Thankyou
For additional information contact: Grant Davey Managing Director E: admin@cradleresources.com.au T +61 8 9389 2000
Panda Hill Niobium Cradle Definitive Feasibility Study Panda Hill - - PowerPoint PPT Presentation
For additional information contact: Grant Davey Thankyou Panda Hill Niobium Cradle Definitive Feasibility Study Panda Hill Managing Director E: admin@cradleresources.com.au Investor Update April 2016 T +61 8 9389 2000 Project Panda Hill
For additional information contact: Grant Davey Managing Director E: admin@cradleresources.com.au T +61 8 9389 2000
2
Cradle owns 50% of the Panda Hill Project Single Open Pit Operation Mining 72Mt at 0.54% Nb over 30 years Producing 1.3Mtpa ramping up to 2.6Mtpa after 4th year
Mining Licence and Environmental Licences are in place Panda Hill is located in Mbeya region in South Western Tanzania
Excellent local infrastructure
Panda Hill Overview
Panda Hill Niobium Deposit Panda Hill Proximity to Infrastructure
3
DFS Overview
year 4 to increase capacity from 1.3Mtpa to 2.6Mtpa)
DFS results demonstrated
Panda Hill Overview
Panda Hill Operations
Panda Hill 2015 Resource Reported Above a 0.3% Nb2O5 Lower Cut-off Combined Carbonatite Classification Million Tonnes Nb2O5 % Nb2O5 Content (KT) Measured 16 0.63 9 Indicated 53 0.50 263 Inferred 109 0.48 528 Total 178 0.50 891
Panda Hill Resource
4
100 200 300 400 500 600 700 800 900 1000 FY2016 FY2018 FY2019 FY2020 FY2021 FY2023 FY2024 FY2025 FY2026 FY2028 FY2029 FY2030 FY2031 FY2033 FY2034 FY2035 FY2036 FY2038 FY2039 FY2040 FY2041 FY2043 FY2044 FY2045 FY2046 FY2048
US$M
Panda Hill Overview
Project Free Cashflow
Niobium Price (US/kg Nb) 38 40 42 44 46 Ungeared NPV10 (post-tax) 282 343 404 465 526 Project IRR (post-tax) 23% 25% 27% 30% 32%
NPV & IRR Sensitivity to LT Niobium Price (Management Case) Running NPV10 (100% basis ungeared)
Peak NPV10 ~US$898m
Assumed Case
(3,000) (2,000) (1,000)
2,000 3,000 (150) (100) (50)
100 150 FY2016 FY2018 FY2020 FY2022 FY2024 FY2026 FY2028 FY2030 FY2032 FY2034 FY2036 FY2038 FY2040 FY2042 FY2044 FY2046 FY2048
Cumulativer Cashflow (US$M) Cashflow (US$M)
Cashflow Cumulative Cashflow
5 $122,533 $96,667 $37,615 Elk Creep (NioCorp) Aley (Taseko) Panda Hill (Cradle)
Panda Hill Overview
Capital Intensity vs. Other Undeveloped Deposits
(US$/t annual Nb Production)
Capital Costs Summary
1 1. Production based on average LOM
Item US$m % Summary Project Capital Costs 165.2 84% Pre Production 30.5 16% Total 195.6 100% Project Capital Costs Mining 3.1 2% Plant 75.4 46% Infrastructure 7.8 5% TSF & Water 42.5 26% In-directs 4.2 3% Management Costs 14.3 9% Subtotal 147.3 90% Project Contingency 17.8 10% Project Escalation 0.0 0% Total 165.2 100% Pre-Production First Fills 2.7 9% Spares 1.9 6% Owners 4.7 15% Pre Production 15.0 50% Prison Relocation 6.2 20% Total 30.5 100%
1. Figures have been rounded 2. Peak Working Capital is estimated at US$8.7M
6
Initial 10 years mining predominantly in the higher grade Angel Zone of exclusively Measured and Indicated Resources Key production figures for first 10 years:
Key production figures for Life Of Mine:
Mining Study:
the following parameters
material type)
material type)
49° for weathered domains and 55° for fresh material domains
Panda Hill Overview
Panda Hill Ore Body
7 $22.00/kg $15.00/kg $18.30/kg $21.96/kg
5 10 15 20 25 30 35 40 45 50
Niobec (Magris) Catalão (AngloAmerican) Panda Hill LOM (Cradle) Panda Hill Yrs 1-4 (1.3Mtpa) (Cradle)
Panda Hill Overview
Mine Site Cash Costs
Assumed Long term Niobium Price US$42/kg Nb US$/kg Nb Average Niobium Price over Last 5 Years US$41/kg Nb
It is widely accepted in the industry that CBMM is the lowest cost producer given its enhanced scale & grade, although does not publicly release any financial information
LOM Production Cost Breakdown
US$/kg Nb
$5.01/kg $11.62/kg $1.67/kg $18.30/kg $3.03/kg $21.34/kg 0.00 5.00 10.00 15.00 20.00 25.00 Mining Processing General & Admin Mine Site Cash Cost Transport, Marketing & Royalties Total Cash Cost
8
Design based on successful existing operational Niobium processing facilities
Process Plant Design and Flowsheet
piloting campaigns
4th year of production
Panda Hill Overview
Panda Hill Flow Sheet
9
contained with 22.1km2 of mining licenses
become a long term producer of Niobium
Panda Hill Overview
Carbonatite Boundary Carbonatite Boundary
10 37 37.2 41.1 42.9 42.8 41.1 40.8 2009 2010 2011 2012 2013 2014 2015
Niobium Overview
Niobium Price History (Average annual value of ferroniobium imports, US$/kg)
Between 2006 and 2008 there was a significant increase in prices, instigated by CBMM to address the structural under-valuing of ferroniobium. The market accepted the increase and stability has been retained at the higher level.
11
Niobium Overview
Global Ferroniobium Demand Forecast (kt FeNb)
0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 2012 2013 2014 2015 2016 2017 2018 2019 2020 Base Demand Demand Growth (Expected Steel Growth) Demand Growth (Normal Nb Intensity increase) Demand Growth (Increased China Nb Intensity to 60g/t)
4.1% 3.0% 1.5% CAGR The amount of Nb used per tonne of steel (Niobium Intensity) has been steadily increasing as Nb steel represents the high quality, new-age end of the steel market.
12
Finalise offtake agreements Secure debt financing Value engineering to look at cost reduction opportunities Front end engineering and design on critical items to reduce the construction period Construction permitting processes Procurement of some long lead items Early site establishment from the main site based contractor Formal decision to Mine Q4 CY2016
Project Development