BLACKSPRING RIDGE PROJECT UPDATE EDF EN Canada and Enbridge - - PowerPoint PPT Presentation

blackspring ridge project update
SMART_READER_LITE
LIVE PREVIEW

BLACKSPRING RIDGE PROJECT UPDATE EDF EN Canada and Enbridge - - PowerPoint PPT Presentation

BLACKSPRING RIDGE PROJECT UPDATE EDF EN Canada and Enbridge Vulcan County Presentation July 3 rd , 2013 AGENDA Landowner & Community Relations Construction Update Questions & Answers | | Vulcan County Presentation


slide-1
SLIDE 1

BLACKSPRING RIDGE PROJECT UPDATE

EDF EN Canada and Enbridge Vulcan County Presentation July 3rd , 2013

slide-2
SLIDE 2

| |

AGENDA

2

❖ Landowner & Community Relations ❖ Construction Update ❖ Questions & Answers

03/07/2013 Vulcan County Presentation

slide-3
SLIDE 3

LANDOWNER & COMMUNITY RELATIONS

Since the acquisition of the Blackspring Ridge Wind Project, EDF EN Canada and Enbridge have reached

  • ut to the project landowners, local and provincial

governmental authorities through various meetings, letters, newsletters and events such as: ▪ Meetings and/or Presentation with Vulcan County, Towns of Vulcan, Carmangay and the MLA for Little Bow ▪ Community Newsletter ▪ Community Board Postings ▪ Landowner Dinner and meetings ▪ Hiring of a local Liaison Agent who will work on site to primarily be the main point of contact for the community and our landowners during construction ▪ Blackspring Ridge Wind Project Liaison Committee

slide-4
SLIDE 4

CONSTRUCTION UPDATE

❖ Office trailers for Mortenson, EDF EN Canada and Enbridge have been set up next to the future substation location. ❖ Mortenson has started cutting and graveling access roads on the south west side of the project. ❖ Foundation excavation has also been started on the south west part of the project. ❖ Directional boring and underground collection cable deliveries have commenced. ❖ 165 blades were received and are currently at the laydown area in Wilson. ❖ The first train of nacelles and hubs were also delivered at the laydown area along with the 2 main transformers. ❖ Total manpower on site at the end of June: ~ 90 EDF EN Canada team on site : ❖ Leslie Warren : Liaison Agent ❖ Robert Kreft : Site manager ❖ Manuel Glazer : Transport and Turbine coordinator ❖ Greg Ronaasen : Civil coordinator ❖ Kimberli Kenna : Administration

Project Site Trailers & Trucks

slide-5
SLIDE 5

CONSTRUCTION UPDATE

5 03/07/2013 Vulcan County Presentation

Access Road – Turbine 10, 11, 12 Project Site Trailers Bolt Cage Assembly – Turbine 12 Wilson Laydown Area

slide-6
SLIDE 6

CONSTRUCTION UPDATE

6 03/07/2013 Vulcan County Presentation

Transformer, Wilson Laydown Area Blades, Wilson Laydown Area

slide-7
SLIDE 7

PROJECT MAP

7 01/05/2013 Vulcan County Introductory Presentation

slide-8
SLIDE 8

THANK YOU FOR YOUR TIME

Stephane Desdunes Matt Bordson Development Manager Enbridge Major Projects 416.216.5886 218.623.7560 Stephane.Desdunes@edf-en.ca Matthew.Bordson@enbridge.com

A wealth of renewable experience in Canada.

8 03/07/2013 Vulcan County Presentation