josephine county public works 2016 17 budget presentation
play

Josephine County Public Works 2016 17 Budget Presentation Robert - PowerPoint PPT Presentation

Josephine County Public Works 2016 17 Budget Presentation Robert Brandes, Director Public Works Operating North Valley Industrial Park Solid Waste County Fleet County Bridge Construction County Transit PUBLIC WORKS ~ FTE BY PROGRAM Admin.


  1. Josephine County Public Works 2016 ‐ 17 Budget Presentation

  2. Robert Brandes, Director Public Works Operating North Valley Industrial Park Solid Waste County Fleet County Bridge Construction County Transit

  3. PUBLIC WORKS ~ FTE BY PROGRAM Admin. Operations Engineering PW Fleet Total FTE's 10 ‐ 11 9.00 39.00 6.80 8.75 63.55 11 ‐ 12 9.00 39.00 6.80 8.50 63.30 12 ‐ 13 7.00 32.50 5.90 7.35 52.75 13 ‐ 14 7.00 31.00 6.30 7.35 51.65 14 ‐ 15 7.00 27.00 6.30 7.35 47.65 15 ‐ 16 7.00 31.00 6.00 7.35 51.35 16 ‐ 17 7.00 31.00 6.00 7.35 51.35

  4. MAJOR REVENUE SOURCE $8 $7 Federal Forest Receipts $6 $5 Millions Surface $4 Transportation Program (STP) $3 Motor Fuel Tax $2 $1 $ ‐

  5. 2014 ‐ 15 ROAD FUND BALANCES BY HB 4175 COUNTIES (Millions) $94 $69 $37 $25 $21 $2 $2 Coos Josephine Linn Lane Curry Douglas Klamath

  6. COUNTIES BUDGET EFB % of budget Columbia 4,863,494 620,491 13% Polk 8,266,807 1,239,865 15% Gilliam 1,127,753 255,136 23% Josephine 8,610,460 2,360,329 27% Yamhill 6,789,007 2,025,221 30% Coos 5,250,462 1,584,512 30% COUNTIES BUDGET EFB % of budget Malheur 3,323,503 1,038,095 31% Jefferson 2,242,955 2,070,260 92% Baker 4,810,482 1,662,424 35% Sherman 3,361,028 3,656,859 109% Benton 6,901,411 2,386,791 35% Tillamook 6,974,795 7,911,893 113% Linn 15,426,409 21,087,862 137% Morrow 4,687,020 2,207,702 47% Washington 110,845,292 157,224,782 142% Multnomah 97,122,366 61,437,710 63% Wasco 2,810,672 4,256,963 151% Umatilla 5,765,766 4,061,148 70% Clackamas 43,952,238 79,681,082 181% Clatsop 6,257,885 4,449,297 71% Wallowa 2,585,119 5,778,107 224% Lane 30,987,962 25,277,984 82% Lincoln 4,894,726 11,245,993 230% Deschutes 17,359,192 14,240,472 82% Hood River 3,214,613 12,028,535 374% Marion 27,997,546 24,503,136 88% Douglas 15,019,019 69,314,878 462% Union 2,640,854 2,317,814 88% Crook 3,540,036 19,440,600 549% Jackson 18,684,857 17,169,878 92% Harney 2,496,266 16,830,659 674% Lake 3,041,472 21,678,338 713% Curry 4,571,165 37,100,438 812% Klamath 11,130,863 93,788,958 843% Grant 4,053,287 64,585,285 1593% Wheeler - - #DIV/0! 501,606,782 796,519,497 159%

  7. OPERATIONS ~ CHIPSEAL Miles Avg. Cost 2006 ‐ 07 37.72 $ 1,320,200 2007 ‐ 08 36.22 $ 1,267,700 2008 ‐ 09 18.87 $ 660,450 2009 ‐ 10 23.91 $ 836,850 2010 ‐ 11 18.03 $ 631,050 2011 ‐ 12 11.58 $ 405,300 2012 ‐ 13 0.00 $ ‐ 2013 ‐ 14 25.94 $ 907,900 2014 ‐ 15 0.00 $ ‐ 2015 ‐ 16 15.20 $ 532,000 2016 ‐ 17 0.00 $ ‐ 06 ‐ 07 ~ 10 ‐ 11 Average $ 943,250 11 ‐ 12 ~ 16 ‐ 17 Average $ 307,533

  8. Preserved vs Non-Preserved County Road Cost per Mile for 2 Lane Road Over 55 years Pavement Condition Preserved Non-Preserved Very Good Good Preserved Preserved Fair Total = tal = Seal Seal Overlay Seal Seal Overlay Seal Seal $520,000 $520,000 $20,000 = $20,000 $20,000 $200,000 $20,000 $20,000 $200,000 $20,000 Poor Initial Building Cost Non- Non- $750,000 Very Preserved Preserved Poor Total = tal = Rebuild Rebuild $1.0 $1.0 Million Million = $500,000 $500,000 0 5 10 15 20 25 30 35 40 45 50 55 Pavement Age (Years) The poorer the road, the greater the liability.

  9. OVERLAYS (CONTRACTED WORK) COST MILES New Hope Rd / Curtis Dr / Soldier Creek Rd 10-11 Harbeck Rd ~ Allencreek Rd $ 576,258 5.00 11-12 Highland Ave $ 386,659 2.30 12-13 Monument Dr (Merlin to NVIP) $ 98,324 0.50 13-14 Monument Dr (NV Pavement Preservation) $ 492,573 2.15 14-15 Merlin Rd / Upper River Rd $ 395,535 2.80 15-16 Vine St $ 139,268 0.70 16-17 NVIP/Azalea Dr $ 504,400 2.10

  10. OPERATIONS MAINTENANCE SERVICE TYPES Road Surface Drainage * potholes * ditching/shaping * sinkhole/washout * culvert repair/replace * guardrail * culvert flushing * brooming * debris removal * digouts * flooding Signs/Striping Specialized Maintenance * striping * spills * sign replacement * slides/rock Vegetation * ice/snow removal * chipping * accident cleanup * mowing * debris/animal removal * hazard tree removal Bridge Maintenance * visibility clearing * damage/cracks * tree down on roadway * debris removal

  11. UNANTICIPATED PROJECT BONNIE LANE ~ CULVERT REPLACEMENT COST $40K

  12. UNANTICIPATED PROJECT PROJECTED COST $116K SMALL CREEK BRIDGE REPLACEMENT WESTSIDE ROAD

  13. UNANTICIPATED PROJECT PROJECTED COST $125K + JUMP OFF JOE CREEK ~ WING WALL REPLACEMENT MONUMENT DR

  14. UNANTICIPATED PROJECT GALICE ROAD ~ SLIDE COST $133K

  15. UNANTICIPATED PROJECT PROJECTED COSTS $155K EWE CREEK ~ CULVERT REPLACEMENT AZALEA DR

  16. UNANTICIPATED PROJECT FOOTHILL BLVD ‐ CULVERT REPLACEMENT COST $162K

  17. ROADS & BRIDGES RESERVE PROJECTS MATCH $250K UNANTIPATED $50K MATCH LAKESHORE DR ~ BRIDGE REPLACEMENT @ LAKESHORE DR ~ SPILLWAY

  18. UNANTICIPATED PROJECTS BONNIE LANE CULVERT REPLACEMENT $ 40,000 LAKESHORE DR SPILLWAY – ADDTL MATCH $ 50,000 SMALL CREEK BRIDGE BRIDGE REPLACEMENT $ 116,000 JUMP OFF JOE CREEK WING WALL REPLACEMENT $ 125,000 GALICE ROAD SLIDE REMOVAL $ 133,000 AZALEA DR CULVERT REPLACEMENT $ 155,000 FOOTHILL BLVD CULVERT REPLACEMENT $ 162,000 $ 781,000

  19. ROADS & BRIDGES RESERVE PROJECTS PROJECTED COSTS $ 32K CATTLE UNDER CROSSING ~ REMOVAL UPPER RIVER ROAD

  20. ROADS & BRIDGES RESERVE PROJECTS PROJECTED COSTS $72K THREE PINES ROAD ~ REALIGNMENT THREE PINES ROAD / HUGO ROAD

  21. ROADS & BRIDGES RESERVE PROJECTS PROJECTED COSTS $126K NEW HOPE ROAD ~ SIDEWALKS

  22. ROADS & BRIDGES RESERVE PROJECTS PROJECTED COSTS $165K W HARBECK ROAD ~ SIDEWALKS/CURB/GUTTER @ SOUTH MIDDLE SCHOOL

  23. ROADS & BRIDGES RESERVE PROJECTS PROJECTED COSTS $ 505K NORTH VALLEY INDUSTRIAL PARK/AZALEA (TBD) ~ OVERLAY @ INDUSTRIAL PARK / MERLIN

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend