Panda Hill Niobium Cradle Definitive Feasibility Study Panda Hill - - PowerPoint PPT Presentation

panda hill niobium
SMART_READER_LITE
LIVE PREVIEW

Panda Hill Niobium Cradle Definitive Feasibility Study Panda Hill - - PowerPoint PPT Presentation

For additional information contact: Grant Davey Thankyou Panda Hill Niobium Cradle Definitive Feasibility Study Panda Hill Managing Director E: admin@cradleresources.com.au Investor Update April 2016 T +61 8 9389 2000 Project Panda Hill


slide-1
SLIDE 1

Thankyou

For additional information contact: Grant Davey Managing Director E: admin@cradleresources.com.au T +61 8 9389 2000

Panda Hill Niobium Project

Cradle Definitive Feasibility Study – Panda Hill

Investor Update April 2016

slide-2
SLIDE 2

2

Panda Hill Overview

Cradle owns 50% of the Panda Hill Project Single Open Pit Operation Mining 72Mt at 0.54% Nb over 30 years Producing 1.3Mtpa ramping up to 2.6Mtpa after 4th year

  • f production

Mining Licence and Environmental Licences are in place Panda Hill is located in Mbeya region in South Western Tanzania

  • 680km west of capital Dar es Salaam
  • Tanzania has a well-established mining industry and culture
  • Panda Hill deposit is covered by three Mining Licenses
  • Title of these licenses extended to 16 Nov 2026

Excellent local infrastructure

  • TAZARA Rail line (2km away)
  • Dar es Salaam – Tunduma Highway (5km away)
  • Songwe Airport (8km away)
  • Major power infrastructure in Mbeya (26km away)
  • 26km from industrial city Mbeya

Panda Hill Overview

Panda Hill Project

Panda Hill Niobium Deposit Panda Hill Proximity to Infrastructure

slide-3
SLIDE 3

3

Panda Hill will be the worlds next Niobium mine due to robust economics

DFS Overview

  • NPV8 US$542M (post tax)
  • LOM average EBITDA of US$112Mpa
  • 4.75 year pay back
  • Initial capital expenditure of US$196M (expansion US$93m in

year 4 to increase capacity from 1.3Mtpa to 2.6Mtpa)

  • LOM of 30+ years
  • LOM Average Niobium price of US$41.89/kg

DFS results demonstrated

  • NPV8 US$542M (post tax)
  • NPV10 US$404M (post tax)
  • IRR 27% (post tax)
  • LOM C1 US$18.30/kg
  • LOM Total Opex US$21.34/kg

Panda Hill Overview

Panda Hill Project DFS Results

Panda Hill Operations

Panda Hill 2015 Resource Reported Above a 0.3% Nb2O5 Lower Cut-off Combined Carbonatite Classification Million Tonnes Nb2O5 % Nb2O5 Content (KT) Measured 16 0.63 9 Indicated 53 0.50 263 Inferred 109 0.48 528 Total 178 0.50 891

Panda Hill Resource

slide-4
SLIDE 4

4

100 200 300 400 500 600 700 800 900 1000 FY2016 FY2018 FY2019 FY2020 FY2021 FY2023 FY2024 FY2025 FY2026 FY2028 FY2029 FY2030 FY2031 FY2033 FY2034 FY2035 FY2036 FY2038 FY2039 FY2040 FY2041 FY2043 FY2044 FY2045 FY2046 FY2048

US$M

Low Capex, strong margin & long life generates compelling economics and returns with significant leverage to positive niobium outlook

Panda Hill Overview

Compelling Economics

Project Free Cashflow

Niobium Price (US/kg Nb) 38 40 42 44 46 Ungeared NPV10 (post-tax) 282 343 404 465 526 Project IRR (post-tax) 23% 25% 27% 30% 32%

NPV & IRR Sensitivity to LT Niobium Price (Management Case) Running NPV10 (100% basis ungeared)

Peak NPV10 ~US$898m

Assumed Case

(3,000) (2,000) (1,000)

  • 1,000

2,000 3,000 (150) (100) (50)

  • 50

100 150 FY2016 FY2018 FY2020 FY2022 FY2024 FY2026 FY2028 FY2030 FY2032 FY2034 FY2036 FY2038 FY2040 FY2042 FY2044 FY2046 FY2048

Cumulativer Cashflow (US$M) Cashflow (US$M)

Cashflow Cumulative Cashflow

slide-5
SLIDE 5

5 $122,533 $96,667 $37,615 Elk Creep (NioCorp) Aley (Taseko) Panda Hill (Cradle)

Low capital costs due to favourable metallurgy & existing infrastructure, making Panda Hill extremely capital efficient vs. other undeveloped niobium deposits

Panda Hill Overview

Panda Hill Project Capital Cost

Capital Intensity vs. Other Undeveloped Deposits

(US$/t annual Nb Production)

Capital Costs Summary

1 1. Production based on average LOM

Item US$m % Summary Project Capital Costs 165.2 84% Pre Production 30.5 16% Total 195.6 100% Project Capital Costs Mining 3.1 2% Plant 75.4 46% Infrastructure 7.8 5% TSF & Water 42.5 26% In-directs 4.2 3% Management Costs 14.3 9% Subtotal 147.3 90% Project Contingency 17.8 10% Project Escalation 0.0 0% Total 165.2 100% Pre-Production First Fills 2.7 9% Spares 1.9 6% Owners 4.7 15% Pre Production 15.0 50% Prison Relocation 6.2 20% Total 30.5 100%

1. Figures have been rounded 2. Peak Working Capital is estimated at US$8.7M

slide-6
SLIDE 6

6

DFS Demonstrates a Highly Economic Project

Initial 10 years mining predominantly in the higher grade Angel Zone of exclusively Measured and Indicated Resources Key production figures for first 10 years:

  • Average grade: 0.68% Nb2O5
  • Average recovery: 61%
  • Strip ratio: 2.5 to 1

Key production figures for Life Of Mine:

  • Average grade: 0.54% Nb2O5
  • Average recovery: 61%
  • Strip ratio: 1.5 to 1

Mining Study:

  • SRK performed the pit optimisation using Whittle based on

the following parameters

  • LOM Average Niobium price of US$44/kg
  • Processing cost US$22.5 to US$23.3/tonne (depending on

material type)

  • Processing recoveries of 55% to 68% (depending on

material type)

  • Average LOM mining cost
  • $11.35/t ore ($4.42/t TMM)
  • Pit wall angles of bench-stack pit slope angles of 46° and

49° for weathered domains and 55° for fresh material domains

  • 30 year mine life

Panda Hill Overview

Panda Hill Project DFS Parameters

Panda Hill Ore Body

slide-7
SLIDE 7

7 $22.00/kg $15.00/kg $18.30/kg $21.96/kg

5 10 15 20 25 30 35 40 45 50

Niobec (Magris) Catalão (AngloAmerican) Panda Hill LOM (Cradle) Panda Hill Yrs 1-4 (1.3Mtpa) (Cradle)

Operating costs are predominately mining & processing and provide a robust margin relative to long term niobium price

Panda Hill Overview

Robust Operating Costs

Mine Site Cash Costs

Assumed Long term Niobium Price US$42/kg Nb US$/kg Nb Average Niobium Price over Last 5 Years US$41/kg Nb

It is widely accepted in the industry that CBMM is the lowest cost producer given its enhanced scale & grade, although does not publicly release any financial information

LOM Production Cost Breakdown

US$/kg Nb

$5.01/kg $11.62/kg $1.67/kg $18.30/kg $3.03/kg $21.34/kg 0.00 5.00 10.00 15.00 20.00 25.00 Mining Processing General & Admin Mine Site Cash Cost Transport, Marketing & Royalties Total Cash Cost

slide-8
SLIDE 8

8

Design based on successful existing operational Niobium processing facilities

  • The flotation process is similar to Niobec
  • The concentrate leach is similar to Catalao
  • Final step in the conversion process is similar to CBMM

Process Plant Design and Flowsheet

  • Based on extensive testwork undertaken at SGS Canada, including 3

piloting campaigns

  • Expandable plant designed ramping up from 1.3Mtpa to 2.6Mtpa after

4th year of production

Panda Hill Overview

Processing Development

Panda Hill Flow Sheet

slide-9
SLIDE 9

9

Significant Resource Upside

  • Total Carbonatite Mineral Resource of 178Mt at 0.50% Niobium
  • Only ~40% of the area of the carbonatite has been properly drill-tested
  • Mineralisation open in all directions
  • Exploration upside potential for remaining untested 60% of carbonatite

contained with 22.1km2 of mining licenses

  • Represents long asset life in a growing market positioning Panda Hill to

become a long term producer of Niobium

Panda Hill Overview

Geology

Carbonatite Boundary Carbonatite Boundary

slide-10
SLIDE 10

10 37 37.2 41.1 42.9 42.8 41.1 40.8 2009 2010 2011 2012 2013 2014 2015

Niobium has a history of stable prices given increasing underlying demand and supply responsibility

Niobium Overview

Stable Pricing

Niobium Price History (Average annual value of ferroniobium imports, US$/kg)

Between 2006 and 2008 there was a significant increase in prices, instigated by CBMM to address the structural under-valuing of ferroniobium. The market accepted the increase and stability has been retained at the higher level.

slide-11
SLIDE 11

11

Demand has steadily increased since 2000 and is forecast to grow at ~3.0% p.a.

Niobium Overview

Global Demand for Niobium

Global Ferroniobium Demand Forecast (kt FeNb)

0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 2012 2013 2014 2015 2016 2017 2018 2019 2020 Base Demand Demand Growth (Expected Steel Growth) Demand Growth (Normal Nb Intensity increase) Demand Growth (Increased China Nb Intensity to 60g/t)

4.1% 3.0% 1.5% CAGR The amount of Nb used per tonne of steel (Niobium Intensity) has been steadily increasing as Nb steel represents the high quality, new-age end of the steel market.

slide-12
SLIDE 12

12

Next Steps

Finalise offtake agreements Secure debt financing Value engineering to look at cost reduction opportunities Front end engineering and design on critical items to reduce the construction period Construction permitting processes Procurement of some long lead items Early site establishment from the main site based contractor Formal decision to Mine Q4 CY2016

Project Development

Where to from here?