oak hill parkway
play

OAK HILL PARKWAY Industry Workshop October 11, 2018 Oak Hill - PowerPoint PPT Presentation

OAK HILL PARKWAY Industry Workshop October 11, 2018 Oak Hill Parkway Design-Build Project October 11, 2018 Safety Moment October 11, 2018 Oak Hill Parkway Design-Build Project October 11, 2018 Table of Contents 1 Project Purpose and Need


  1. OAK HILL PARKWAY Industry Workshop October 11, 2018 Oak Hill Parkway Design-Build Project October 11, 2018

  2. Safety Moment October 11, 2018 Oak Hill Parkway Design-Build Project October 11, 2018

  3. Table of Contents 1 Project Purpose and Need 4 2 Proposed Project Overview 5 - 10 3 Project Status and Challenges 11 - 14 4 Qualification Statement Evaluations 15 - 21 5 Procurement Timeline 22 6 Proposer Responsibilities 23 - 24 7 Disadvantaged Business Enterprises (DBE) 25 - 43 Oak Hill Parkway Design-Build Project October 11, 2018 3

  4. Oak Hill Parkway Project – Purpose and Need  Proj oject ct p purpos ose and n need eed – Improve mobility and operational efficiency – Promote long-term congestion management – Improve safety – Improve emergency response Oak Hill Parkway Design-Build Project October 11, 2018 4

  5. Oak Hill Parkway Project – Overview Oak Oak Hill Hill Par arkway Design-Build d Projec ect  Total le l length: Approximately 7 miles Oak Hill Parkway Design-Build Project October 11, 2018 5

  6. Oak Hill Parkway Project – Overview Oak Oak Hill Hill Par arkway Design-Build d Projec ect  Total le l length: Approximately 7 miles * * *West o of SH 71 there w will b l be t two ( o (2) f frontag age r road oad l lanes i in eac ach d direction on Note: Additional capacity is shown with red arrows Oak Hill Parkway Design-Build Project October 11, 2018 6

  7. Oak Hill Parkway Project – Overview (continued)  US 2 S 290 from Loop 1 (Mo MoPac) t to R RM M 1826 with t trans nsiti tion e n extend nding ng w west o of Circl cle Driv Drive – Three (3) mainlanes for through traffic in each direction – Two (2) to three (3) frontage road lanes in each direction – Overlay from approx. Monterey Oaks Blvd. to MoPac – Widen and overlay from Parkwood Dr. to Monterey Oaks Blvd. – Full reconstruction from Circle Dr. to Parkwood Dr. • New overpass for the US 290 mainlanes over William Cannon Dr. • Depressed mainlanes of US 290 under SH 71 at US 290 / SH 71 interchange – Full intersections constructed along US 290 at Convict Hill Rd., RM 1826, Scenic Brook Dr., and Circle Dr. (South View Rd.) Oak Hill Parkway Design-Build Project October 11, 2018 7

  8. Oak Hill Parkway Project – Overview (continued)  Two wo Direct C Connector ors (S-E a E and W W-N directio ion) Oak Hill Parkway Design-Build Project October 11, 2018 8

  9. Oak Hill Parkway Project – Overview (continued)  SH SH 71 (f (from U US S 290 to Si Silvermine Dr Dr.) – Full reconstruction from US 290 to Silvermine Dr. – Direct Connector ramps to extend past Scenic Brook Dr. where the mainlanes transition to a five-lane (three lanes northbound, two lanes southbound) rural highway with U-turns for local access  Multiple stormwater detention and water quality treatment ponds within the corridor  Bicycle and pedestrian accommodations along entire corridor, including seven-mile shared-use path, sidewalks, and trailhead at Williamson Creek on William Cannon Dr.  Landscaping, tree protections & plantings, and corridor aesthetics Oak Hill Parkway Design-Build Project October 11, 2018 9

  10. Oak Hill Parkway Project – Overview (continued) Oak Hill Parkway Design-Build Project October 11, 2018 10

  11. Project Status  Contract M Method hod – Design-Build Contract with an anticipated 5-year Performance Warranty.  Project C t Cost E t Estima mate – Anticipated Design-Build Contract (DBC) cost of $467.2M.  Di Disadvantaged Business E Enter erpr prise (DB DBE) Go Goal – It is anticipated that there will be a DBE goal of 7.0% for construction. – It is anticipated that there will be a DBE goal of 12.6% for professional services.  Envir ironm nment ntal al C Clear aranc ance – TxDOT is pursuing a Record of Decision for the Project and environmental clearance is anticipated in December 2018. – A Public Hearing for the DEIS was held on May 24, 2018. Information can be found on the public meeting website: http://www.oakhillparkway.com/environmental/public-input.php Oak Hill Parkway Design-Build Project October 11, 2018 11

  12. Project Status (continued)  Design a and nd C Cons nstruction – A draft schematic currently under review by TxDOT will be provided in the Reference Information Documents (RIDs). – Schematic approval is anticipated in conjunction with completion of the environmental process.  Ri Right of W of Way (R (ROW) – TxDOT anticipates the need for ROW acquisition services for this Project (approximately 80+ parcels). – TxDOT is currently developing ROW maps for the Project and will begin the ROW appraisal and acquisition process and continue this process until contract execution. – If the ROW acquisition process has not been completed by contract execution, it is anticipated that the DB Contractor will complete TxDOT ROW acquisition efforts. Oak Hill Parkway Design-Build Project October 11, 2018 12

  13. Project Status (continued)  Geotech chnica cal – TxDOT will conduct geotechnical investigations and provide the information to shortlisted proposers as it becomes available. – A geotechnical report is anticipated to be available in the Spring of 2019.  Utili lities – The DB contractor will be responsible for performing necessary utility relocations / adjustments. – TxDOT anticipates providing SUE Level B-D and Level A at isolated locations to shortlisted proposers prior to issuance of the RFP in the Spring of 2019.  Railroad – There are no railroad crossings on the project.  Hazardous M Material I Investigations – The environmental documents to be included in the RIDs will include studies showing the results of hazardous materials assessments related to the Project. Oak Hill Parkway Design-Build Project October 11, 2018 13

  14. Project Challenges  Construction phasing  Traveling impacts during construction – Work Zone management strategies – Traffic Incident management (inside work areas---emergency response)  Business impacts during construction (accommodate business owners’ needs)  Environmentally sensitive area – Edwards Aquifer recharge zone / contributing zone  Karst feature mitigation  Minimal disturbance to waters of US and wetlands  Tree protections/preservations  Utility relocations and impacts  ROW acquisition efforts  Drainage design Oak Hill Parkway Design-Build Project October 11, 2018 14

  15. PROJECT PROCUREMENT Oak Hill Parkway Design-Build Project October 11, 2018

  16. Qualification Statement Evaluations THE PROCUREMENT PROCESS QS Request for Request for Conditional Evaluations Qualifications Proposals Award (Shortlisting)  Two step procurement process – RFQ – RFP  QS Evaluations (Shortlisting) - How each QS will be evaluated: – Project Qualifications and Experience (60% weighting) – Statement of Technical Approach (30% weighting) – Safety Qualifications (10% weighting) Oak Hill Parkway Design-Build Project October 11, 2018 16

  17. Qualification Statement Evaluations  Proj oject Q Qualifi fications a and Experience (60% (60% we weighting) – Experience with designing comparable projects (8 p 8 poi oints) – Experience with constructing comparable projects (8 p 8 poi oints) – Experience with independent quality assurance on comparable projects (8 p 8 poi oints) – Strength of the proposed organization and management structure (4 p 4 poi oints) – Experience of the Key Personnel for the Project (29 p 29 poi oints) – Responsiveness toward the DBE involvement, objectives and goals (3 p 3 poi oints) Oak Hill Parkway Design-Build Project October 11, 2018 17

  18. Qualification Statement Evaluations  Key Personne nnel Experienc nce ( (29 p points t total al) – Project Manager (5 po points) – Independent Quality Firm (IQF) Manager (5 po points) – Construction Manager (4 po points) – Design Manager (4 po points) – Professional Services Quality Assurance Manager (PSQAM) (4 po points) – Environmental Compliance Manager (2 po points) – Right of Way (ROW) Manager (1 po point) – Utility Manager (1 po point) – Lead Maintenance of Traffic (MOT) Design Engineer (1 po point) – Certified Arborist (1 po point) – Safety Manager (1 po point) Oak Hill Parkway Design-Build Project October 11, 2018 18

  19. Qualification Statement Evaluations  Statement of of Tech chnical Approa oach (30% (30% we weighting) – Demonstrate a full understanding of the Project’s scope and complexity (8 po points) – Demonstrate a complete understanding of Project risks and potential solutions that may arise during all Project phases, including design and construction (11 po points) – Demonstrate a complete understanding of interaction between Quality Control, Independent Quality Firm, Professional Services Quality Assurance Firm and Owner Verification, Testing and Inspection and the ability to plan, organize, execute, assure and control the quality of the Work with respect to design, testing, and inspections (11 11 p points ts)  Safety Q Quali lifications ( (10% weigh ghting) g) – Fatal injury rate per 100,000 full-time workers (3 po points) – Incidence rate of injury and illness cases per 100 full-time workers (4 po points) – National Council on Compensation Insurance (“NCCI”) experience modifier (3 po points) Oak Hill Parkway Design-Build Project October 11, 2018 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend