Alternative Proposal for Discussion October 27, 2015 Update Since - - PowerPoint PPT Presentation

alternative
SMART_READER_LITE
LIVE PREVIEW

Alternative Proposal for Discussion October 27, 2015 Update Since - - PowerPoint PPT Presentation

PDR Energy Baseline Alternative Proposal for Discussion October 27, 2015 Update Since Last Meeting Since the October 12 th Working Group Meeting Stem, Solar City, AMS and CESA have had over a half-dozen meetings to discuss adjustments to


slide-1
SLIDE 1

Proposal for Discussion October 27, 2015

PDR Energy Baseline Alternative

slide-2
SLIDE 2
  • Since the October 12th Working Group Meeting Stem, Solar

City, AMS and CESA have had over a half-dozen meetings to discuss adjustments to the CAISO’s proposed methods for estimating generation output used for retial purposes.

  • We concluded that the CAISO’s proposed option titled “using

a baseline” that calculates a Gtadjusted value is the most viable

  • ption if we must move forward quickly.
  • Similar to the CAISO’s Gtadjusted construct, we propose

establishing a “typical-usage level” (GTYPICAL) based on electric

  • utput using (G) metered quantities during non-dispatch days.
  • We recommend moving forward with a Gtadjusted calculation,

while also continuing to discuss broader issues around dual- use in Phase II of the CAISO’s ESDER Initiative.

Update Since Last Meeting

slide-3
SLIDE 3

Background | Why do we need a change?

3

  • In its recent Local Capacity Resource Procurement, SCE signed

PPAs for 135 of Demand Response Energy Storage (DRES) Resources - 85 MW with Stem, 50 MW with AMS.

  • Projects are being installed now, with testing occurring in the

second half of 2015 and commercial operation dates of 10/1/2016.

  • AMS contracts require use of an energy baseline unless there

is a CAISO approved alternative.

  • Resources are designed to be dispatched often, making use of

the PDR baseline / collecting 10 days of accurate load data on non-event days could be challenging during certain times of the year.

slide-4
SLIDE 4

Alternative Baseline| Use Case

4

  • Location: Behind-the-Meter C&I installation
  • Product: Load drop to an IOU ~100 times a year using DR

and/or battery storage

  • Value Streams:

– Wholesale: Contractual dispatches by IOU – Retail: Energy arbitrage, demand charge management, retail demand response programs

slide-5
SLIDE 5

Alternative Baseline| Proposal Overview

5

  • Similar to the CAISO’s Gtadjusted construct, establish a “typical-usage level” (GTYPICAL)

based on electric output using (G) metered quantities during non-dispatch days.

  • Days would be selected by conducting a look back of comparable, non-dispatch

days (similar to the CAISO’s existing 10-in-10 in 45 baseline methodology for loads).

  • Scenario A: Similar to the PDR baseline methodology, the first 10 non-event similar

day-type days are selected. A non-event day is a day in which no hour contains a PDR dispatch. A profile is created by averaging 5-minute data to the hour and then

  • ver the 10 days. Performance (P) during each interval (t) during the PDR call is

therefore: P = - (G - GTYPICAL).

  • Scenario B: If 10 non-event days cannot be found within a look-back window, then

the resource is deemed to be a full-time market participant and GTYPICAL = 0 and the resource receives credit for the full generation value during the event duration (standard proposed PDR rules for MGO).

Use the battery meter to directly measure/settle contractual dispatches; with an adjustment calculating out typical retail use.

slide-6
SLIDE 6

6

  • 250

250 500 750 1000

0:00 2:00 4:00 6:00 8:00 10:0012:0014:0016:0018:0020:0022:00

Energy (kWh) Performance with 10-day Adjustment on MGO

Facility load (kW) Site meter (kW) Performance, G_adj (kW) MGO adjustment

Average of 10 non-event days over past 45 days Sept 22, 2014 Dispatch, 10 Prior Workdays for Adjustment Calculation

MGO Hour-Specific Adjustment Method

18% adjustment

Dispatch

slide-7
SLIDE 7

7

Meter 9/8 9/9 9/10 9/11 9/12 N 723 kW 723 kW 723 kW 719 kW 723 kW G

  • 28 kW
  • 28 kW
  • 15 kW
  • 8 kW
  • 27 kW

L 751 kW 751 kW 738 kW 727 kW 751 kW

Measurements at HE 15:00 in kW

Meter 9/15 9/16 9/17 9/18 9/19 N 723 kW 723 kW 723 kW 723 kW 723 kW G

  • 127 kW
  • 66 kW
  • 50 kW
  • 21 kW

0 kW L 851 kW 789 kW 773 kW 743 kW 700 kW Meter Dispatch Day: 9/22 N 543 kW G

  • 211 kW

G_typical

  • 37 kW

L 754 kW P = -(G - G_typical) 174 kW

slide-8
SLIDE 8

8

Alternative Baseline | Likely Dispatch

Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15

  • n peak

36.49 34.93 79.92 56.98 51.73 34.31 34.52 33.48 36.95 32.02 35.29 38.3

  • ff peak

37.22 35.52 71.53 57.54 54.06 35.4 34.79 33.97 37.59 32.4 36.04 39.15 Dispatch Days 23 20 21 22 11

Net Benefits Test Prices ($/MWh) and Workdays with LMP Above On Peak Price

Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14

  • n peak

52.4 50.15 42.8 56.63 65.57 79.43 71.51 65.35 56.08 55.57 62.97 58.45

  • ff peak

56.16 51.62 43.54 57.42 66.23 80.26 72.79 67.86 61.95 64.09 64.38 64.21 Dispatch Days 1 4 22 8 11 1 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13

  • n peak

31.87 39.44 40.53 37.25 37.18 38.05 41.63 45.93 48.6 47.79 44.64 41.35

  • ff peak

32.13 39.38 41.14 38.06 37.98 39.23 42.66 48.21 49.9 51.46 48.22 42.19 Dispatch Days 23 15 12 23 20 21 22 13 6 8 9 16

slide-9
SLIDE 9

Additional Slides (If Needed)

slide-10
SLIDE 10

10

Most Recent 10 Days without Dispatch

February 17-28, 2014: one week has 4 days of peak shaving

slide-11
SLIDE 11

11

Two Previous Weeks: No Peak Shaving