WIS 96 Project Update Tim Rank, Project Manager Jeremy Bartz, Project Leader WisDOT July 2020 WIS 96 Overview Proposed Project Scope/Need Proposed Improvements Right-of-way Needs Traffic Control Schedule Resources


slide-1
SLIDE 1

WIS 96 Project Update

Tim Rank, Project Manager Jeremy Bartz, Project Leader

WisDOT

July 2020

slide-2
SLIDE 2

WIS 96

  • Overview
  • Proposed Project Scope/Need
  • Proposed Improvements
  • Right-of-way Needs
  • Traffic Control
  • Schedule
  • Resources
  • Project Contacts
slide-3
SLIDE 3

WIS 96 Proposed Project Scope/Need

  • Projects 4075-35-71 and 4075-35-72 include

4.9 miles of WIS 96 from Claribel Street to County D, between Kaukauna and Wrightstown in Brown & Outagamie County (will be built together)

  • Last improvement project took place in 2000

and 2005

slide-4
SLIDE 4

WIS 96 Proposed Project Scope/Need

  • Deteriorating pavement, drainage structures,

curb and gutter, and sidewalk need repair

  • Multiple curb ramps along the corridor are

currently not Americans with Disabilities Act (ADA) compliant.

slide-5
SLIDE 5

WIS 96 Proposed Project Scope/Need

slide-6
SLIDE 6

WIS 96 Proposed Improvements

  • 4075-35-71 (Claribel Street to County J)
  • Resurface level improvement: mill and overlay within the existing pavement

footprint

  • Culvert pipe repair/replacement-2 locations
  • Miscellaneous curb & gutter repairs
  • Curb ramp improvements at Lamp Lighter Dr.
  • Pavement marking
  • Shoulder work
  • Additional project information, including project displays, can be

found at the design website listed on the Resources slide.

slide-7
SLIDE 7

WIS 96 Proposed Improvements

  • 4075-35-72 (County J to County D)
  • Resurface level improvement: mill and overlay within the existing pavement

footprint

  • Culvert pipe repair/replacement-5 locations
  • Storm sewer repair/replacement-4 locations
  • Miscellaneous curb & gutter or sidewalk repairs
  • Curb ramp improvements at all intersections within Wrightstown
  • Pavement marking
  • Shoulder/centerline rumble strips: from County J to Van Dyke Street
  • Shoulder work: from County J to Van Dyke Street
  • Additional project information, including project displays, can be

found at the design website listed on the Resources slide.

slide-8
SLIDE 8

WIS 96 Right-of-way Needs

  • Temporary Limited Easements (TLE)
  • Will be needed at some culvert replacement locations to allow for

temporary disturbance and sufficient work space to repair pipes

  • Needed at most curb ramp improvement locations within the Village of

Wrightstown to allow grading and blending in of adjacent properties

  • Permanent (Fee)
  • Will be needed at some curb ramp improvement locations in the village
  • f Wrightstown due to updated layout of the sidewalk
  • Will purchase area were existing sidewalk is outside of the existing

right of way to place the sidewalk into WisDOT right of way for future maintenance needs

  • May need at select culvert locations…to be confirmed in final design
slide-9
SLIDE 9

WIS 96 Traffic Control

  • Work expected to take place under flagging
  • perations with single lane closures
  • Road will remain open to traffic during

construction for the majority of the project….except:

  • Short term detour will be needed for culvert pipe

replacements

  • Tentative detour = WIS 55 - I-41 - County U
slide-10
SLIDE 10

WIS 96 Schedule

  • Additional public outreach will be conducted in

late 2021 to provide updates prior to real estate acquisition and final design.

  • Real estate acquisition will begin in early 2022.
  • Design is on-going and will continue through

the summer of 2023.

  • Construction is tentatively scheduled for 2025

with the possibility of advancement to 2024 if funding becomes available.

slide-11
SLIDE 11

WIS 96 Resources

  • Design website
  • https://wisconsindot.gov/Pages/projects/by-

region/ne/96kauwrit/default.aspx

  • See website for comment sheet and exhibits
  • Track the project during construction on the WisDOT Northeast

Region Construction Website

  • https://projects.511wi.gov/region/northeast
  • In This Together
  • Recognizes businesses located in work zones have special

needs

  • The program is offered to business and community leaders as

an idea source as they plan for road construction in their area

  • Find out more at: http://wisconsindot.gov/Pages/projects/in-

together/default.aspx

slide-12
SLIDE 12

WIS 96 Project Contacts

Tim Rank, P.E. Project Manager WisDOT NE Region 944 Vanderperren Way Green Bay, WI 54304 Phone: (920) 360-2579 Email: tim.rank@dot.wi.gov Jeremy Bartz, P.E. Project Leader WisDOT NE Region 944 Vanderperren Way Green Bay, WI 54304 Phone: (920) 363-6356 Email: jeremy.bartz@dot.wi.gov