This presentation is for the project on US 10 and WIS 65 in the village of Ellsworth, Pierce County. Rather than holding an in-person meeting, public involvement efforts have moved online as a precaution against COVID-19 based on the most current


slide-1
SLIDE 1

This presentation is for the project on US 10 and WIS 65 in the village of Ellsworth, Pierce County. Rather than holding an in-person meeting, public involvement efforts have moved online as a precaution against COVID-19 based on the most current health information from state, federal and local health departments. All meeting materials, including the handout with a comment form, are posted

  • n the design website for this project.

https://wisconsindot.gov/Pages/projects/by-region/nw/us10wis65ellsworth/default.aspx

If you have any questions, please contact WisDOT Project Supervisor James Koenig at (715) 838-8391.

slide-2
SLIDE 2

US 10

Village of Ellsworth Main Street WIS 65 to N. Beulah St.

Public Involvement Meeting

WIS 65

Village of Ellsworth Maple Street US 10 to Midway Ave.

slide-3
SLIDE 3

Project Team

  • James Koenig
  • WisDOT Project Supervisor
  • Brett Hollister
  • WisDOT Consultant Project Manager
  • Julie Martin
  • WisDOT Real Estate Specialist
  • Brad Halvensleben
  • Consultant Project Manager (KL Engineering, Inc.)
slide-4
SLIDE 4

Presentation Agenda

  • Project Location
  • Project Purpose and Need
  • Proposed Improvements
  • Construction Staging
  • Real Estate
  • Project Schedule
  • Contact Information
slide-5
SLIDE 5

Project Location

slide-6
SLIDE 6

Purpose and Need

  • Purpose
  • Improve US 10 and WIS 65 pavement condition
  • Improve truck turning at the US 10 and WIS 65 intersection
  • Upgrade curb ramps to meet current standards
  • Need
  • Deteriorating pavement condition
  • Conflicting truck turning movements at the US 10 and WIS 65

intersection

  • Non-compliant curb ramps
slide-7
SLIDE 7

Proposed Improvements

  • Resurface US 10 with asphalt pavement
  • Mill and resurface WIS 65 with asphalt pavment
  • Realign left-turn lanes at US 10 and WIS 65 intersection
  • Upgrade curb ramps
  • Replace pavement marking
slide-8
SLIDE 8

Proposed Construction Staging

  • 2021 construction season (June-October)
  • Open to traffic
  • Single-lane closures through flagging operations
  • Pedestrian detours during curb ramp replacement
slide-9
SLIDE 9

Real Estate

  • Real Estate acquisition for US 10 and WIS 65 intersection

improvements

  • Temporary easements for curb ramp upgrades
  • Real Estate Acquisition Process
  • Contact: Julie Martin, (715) 836-2875 or

julie.martin@dot.wi.gov

slide-10
SLIDE 10

Project Schedule

  • Environmental Document

January 2020

  • Preliminary Plans

January 2020

  • Real Estate Plat

May 2020

  • Public Involvement Virtual Presentation

July 2020

  • Final Plans

November 2020

  • Construction

Summer 2021

slide-11
SLIDE 11

What we need from you

Share Your Concerns or Comments

https://wisconsindot.gov/Pages/projects/by-region/nw/us10wis65ellsworth/default.aspx

Responses returned by Aug. 14, 2020

  • By email: HollisterB@AyresAssocites.com
  • By mail:
  • James Koenig

Wisconsin Department of Transportation 718 W. Clairemont Ave. Eau Claire, WI 54701

Thank you for your time

slide-12
SLIDE 12

Project Team

  • James Koenig, WisDOT Project Supervisor
  • (715) 838-8391
  • james.koenig@dot.wi.gov
  • Brett Hollister, WisDOT Consultant Project Manager
  • (715) 834-3161
  • HollisterB@AyresAssociates.com
  • Julie Martin, WisDOT Real Estate Specialist
  • (715) 836-2875
  • julie.martin@dot.wi.gov
  • Brad Halvensleben, Consultant Project Manager
  • (608) 663-1218, Ext. 826
  • bhalvensleben@klengineering.com