Extensive works to remove
25 gantries + 78 light poles
West Gate Freeway
West Gate Freeway
Widening works underway
West Gate Freeway
Tunnels
Getting ready to ship first TBM