Vista Ridge Update Tim Skoglund, P.E. Senior Director Vista Ridge January 18, 2017 CIAC Meeting January 18, 2017 Public Private Partnership P3 Contracts signed November 2014 P3 Framework: Risk Transfer Holds Groundwater Leases Global


slide-1
SLIDE 1

CIAC Meeting Tim Skoglund, P.E.

Senior Director – Vista Ridge

Vista Ridge Update

January 18, 2017

slide-2
SLIDE 2

January 18, 2017

Vista Ridge Update

Page 2

Holds Groundwater Leases

Public‐Private Partnership

  • P3 Contracts signed November 2014

P3 Framework: Risk Transfer Global Experience: Water and Power Financing: Equity + Bonds/Loans Project Construction Firm (2011)

  • 50,000 AFY Water Supply
  • 30 Year Term + Asset Transfer
  • SAWS pays only for Water Delivered: Fixed Price + O&M
slide-3
SLIDE 3

January 18, 2017

Vista Ridge Update

Page 3

Holds Groundwater Leases

Project Company Change in Control

  • Change in Control – June 10, 2016

Project Construction Firm (2011) Controlling Project Owner (2016)

  • 80% Controlling Share of Project Company (Vista Ridge LLC)
  • Project Continuity and successful SAWS track record
  • Better standards for materials, equipment, construction
slide-4
SLIDE 4

January 18, 2017

Vista Ridge Update

Page 4

Project Timeline

Commercial Close

November 4, 2014

Financial Close

November 2, 2016

Water Delivery Begins

~ 2020

Asset Transfer to SAWS

~ 2050

Debt Service Drops Off

SAWS pays lower price

Rate Lock ($1,606/AF)

May 17, 2016

slide-5
SLIDE 5

January 18, 2017

Vista Ridge Update

Page 5

Tax‐Exempt Interest Rates July 1993 – May 2016

Locked in the Lowest Rates in Last 30 Plus Years

slide-6
SLIDE 6

January 18, 2017

Vista Ridge Update

Page 6

Tax‐Exempt Interest Rates Commercial Close to Current

Locked in 36 Basis Points off All‐Time Low and 126 Basis Points Less than 12/1/16

slide-7
SLIDE 7

January 18, 2017

Vista Ridge Update

Page 7

Millions of Dollars in Savings

Date/Contractual Determined Rate Capital & Raw Groundwater Unit Price Annual Cost for 50,000 AF* Maximum 6.04% $1,959 $97,950,000 11/4/2014 4.83% $1,739 $86,950,000 7/22/2015 4.97% $1,760 $88,000,000 2/19/2016 4.45% $1,680 $84,000,000 3/7/2016 4.59% $1,702 $85,100,000 4/12/2016 4.24% $1,649* $82,450,000 5/17/2016 3.92% $1,606 $80,300,000 6/10/2016 3.77% $1,586* $79,300,000 11/2/2016 4.19% $1,643* $82,150,000 12/1/2016 5.18% $1,794 $89,700,000

Interest Rate Lock Saved SAWS ~ $1.9 Million a Year Compared to Financial Close Rate

* Staff estimates.

slide-8
SLIDE 8

January 18, 2017

Vista Ridge Update

Page 8

November 2nd Project Company Locked in Rates

Financial Close Avoided Post‐Election Increase in Interest Rates

slide-9
SLIDE 9

January 18, 2017

Vista Ridge Update

Page 9

Development and Financing

  • Easements (25% at Financial Close)
  • Hydrogeology
  • Basic Engineering
  • Permitting
  • Survey
  • Financing

Project Phases

Construction

  • Detailed Design
  • Construction
  • Commissioning
  • Performance Testing

Commercial Operation

  • Maintenance, Repair, Replacement
  • Annual Budget Review (Budget Panel)
  • SAWS pays O&M and Electricity Cost
  • End‐of‐Term Condition Assessment
slide-10
SLIDE 10

January 18, 2017

Vista Ridge Update

Page 10

Infrastructure

18 Wells 140‐mile Pipeline 3 Pump Stations Treatment: T, Cl, pH $540 million Construction $927 million Capital Cost

slide-11
SLIDE 11

January 18, 2017

Vista Ridge Update

Page 11

SAWS Responsibilities

Establish Electric Power Service Monitor Project Execution Wholesale Water Integration Infrastructure in San Antonio

slide-12
SLIDE 12

January 18, 2017

Vista Ridge Update

Page 12

TERMINUS IPS #2 IPS #1 HSPS & WELL FIELD

ELECTRIC SERVICE PROVIDER BOUNDARY MAP

slide-13
SLIDE 13

January 18, 2017

Vista Ridge Update

Page 13

Monitor Project Execution

Development Review Design Review Construction Observation Operations Monitoring

  • CH2M Hill Engineers hired as

Technical Advisor

– ESP Support – Monitor Execution

  • $4.5 million over 5 years
  • Time and Material Contract
slide-14
SLIDE 14

January 18, 2017

Vista Ridge Update

Page 14

Vista Ridge Integration

  • Treatment Facilities

– Calcium, (Iron?)

  • New Pump Station
  • Ground Storage Tanks
  • Valves, Pumps, Controls
  • Pipelines

– Condition assessment – Rehab/replace – New construction: 5 miles

slide-15
SLIDE 15

January 18, 2017

Vista Ridge Update

Page 15

Terminus Site

slide-16
SLIDE 16

January 18, 2017

Vista Ridge Update

Page 16

Integration Project – Alternate Procurement Method

  • Design‐Build Method

– Schedule and Collaboration Benefits – Owner’s Rep + Design Builder

  • Black & Veatch hired as OR

– Preliminary Engineering/Studies ($4.3 million) – Project Management – Construction Management

  • Design Build Firm (TBD)

– $125 million

slide-17
SLIDE 17

January 18, 2017

Vista Ridge Update

Page 17

Integration Project Timeline

Bitters PS Basin PS

slide-18
SLIDE 18

CIAC Meeting Tim Skoglund, P.E.

Senior Director – Vista Ridge

Vista Ridge Update

January 18, 2017