Innovation in Construction 3dExperience Forum 2012 Martin Simpson - - PowerPoint PPT Presentation

innovation in construction
SMART_READER_LITE
LIVE PREVIEW

Innovation in Construction 3dExperience Forum 2012 Martin Simpson - - PowerPoint PPT Presentation

Innovation in Construction 3dExperience Forum 2012 Martin Simpson Martin Simpson Associate Director Arup Professor of Innovation University of Salford Why do things differently? Global Consumption of Resources = = x ? = World set to


slide-1
SLIDE 1

Innovation in Construction

3dExperience Forum 2012

slide-2
SLIDE 2

Martin Simpson

Martin Simpson

Associate Director Arup Professor of Innovation University of Salford

slide-3
SLIDE 3
slide-4
SLIDE 4

Why do things differently?

slide-5
SLIDE 5
slide-6
SLIDE 6

Global Consumption of Resources

= = =

x ?

slide-7
SLIDE 7

If the world continues using its natural resources at the current rates we will be getting through 140 billion tonnes of minerals, ores, fossil fuels and biomass by 2050

World set to treble consumption by 2050.

slide-8
SLIDE 8

8

The 160 million buildings in the EU use 40% of Europe’s energy and create 40% of it’s carbon dioxide.

London by night

slide-9
SLIDE 9

“Rethinking Construction” by Sir John Egan - 1998.

  • 30% of construction is rework
  • 40% of the manpower used on construction sites can be

wasted

  • At least 10% materials are wasted
  • Over 40% of projects are completed late or over budget.

Waste in the Construction Industry

slide-10
SLIDE 10

10

Duplication of Work

The cost of inadequate interoperability in the U.S. capital facilities industry estimated at:

$15.8 billion per year

slide-11
SLIDE 11

Cost Time

Feasibility Concept Design Detailed Design Construction

To cost of post construction change is many times the cost of change during design

Post Construction

This must be avoided Egan stated that up to 30% of construction is rework This is the ideal place for change to occur, ie where it is cheap!

How Cost Changes with Time

slide-12
SLIDE 12

Ability to influence change Time

Feasibility Concept Design Detailed Design Construction Post Construction

How the ability to influence change varies with time

Macleamy’s

slide-13
SLIDE 13

The Stages of a project

  • Feasibility

Feasibility

The Project Life-Cycle

slide-14
SLIDE 14

The Stages of a project

  • Feasibility
  • Pre-construction

Feasibility Design Tender Pre-construction

The Project Life-Cycle

slide-15
SLIDE 15

The Stages of a project

  • Feasibility
  • Pre-construction
  • Construction

Feasibility Construction

The Project Life-Cycle

Design Tender Pre-construction

slide-16
SLIDE 16

The Stages of a project

  • Feasibility
  • Pre-construction
  • Construction
  • Operation

Operation

The Project Life-Cycle

Feasibility Construction Design Tender Pre-construction

slide-17
SLIDE 17

The Stages of a project

  • Feasibility
  • Pre-construction
  • Construction
  • Operation
  • Decommission

Decommission

The Project Life-Cycle

Operation Feasibility Construction Design Tender Pre-construction

slide-18
SLIDE 18

Façade Design Quantities Extraction

Fractured Processes within the Construction Industry

slide-19
SLIDE 19

Ability to influence change Time

Feasibility Concept Design Detailed Design Construction Post Construction

MacLeamy’s Curves showing commitment of resource to design (including final fabrication design)

slide-20
SLIDE 20

Handover As Built Construction Design

Current Practice

Concept

E x a m p l e ,

Information Flow across the Project Life-Cycle

?

Data, Information & Knowledge

Date atrophy during project lifecycle due to:

  • Information exchange via 2D drawings/Sketches/Reports/Conversations...
  • Upfront simulation is limited and for some disciplines simulation is not accurate
  • We start the final production phase commence before design is complete.
  • Often without production of prototypes (Most buildings are unique!)
slide-21
SLIDE 21

Ability to influence change Time

Feasibility Concept Design Concurrent Design & Fabrication Design Assembly Operation

MacLeamy’s Curve

slide-22
SLIDE 22

What is BIM?

slide-23
SLIDE 23

“A coordinated digital dataset that contains appropriate computable information necessary to design, build, operate and ultimately decommission a project”

* Sharing Structured Information Defining BIM

slide-24
SLIDE 24

Information Communication Technology Project Information Management

Building Information Model (Management)

Project Team members need coordinated up to date information to be able to do modelling & calculations Project Team members need carry out tasks in such a way that they are easily coordinated, recorded and verified Project Team members need to be able to exchange and stored project data quickly and with confidence

Geometrical & Technical Simulations (Virtual Prototype)

BIM

BIM is.... ...Sharing Structured Information

slide-25
SLIDE 25

In fact…

  • BIM is not confined to Buildings. It is a tool for the built

environment and equally applicable to any asset. (Perhaps Asset is more appropriate than Building!)

  • Model does not mean 3D model. Think Financial Model or

Scientific Model. It reflects the way something behaves rather than limited to physical existence.

  • Information is key.

...Perhaps Asset Information Management is more appropriate!

slide-26
SLIDE 26

BIM = Total Architecture

“The term ‘Total Architecture’ implies that all relevant design decisions have been considered together and have been integrated into a whole by a well organised team empowered to fix priorities” Sir Ove Arup – The Key Speech - 1970 “This is an ideal which can never – or only very rarely – be fully realised in practise, but which is well worth, for striving for artistic wholeness or excellence depends on it, and for our own sake we need the stimulation produced by excellence” “This is an ideal which can never – or only very rarely – be fully realised in practise, but which is well worth

slide-27
SLIDE 27

Geometry

slide-28
SLIDE 28

"Let no man ignorant of geometry enter here."

Inscribed over the entrance to Plato’s academy in ancient Greece.

slide-29
SLIDE 29

China Comic and Animation Museum (CCAM) Architect: MVRDV

slide-30
SLIDE 30

CCAM - Bubbles

Collection Interaction Theatre Library Education Lobby

slide-31
SLIDE 31

CCAM Bubbles

slide-32
SLIDE 32

CCAM Evolution to final concept

Arches between Theatre and Interactive Bubbles

slide-33
SLIDE 33

CCAM – Complex Interactions between bubbles

Leg Outline Adjacent Bubble Intersection Boundary Lines

slide-34
SLIDE 34

Main Intermediate

CCAM – Complex Interactions between bubbles

slide-35
SLIDE 35

This is where it gets interesting

Main Intermediate Theatre Main Intermediate Interactive The intersections don’t line up!

slide-36
SLIDE 36

Main Intermediate Theatre We need to use the points from the Theatre Bubble to define the lines for the Intersection so that the arches will line up Points of Intersection

CCAM – Complex Interactions between bubbles

slide-37
SLIDE 37

CCAM - This is where it gets interesting

Main Intermediate Theatre Main Intermediate Interactive (Below Occ) The intersections don’t line up! Main Intermediate Interactive (Above Occ)

slide-38
SLIDE 38

CCAM – VBA Code

slide-39
SLIDE 39

CCAM - Education: Vertical Frames

Vertical Frames correspond with floor levels

slide-40
SLIDE 40

CCAM - Education: Horizontal Frames

Horizontal Frames at floor levels and share load between vertical frame

slide-41
SLIDE 41

CCAM - Education Bubble Complete

slide-42
SLIDE 42

CCAM - Complete Model

slide-43
SLIDE 43

CCAM - Complete Model

slide-44
SLIDE 44

Simulation

slide-45
SLIDE 45

CCAM - Structural Analysis Model

slide-46
SLIDE 46

Rationalisation

China Comic and Animation Museum - Process

Architectural Requirements 3D Parametric Model Structural Analysis Model Member Design Analysis 2D Drawing

slide-47
SLIDE 47

Evolution of Optimisation

Structural Optimisation

Large Analytical Models Automated Design of Elements Spreadsheets Hard Code Optimisation

  • Optimisation for Minimum Weight
  • Optimisation for No of Elements
slide-48
SLIDE 48

Roof space frame sizing optimization

slide-49
SLIDE 49

Virtual Prototype

slide-50
SLIDE 50

Virtual Prototype

slide-51
SLIDE 51

Virtual Prototype

slide-52
SLIDE 52

Virtual Prototype

slide-53
SLIDE 53

Virtual Prototype

slide-54
SLIDE 54

Virtual Prototype

slide-55
SLIDE 55

OBJECTIVES

  • Minimize steel weight

VARIABLES

  • 1955 member size variables

(~20 size choices) CONSTRAINTS

  • Strength (BS5950 2000)
  • Deflection (SPAN / 360 for SLS)
  • Architectural requirements

Universal Beam (UB) Section Rectangular Hollow Section (RHS) Circular Hollow Section (CHS)

Optimisation

Structural Optimisation

slide-56
SLIDE 56

1414 1146 200 400 600 800 1000 1200 1400 1600

PRODUCT METRICS Conventional Design Optimized Design Design Method Design Cycle Time Total Design Cycles Total Time Conventional 4 hrs 39 9360 min Serial Opt (1 CPU) 6 min 8042 48250 min Parallel Opt (128 CPUs) 3 sec 8042 402 min Total Steel Weight (met tons)) 1146 1414 PROCESS METRICS

  • 19%

(~$5M savings)

Optimisation

Structural Optimisation

slide-57
SLIDE 57

Communication

slide-58
SLIDE 58

Virtual Design Review

slide-59
SLIDE 59

Virtual Design Review meetings

Sharing Information at the Human level

slide-60
SLIDE 60

Fabrication

slide-61
SLIDE 61

Renkioi Hospital, Dardanelles

  • Commissioned February 1855
  • Brunel played the roles of architect,

planner, structural engineer, mechanical, electrical and public health engineers and management contractor.

  • Design Period: 6 days
  • Fabricated & Shipping byMay
  • First 300 patients on 11 August 1885
  • 1000 beds by December
  • By the end of March 1856 it could have

accommodated 2,200 patients.

  • PreRenkioi, mortality rates were 42%.

Once Brunel's hospital was operational, deaths fell to 3.5%.

slide-62
SLIDE 62

Crystal Palace – The Great Exhibition

  • 563m long by 124m wide
  • 400 tons of glass, and 4000 tons of iron,
  • Floor area of 74,320 m2 with over 8 miles of tables
  • Displaying over 100,000 objects
slide-63
SLIDE 63

Crystal Palace - Design Team

Joseph Paxton Head Gardener at Chatsworth House Experience: Orangery & The Large Greenhouse

slide-64
SLIDE 64

Crystal Palace - Design Team

William Cubitt Chairman of Building Committee of Great Exhibition and consulting engineer Charles Fox Specialist Contractor

slide-65
SLIDE 65

Crystal Palace – The Great Exhibition

  • First Plans in 9 days
  • Built in 9 months
  • With a workforce of 5000
  • 84,000 m2 of Glass
  • First major installation of public toilets
slide-66
SLIDE 66

Empire State Building

102 Storeys / 381m / 257,100 m2 Architect William F Lamb (Shreve, Lamb and Harmon) Drawings produced in 2 weeks Contractor The Starrett Brothers and Eken Start on site 21 January 1930 Main construction 17 March 1930 Official opened on 1 May 1931 ( 1 year and 45 days) 340, 000 tons of steel, 6,500 windows, 64 lifts, 70 miles of pipework,

slide-67
SLIDE 67

Empire State Building

slide-68
SLIDE 68

Why do buildings take longer?

  • Increasing complexity. Building systems are far more complex now.
  • A modern building is unrecognisable from the Renkioi Hospitals
slide-69
SLIDE 69

Design for Manufacture

  • Offsite Manufacture
slide-70
SLIDE 70

Design for Manufacture – 122 Leadenhall Street

Client: British Land/Oxford Propeties Architect: Rogers Stirk Habour + Partners Main Contractor: Laing O’Rouke Specialist Steelwork: Wastons

slide-71
SLIDE 71

Telka is the default detailing package in the structural steel industry

slide-72
SLIDE 72

Design for buildability

slide-73
SLIDE 73

Design for buildability

slide-74
SLIDE 74

Design for buildability

Working in close collaboration with specialist fabricator

slide-75
SLIDE 75

Analysis, detailing, fabrication

Typical information provided to specialist fabricators

slide-76
SLIDE 76

Analysis, detailing, fabrication

Tekla Drawing Model Rhino Transition Model Excel Load Input GSA Global Analysis D3 Plot Stress checks Excel/VB Weld checks ANSA Meshing Nastran Analysis

Steelwork Design for fabrication process

slide-77
SLIDE 77

Modelling, Analysis, Design, Fabrication

TEKLA RHINO GSA Steelwork Design for fabrication process

slide-78
SLIDE 78

Analysis, detailing, fabrication

slide-79
SLIDE 79

Analysis, detailing, fabrication

Steelwork Design for fabrication process – weld thickness graphs

slide-80
SLIDE 80

Analysis, detailing, fabrication

Steelwork Design for fabrication process – Fabrication Drawings

slide-81
SLIDE 81

Analysis, detailing, fabrication

Steelwork Design for fabrication process – Fabrication Drawings

slide-82
SLIDE 82

Analysis, detailing, fabrication

Steelwork Design for fabrication process – full size mock up

slide-83
SLIDE 83
slide-84
SLIDE 84
  • Collaborative approach
  • Grounded by engineering principles
  • Design and production through BIM
  • Reduced risk
  • Faster programme
  • Unique architecture

Leadenhall Building An exemplar project for design for manufacture

slide-85
SLIDE 85

Conclusions

slide-86
SLIDE 86

Asset Management Supply Chain Management 4D Modelling Engineering Optimisation Whole life costing Interior Design & Fit out Façade Design Quantities Extraction Building Information Modelling/ Management Building Services Architectural Design Clash detection & coordination Structural Design Adaptive Survey & Drawing Digital Fabrication Real time value Engineering Real-time progress reporting & RFI

Unified Approach to BIM(M)

slide-87
SLIDE 87

Handover As Built Construction

Object included in handover data set with corresponding population of AIM . As - built changes incorporated & data set updated as necessary . Object data fields completed progressively . Schedules & takeoffs . Object carried into design development . 3 D view for spatial fit . Schedules & take -

  • ffs

. Library object used in concept GA - simple plan view

Design

Whole Lifecycle Information Management

Current Practice

Concept

E x a m p l e ,

Information Flow across the Project Life-Cycle

?

Data, Information & Knowledge

slide-88
SLIDE 88

The Future?

slide-89
SLIDE 89

The Future?

slide-90
SLIDE 90

The only constant in this world is change….

slide-91
SLIDE 91

91

We only have the earth

slide-92
SLIDE 92