SLIDE 1 Hill St / SH 1 Intersection
Puhoi to Warkworth Project - Submission to NZTA to construct improvements at Hill Street Intersection prior to the Project Construction
SLIDE 2
SLIDE 3 What is the problem?
Delays occur not only at peak hours but can
- ccur at any time of the day.
The intersection configuration is poorly
managed.
It chokes very easily.
SLIDE 4
Elizabeth Street traffic
SLIDE 5
Who gives way to what?
SLIDE 6
And here?
SLIDE 7
Informal Slip Lane SH1 North
SLIDE 8
Informal left lane SH1 North
SLIDE 9
SH1 northbound traffic blocked by right turn queue
SLIDE 10
Existing pedestrian crossing facility to northern suburbs
SLIDE 11
More specifically.
Traffic does not clear freely when the
lights change. Queues are often blocked.
Inadequate capacity on SH1. Traffic exiting both Elizabeth St and
Kowhai Park are faced with concurrent give ways.
Pedestrians are badly catered for.
SLIDE 12
How will the RONS project effect the Hill St Intersection?
SLIDE 13 What do we Know?
That half of the traffic on the Project is actually
going to/from Warkworth.
To do this this traffic will travel 2km north to go
south.
Most of the Project’s Warkworth traffic goes
through the Hill Street Intersection.
It is not logical to go north to go south. It is not economic. A connection to/from the Project south of
Warkworth would reduce traffic at Hill Street Intersection.
SLIDE 14
What are the predicted traffic flows in 2026?
SLIDE 15 What is the predicted effect of the Project on Hill St Intersection in 2026?
SH1 South traffic is down 32% and Hill St traffic
is up 30%
SH1 North traffic is 6% down and Elizabeth St
traffic is 11% up.
Matakana Road and Sandspit traffic is much
the same.
These % do not recognise that traffic in the 12
years has also increased by 4% pa (48%).
THE TRAFFIC AT THE HILL ST
INTERSECTION IS NOT REDUCED!
SLIDE 16
SLIDE 17 Proposed Matakana Link Road
At Hill Street Intersection only 40% of the
eastern traffic comes from Matakana Road. 60% comes from Sandspit Road
33% of the Matakana Road and Sandspit Road
traffic turns off into Elizabeth Street. A significant % will be going to Woodcocks Road
The Link cannot reduce the eastern traffic at Hill
St Intersection by more than 20% ( probably less than 15%).
Link is useful but is NOT A SOLUTION for
the Hill Street Intersection!
SLIDE 18 Problems with Project Construction Traffic at the Hill St Intersection
Clearance rate of traffic on SH1 through the signals per
cycle is low. Typically a max of 15 to 20 vehicles.
An addition of 2 vehicles per cycle of construction traffic
- n SH1 is not minor as stated by the NZTA consultant.
Concrete and Metal truck and trailer units from Matakana
have a very poor clearance rate because of stacking problems around Elizabeth Street. This is not minor as stated by the NZTA consultant.
Truck and trailer units can block Elizabeth St. CONSTRUCTION TRAFFIC IS A SIGNIFICANT
PROBLEM
SLIDE 19
Truck and trailer over line but still blocking Elizabeth Street
SLIDE 20
What are the options for Hill St Intersection?
NZTA 2009 Proposal or similar. Large Roundabout Do Minimum (10 years only) Do Nothing
SLIDE 21 NZTA current proposed upgrade (2009)
NZTA say this will not be started until after the
Project is completed. This suggests that Hill Street Improvements will not be complete for 10 years.
In the meantime the Hill St Intersection
problems only get worse.
Growth rates in the interim are likely to be of the
Construction in 10 years time will be more
difficult at the completion of the Project because this traffic growth.
SLIDE 22
SLIDE 23 Current (2009) NZTA proposal Main Features
This proposal offers a managed solution Includes traffic Signals at both Sandspit Road
and Hill St.
All Elizabeth St outbound traffic goes through
the main traffic signals. Intersection now has 5 legs increasing signal delays.
Intersection is more than twice as large creating
longer delays while signals change.
Stacking lengths are improved. Additional lanes from south but no widening of
SH1 bridge south of Shoesmith Street.
No right turn into Hill St from SH1 north.
SLIDE 24
Large Roundabout
Possible alternative design based on a
rotary intersection.
SLIDE 25
SLIDE 26 Advantages of the Large Roundabout
Rotary intersections have simple ‘give way to the right’
decisions.
Large size means one decision taken at a time Addition of a SH1 straight through only lane with traffic
signals gives a direct path for the major flow.
Traffic signals intercept the major flow giving minor legs
the opportunity to enter the rotary intersection.
Hill St can be entered from the north via the roundabout
c/f NZTA option.
Construct now and Project construction traffic will be
improved.
Warkworth residents will have better access
SLIDE 27
Advantage to pedestrians
The new road bridge over the stream
allows pedestrians and mobility scooters access to the traffic signals via an underpass.
The traffic signal sequence allows more
time to cross to Warkworth.
Traffic is one way and there is no threat
to pedestrians from turning traffic.
SLIDE 28
Construction
A large part of the alternative design can
be constructed off the highway.
The balance is improvements uses the
existing construction as a base.
Services are largely unaffected. Land purchase is not required.
SLIDE 29
Do Minimum (10 years only)
Increases capacity SH1 both ways Improves queuing and clearance on SH1
and thus improves SH1 capacity.
Improves traffic flow from Matakana and
Sandspit.
Improves access for pedestrians and
provides access to Kowhai park.
However DOES NOT SOLVE
management issues at Elizabeth St.
SLIDE 30
SLIDE 31
SLIDE 32
Do Nothing
Problems get worse during the
construction of the Project.
Project does not solve Hill St
intersection, it only gets worse
NZTA will ALIENATE both the SH1
users and the Warkworth/ Mahurangi residents FOR THE NEXT 10 years.
SLIDE 33
Rodney Board calls for action
SLIDE 34 Conclusion
The Project is not a solution for the Hill Street
Intersection.
Construction Traffic from the Project will
significantly increase the problem.
Problems at Hill St Intersection will only get
worse
Procrastination is not a solution Prior improvement of Hill St Intersection
should be a condition of the Project
Thank you for your attention