Introduction Qenos update since November ACNCG Qenos actions arising (nil raised) Community Regulatory Interface 2015 Qenos ACNCG Focus Areas 2014


slide-1
SLIDE 1
slide-2
SLIDE 2

Introduction Qenos update since November ACNCG Qenos actions arising (nil raised) Community Regulatory Interface 2015 Qenos ACNCG Focus Areas 2014 Performance Trends

slide-3
SLIDE 3

Community

  • December & March EMT meetings held
  • Consultation

− Community briefing & discussion on Qenos Noise EIP conducted − EMTs moved to evening − several new members have joined EMT − Qenos SHE Excellence Awards

  • Complaints

− 3 noise complaints in January for flare noise from Olefins after steam supply interruption.

slide-4
SLIDE 4

Regulatory Interface

  • EPA
  • Discussed draft groundwater Quality Management plan with EPA in December
  • Liaising with EPA about future of accredited licence program
  • Regulatory noise limits established in residential areas endorsed by EPA
  • CWW
  • Minor Sulphide excursion for Olefins Trade waste 15th Dec & 30th Jan.
  • Customer notified non compliance in place until ETP clean completed
  • ETP clean executed without complaints or non compliances
  • Worksafe

Nothing to report

slide-5
SLIDE 5

2015 Goals

Aspect Aim

November 2014 ACNCG April 2015 ACNCG Status Improve SHE performance

Reduce injury rate

  • 1 injury for the quarter, Injury rate better

than 2014 and plan. Reduced community noise

  • Implementation of Plastics recycle

gearbox investment.

  • Scope F-651 noise treatment.
  • Reduced flare noise complaints.
  • Community noise monitoring program in

place.

  • One gearbox installed in March.

Performance being evaluated.

  • F-651 scope evaluation in 2016.
  • Complaints related to steam outage in

January,

  • Community noise monitoring at Charles

Road & Galvin street in February And March

Business Outlook

Qenos is anticipating 2015 to be a further improvement in overall Business, however there is a general downturn across all sectors of industry at present.

  • Change in global oil price has also

driven down regional PE pricing.

  • Far more challenging year than we

anticipated.

Consolidate investments

Olefins plant will continue to focus upon ethylene yield optimisation and energy utilisation.

  • Significant feedstock shortfall in Feb &
  • March. April and May are also expected

to be lower. Esso industrial issues. Polymer plant reliability improvements and performance enhancement to achieve 200kT PE production.

  • Based upon the first quarter ethane

shortfall and continuing restrictions in supply, PE volume will be well below plan. Support the major investment in Botany

  • Turnaround planning process is on
slide-6
SLIDE 6
slide-7
SLIDE 7

100 120 140 160 180 200 220 240 2010 2011 2012 2013 2014

KT

Polyethylene production

93% of production plan

slide-8
SLIDE 8

5 10 15 20 25 30 2010 2011 2012 2013 2014

Events per Annum Community complaints Environment incidents

Environment trends

Significant flare reduction reducing complaints. 2 Solvent LOC at Resins

slide-9
SLIDE 9

Water Usages

Steam reductions. On site water reuse.

* No recycled water available in 2014

200 400 600 800 1000 1200 500 1,000 1,500 2,000 2,500 3,000 2010 2011 2012 2013 2014

ML / year ML / year Alternative Water supply Mains Water Supply Waste Water Water supply Waste water

slide-10
SLIDE 10

Water Efficiency

Reduced steam production. Increased on site water reuse.

0.0 2.0 4.0 6.0 8.0 10.0 4 8 12 16 20 2010 2011 2012 2013 2014

KL / Tonne PE KL / Tonne PE Recycled water Water Consumption Waste Water Water supply Waste water

slide-11
SLIDE 11

Greenhouse Gas Emissions

Altona Revamp & Cogeneration projects Steam savings

0.00 1.00 2.00 3.00 4.00 5.00 200 400 600 800 1,000

2010 * 2011 * 2012 * 2013 * 2014 *

Tonnes CO2/Tonne PE Emissions KT CO2e) Purchased Electricity Emissions On site emissions Emissions Intensity

slide-12
SLIDE 12

30.0 35.0 40.0 45.0 50.0 55.0 60.0 2010 2011 2012 2013 2014

GJ/T PE Energy Efficiency

Energy Efficiency

Altona Revamp & Cogeneration projects Steam savings

slide-13
SLIDE 13

200 400 600 800 1000 2010 2011 2012 2013 2014

Tonnes General waste Prescribed Waste to landfill Recycled waste

Waste

Prescribed waste in 2014

  • Resins - pond cleans 50t
  • Resins – mud-hole waste 48 t
  • Olefins - caustic tank clean 41t
slide-14
SLIDE 14

200 400 600 800 1000 2010* 2011* 2012* 2013* 2014*

Tonnes

VOC NOX SOX

* Financial year

Emissions

Reduction in boiler firing. Reduced flaring Reduced fugitive emissions

slide-15
SLIDE 15

1 2 3 4 5 2010* 2011* 2012* 2013* 2014*

Tonnes Benzene

Financial year

Emissions

Minor increase in pump seal emissions

slide-16
SLIDE 16

Aspect Aim 2013 vs 2014 Improve SHE performance

Reduce injury rate - TRIR 0.72 0.46 Reduce flare impact on community 2929t 850t

Business Outlook

With improved capacity and efficiency across the Altona Plants, coupled with the reduced $A Qenos expects 2014 to be see an improvement in overall Business performance - EBITDA 300%

Consolidate investments

Optimise the Olefins site for further yield improvements and energy efficiencies. 1% increase in yield 42 GJ/T 37 GJ/T Optimise steam generation from cogeneration plant 29 T/Hr 34 T/Hr Maximise ethylene/PE production across Altona Plants – 200kta 5 kT increase in ethylene production

2013 vs2014