Project Texas Transportation Commission April 30, 2020 April 30, - PowerPoint PPT Presentation

Oak Hill Parkway Project Texas Transportation Commission April 30, 2020 April 30, 2020 Oak Hill Parkway Project Minute Order authorization Summary of Commission Actions: Authorize the condit itio iona nal award d to the best value


  1. Oak Hill Parkway Project Texas Transportation Commission April 30, 2020 April 30, 2020 Oak Hill Parkway Project

  2. Minute Order authorization Summary of Commission Actions: ▪ Authorize the condit itio iona nal award d to the best value proposer for the design-build contract (DBC) for the Oak Hill Parkway Project in Travis County. ▪ Authorize TxDOT to commence and complete negotiations with the best value proposer and to modify the DBC, as necessary, as a result of such negotiations in preparation for the execution and delivery of the DBC. ▪ Authorize TxDOT, in the event that the negotiations with the selected proposer cannot be successfully completed, to commence negotiations with the next proposer in the order of the selection ranking. April 30, 2020 Oak Hill Parkway Project 2

  3. Design-build scope ▪ Ranks #29 on the 2019 Top 100 Most Congested Roadways in Texas* ▪ Project limits: – Along US 290 from just east of Circle Dr. to Loop 1 – Along SH 71 from US 290 to Silvermine Dr. ▪ Project purpose: – Improve mobility and operational efficiency – Promote long-term congestion management – Improve safety – Improve emergency response * Was #53 on the 2018 Top 100 Most Congested Roadways in Texas and #64 on the 2017 Top 100 Most Congested Roadways in Texas. April 30, 2020 Oak Hill Parkway Project 3

  4. Overview ▪ Texas Clear Lanes Project ▪ Total length: – US 290: 5.8 miles – SH 71: 1.2 miles ▪ Increased capacity: – US 290 mainlanes – SH 71 mainlanes – Reconstruction of US 290 and SH 71 * * interchange ▪ Added and existing capacity is non-tolled *West of SH 71 there will be two frontage road lanes in each direction. Additional capacity is shown with red arrows. April 30, 2020 Oak Hill Parkway Project 4

  5. Proposals submitted Colorado River Constructors Flatiron-Lane Oak Hill Joint Venture Hill Country Infrastructure Equity members Equity members Equity members Fluor Enterprises, Inc. Flatiron Constructors, Inc. Webber, LLC Balfour Beatty Infrastructure, The Lane Construction Ferrovial Agroman US Corp. Inc. Corporation Major non-equity members Major non-equity members Major non-equity members AECOM Technical Services, Inc. Bridgefarmer & Associates, Inc. CONSOR Engineers, LLC Raba Kistner, Inc. The Levy Company, Inc. OTHON, Inc. Wood Environment & Rodriguez Engineering Infrastructure Solutions, Inc. Laboratories, LLC April 30, 2020 Oak Hill Parkway Project 5

  6. Best value recommendation Colorado River Constructors Colorado River Constructors Price Equity members Fluor Enterprises, Inc. Design-build $677,099,500 Balfour Beatty Infrastructure, Inc. Proposal Rankings 1. Colorado River Constructors 2. Hill Country Infrastructure 3. Flatiron-Lane Oak Hill JV April 30, 2020 Oak Hill Parkway Project 6

  7. Next steps ▪ Negotiate final terms of the design-build contract ▪ Federal Highway Administration concurrence with final award ▪ Final award and execution anticipated in Summer 2020 ▪ Anticipate substantial completion date in late 2025 April 30, 2020 Oak Hill Parkway Project 7

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.