Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR - - PowerPoint PPT Presentation

liaison group
SMART_READER_LITE
LIVE PREVIEW

Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR - - PowerPoint PPT Presentation

West Community Liaison Group 7 November 2018 Introduction JIM WILLIAMSON - CHAIR Time Item Topic 5:30pm 1 Welcome, introductions and apologies and actions from previous meeting 5:40pm 2 Project Update Tea break 6:45pm 3 7.00pm 4


slide-1
SLIDE 1

West Community Liaison Group

7 November 2018

slide-2
SLIDE 2

JIM WILLIAMSON - CHAIR

Introduction

slide-3
SLIDE 3

Time Item Topic 5:30pm 1 Welcome, introductions and apologies and actions from previous meeting 5:40pm 2 Project Update 6:45pm 3 Tea break 7.00pm 4 Presentation of project videos and photos 7.10pm 5 Member feedback and questions 7.25pm 6 Action summary and close 7.30pm 7 Meeting close

slide-4
SLIDE 4

ANTHONY HAVERS WEST GATE TUNNEL AUTHORITY

WGTA Update

slide-5
SLIDE 5

Caretaker conventions

  • Issued by the Department of Premier and Cabinet
  • Started: 6pm on Tuesday, 30 Oct 2018
  • End: When the election result is clear
  • Guidelines on handling government business during the 2018 State

Election period

  • Available on Department of Premier and Cabinet's website at

www.dpc.vic.gov.au/caretaker

slide-6
SLIDE 6

Charles Fairbairn CPBJH Joint Venture

Cycling, Walking and Pedestrian Update

slide-7
SLIDE 7

More than a road

7

Reducing conflicts between trucks + local road users

  • 14km of new +

improved walking + cycling paths

  • 2.5km elevated

veloway 9 hectares of new open space including parks + wetlands

slide-8
SLIDE 8

New and upgraded paths to make cycling safer

slide-9
SLIDE 9

New and upgraded paths to make cycling safer

  • New off-road path between Fogarty

Avenue and Hyde Street

  • A new bridge over Whitehall Street will

create a link between Yarraville Gardens and the Maribyrnong River

  • Upgraded cycling facilities along Hyde

Street from Somerville Road

  • A new bridge over Footscray Road and

a new pedestrian and cycling bridge at Dynon Road

slide-10
SLIDE 10

Charles Fairbairn CPBJH Joint Venture

Construction Update

slide-11
SLIDE 11

Current and upcoming works

11

Fogarty Avenue / The Avenue Williamstown Road interchange Millers Road interchange Temporary noise walls / Muir Street walking and cycling bridge Freeway widening and temporary noise walls Temporary noise walls / Rosala Avenue walking and cycling bridge

slide-12
SLIDE 12

Williamstown Road interchange

12

slide-13
SLIDE 13

Williamstown Road interchange continued

  • Building the permanent inbound exit ramp at

Williamstown Road

  • Removal of existing noise wall – end of

Williamstown Road inbound exit ramp

  • Widening the inbound bridge (freeway) over

Williamstown Road

  • Excavation of the shaft for the sewer relocation

works across Williamstown Road interchange

  • Widening the West Gate Freeway centre

median

Williamstown Road freeway bridge widening works (looking West)

November/December

13

slide-14
SLIDE 14

Williamtown Road interchange continued

14

Williamstown Road bridge widening (over freeway)

  • Night time closures of the West Gate Freeway to jack up the existing bridge

beams and replace the bearings

  • Night time closures of Williamstown Road to lift new concrete beams into place
  • Concrete pour to join the existing bridge to the newly constructed bridge

Traffic switch late November

  • The inbound carriageway will be switched onto newly constructed lane on the

approach to Williamstown Road bridge over the freeway

November/December

slide-15
SLIDE 15

Fogarty Avenue

15

slide-16
SLIDE 16

Fogarty Avenue continued

  • Temporary noise wall installation
  • Temporary noise walls will be installed on

Fogarty Avenue between the Hockey Club and Wembley Avenue

  • Existing noise walls will be removed once

temporary noise walls installed

  • Temporary noise walls will remain in place

until construction of the new noise walls are complete November – mid 2019

Installing foundations for the noise walls

16

slide-17
SLIDE 17

Fogarty Avenue / The Avenue

November/December

Fogarty Avenue

  • 66kV relocation works are ongoing
  • Stormwater drainage started in late

October (completed in stages) – deeper and wider trenches required

  • Current stage - closure of Fogarty

Avenue / The Avenue until end of November Newport Rail bridge (The Avenue) Preparatory works to start in late November including:

  • Vegetation removal
  • Setting up traffic barriers
  • Piling and excavation works

Trenching works on Fogarty Avenue

slide-18
SLIDE 18

South of the West Gate Freeway

November/December

  • Piling works for new permanent noise
  • walls between Williamstown Road

(Melbourne Road) and Newport Rail line

  • Piling works for new Muir Street walking

and cycling bridge

  • Installation of temporary noise wall

between Williamstown Road (Melbourne Road) and the Newport Rail line continuing

Temporary noise walls

slide-19
SLIDE 19

Millers Road interchange

19

slide-20
SLIDE 20

Millers Road interchange continued

Widening Millers Road underneath the freeway

  • New southbound lane underneath the freeway
  • Work switches to building the additional northbound lane later this year

Building temporary and permanent ramps

  • Millers Road temporary inbound and outbound exit ramps
  • Millers Road permanent inbound entry ramp

Tree removal

  • Millers Road outbound exit ramp and sections along Beevers Street

Beevers Street

  • 66kv relocation works still in planning phase

November/December

20

slide-21
SLIDE 21

Millers Road interchange continued

Walking and cycling bridge – Rosala Avenue / Richards Court

  • Setting up site in reserve near Buchanan Road

through to Primula Avenue

  • Piling works for foundation of walking and cycling

bridge

  • Rosala Avenue pedestrian overpass will remain
  • pen during these works

Installation of temporary noise walls

  • Adjacent to residential fences from the reserve

near Buchanan Road through to Millers Road

  • Millers Road outbound exit ramp and sections

along Beevers Street

Paringa Road works began in late September

  • Long-term closure of Paringa Road from Millers

Road

  • Gas and telecommunication relocations

underway

Long term closure of Paringa Road from Millers Road

21

slide-22
SLIDE 22

West Gate Freeway - Chambers Road to Grieve Parade

22

slide-23
SLIDE 23

West Gate Freeway - Chambers Road to Grieve Parade

23

  • Local road closures
  • Widening works in this area require

some temporary road closures to be put in place between:

  • Freemans Road;
  • Misten Avenue;
  • Rosala Avenue; and
  • Irwin Avenue.

Access to all properties will be maintained although some properties will experience changes to the way they access their property.

  • Temporary and new noise walls
  • Installing a temporary noise wall between

Freemans Road and Chambers Road

  • Removing the existing noise wall following

the installation of the temporary noise wall

  • Foundations for the new permanent noise

wall with piling starting early next year

November/December

slide-24
SLIDE 24

Postponed works

  • 220kv power line works, monopole

installation and Muir Street pedestrian

  • verpass
  • Temporary closure of the pedestrian
  • verpass connecting Muir Street and

Fogarty Avenue has been postponed

  • Enabling the safe relocation of high

voltage power lines

  • Working with AusNet on determining

the best time to complete these works.

24

slide-25
SLIDE 25

Keeping communities informed

101 incoming calls and emails 3 notifications delivered to 1130 properties 8 face to face meetings 8 door knocking events 79 incoming calls and emails 8 notifications delivered to 350 properties 8 face to face meetings 8 door knocking events

SEPTEMBER 2018 OCTOBER 2018

slide-26
SLIDE 26

Who are we hearing from?

26

Fogarty Avenue 11% of enquires Millers Road 11% of enquires Williamstown Road 8% of enquires Beevers Street 7% of enquires

Other queries relate to property condition surveys and traffic updates

slide-27
SLIDE 27

Employment and learning opportunities

Group Commitment Outcome to 31 October 2018 Comment Women 400 – 600 525 230 CPBJH JV 181 AJJV 114 subcontractors Retrenched automotive workers 100 – 150 10 Significant opportunity in construction roles yet to commence People seeking asylum and new migrants (less than 52 weeks) 35 – 50 142 The achievement is 300% of the stretch target People who identify as Aboriginal or Torres Strait Islander 80 -90 40 People living with disability 30 – 40 13 Students in juvenile detention (SWPL) 10 – 15 Yet to commence Students from disadvantaged backgrounds (SWPL) 20 – 25 Yet to commence

slide-28
SLIDE 28

DAVID CLEMENTS TRANSURBAN

Presentation of project videos and photos

slide-29
SLIDE 29

29

West Gate Freeway

10+ km

  • f traffic safety barriers

New inbound

exit ramp

Relocating

utilities

Extensive works to remove

25 gantries + 78 light poles

slide-30
SLIDE 30

West Gate Freeway

West Gate Freeway

Widening works underway

slide-31
SLIDE 31

West Gate Freeway

Tunnels

Getting ready to ship first TBM

slide-32
SLIDE 32

THANK YOU