BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation - - PowerPoint PPT Presentation

blackspring ridge project update
SMART_READER_LITE
LIVE PREVIEW

BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation - - PowerPoint PPT Presentation

BLACKSPRING RIDGE PROJECT UPDATE Liaison Committee Presentation February 23, 2015 GOAL OF THE LIAISON COMMITTEE As part of the Blackspring Ridge Wind Project, a Liaison Committee was established to facilitate the participation of the


slide-1
SLIDE 1

BLACKSPRING RIDGE PROJECT UPDATE

Liaison Committee Presentation February 23, 2015

slide-2
SLIDE 2

GOAL OF THE LIAISON COMMITTEE

❖ As part of the Blackspring Ridge Wind Project, a Liaison Committee was established to facilitate the participation of the community in the development of the wind farm. ❖ The Liaison Committee will ensure that the interests of landowners are considered and participation of local businesses and services is encouraged. The objectives of the committee are to: ❖ Ensure effective communication between all stakeholders and EDF EN Canada Development Inc., acting as Manager

  • n behalf of the Co-Owners

❖ Understand issues related to the development and construction of the wind farm; ❖ Recommend satisfactory solutions to stakeholders; ❖ Identify potential opportunities for local business and services

slide-3
SLIDE 3

LIAISON OFFICE

❖ As Manager of the Blackspring Ridge Wind Project, EDF EN Canada Development Inc. is committed to working with all stakeholders during the Operations phase of the Project. ❖ If you have any questions or comments, please do not hesitate to contact the Blackspring Ridge Liaison Office at: ❑ Kimberli Kenna, Site and Liaison Administrator ❑ If land related meetings are needed or requested, Paul Lawson is available by appointment. ❑ Telephone: 403-671-4000 ❑ E-mail: blackspringridge@edf-en.ca ❖ More information on the Project can also be found at www.blackspringridge.ca.

slide-4
SLIDE 4

BLACKSPRING RIDGE TEAMS

❖ Commercial Operation was reached in May 2014. Various teams have been hired, trained and are now currently a couple months away from starting year 2 of the 20 year Operations phase. ❖ Following is a brief description of each of the teams responsibilities: ❑ EDF EN Canada Development Inc.: ECDI will continue to be the Manager of the Project and will continue to be the main point of contact for all stakeholders and manage tasks such as landowner payments. ❑ Enbridge: Enbridge will be the Balance of Plant Operations & Maintenance (BOP O&M) Manager and will be responsible for the maintenance of the site and the substation. ❑ Vestas: With approximately 20 technicians on site, Vestas will be the Operations & Maintenance Manager for wind turbines and will be responsible for the day to day Operations & Maintenance (O&M) of all the turbines.

slide-5
SLIDE 5

RESTORATION/RECLAMATION

❖ Restoration/Reclamation wrapped up Fall of 2014, thank you to all our landowners and tenants for the collaboration and support throughout this phase. ❖ After harvest this year we will be in contact with remaining landowners to review final documentation.

slide-6
SLIDE 6

SAFETY ON-SITE

❖ Now that Blackspring Ridge is almost complete year one of being in full operation, we want to remind all of safety, as it is always priority. ❑ Underground cables, junction boxes, overhead lines and substation are all energized. Please call “Alberta One Call” before excavating or digging. http://www.albertaonecall.com ❖ Posts have been installed at the entrance of each access road, signs are in the finalization process and will be placed. The signs will state authorized personnel only, no trespassing. ❖ Reflector tape has been placed on select turbines for visual safety. ❖ There will also be 5 STARS Air Ambulance signs posted within the project area.

slide-7
SLIDE 7

❖ All Crop Compensation payments for 2014 were processed and distributed as of early January 2015. ❖ Rent payments for 2015 were processed and distributed February 2015. ❖ Royalty payments related to the production of the Blackspring Ridge Wind Project for Quarter 4 (October/November/December 2014) to be received February 2015. ❑ 2015 Quarter 1 Royalty (January/February/March) payments will be processed in late April, once full production data has been received for all three first months of 2015.

LANDOWNER PAYMENTS

slide-8
SLIDE 8

ENVIRONMENTAL MONITORING - OPERATIONS PHASE

❖ EDF EN Canada and Enbridge consider environmental protection to be an important and integral part of the Project. ❖ As per ESRD requirements, ECDI and Enbridge will run its second year of the 2 year Post Construction Monitoring of birds and bats. ❖ Noise Monitoring was conducted the end of August 2014. Results and reports can be found

  • n the AUC website:

http://www.auc.ab.ca/applications/current-applications

❑ application 1611025-1 ❑ proceeding 3537

slide-9
SLIDE 9

BLADE DONATION & COMMUNITY FUND PROJECT

❖ On October 31, 2014 the Village of Carmangay received a blade from the Blackspring Ridge Wind Project. A double sided information kiosk will be created and installed early 2015. ❖ The Blackspring Ridge Wind Project Community Fund will take place for its second year, this coming

  • summer. Announcements for when this will kick off will

be emailed to landowners, placed in local newspapers and posted on community centre boards.

slide-10
SLIDE 10

THANK YOU

For questions, comments or inquiries, please contact the Blackspring Ridge Liaison Office:

▪ Telephone: 403-671-4000 ▪ E-mail: blackspringridge@edf-en.ca

A wealth of renewable experience in Canada.

10 23/02/2015 Liaison Committee Presentation