decc cc se seawall pr project ct
play

DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, - PowerPoint PPT Presentation

DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, P PE E CHASE D DEWHIRS RST, P PE AMI Consulting Engineers, PA - Multidiscipline Engineering Firm Marine Civil Structural Mechanical Environmental OWNE NER City


  1. DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, P PE E CHASE D DEWHIRS RST, P PE AMI Consulting Engineers, PA - Multidiscipline Engineering Firm Marine Civil Structural Mechanical Environmental

  2. OWNE NER ∙ City of Duluth / DECC EN ENGINEER ER: ∙ Civil, Marine, Mechanical, Environmental – AMI ∙ Electrical – Gausman & Moore

  3. Limits of Construction: Inner End of MN Slip & STA 0+00 to 12+08

  4. GENERAL CONSTRUCTION OVERVIEW/CONT GENERAL C CONSTRUCTION ON OV OVERVI VIEW  ADDENNDUMS  Install New Epoxy Coated Seawall – 54,810 SF Bid form to include Electrical & Updated Quantities o 1,218 LF x 45’ Length SSP Documentation further explaining what is included in each bid item o o C12x30 Double Wale Final Construction Documents o o 1-3/4” Tierods Historical Documents o o Timber Rub Rails o  Install New Tieback System – 1,140 LF OWNER ER F FUR URNISHED ED M MATER ERIALS HP10x42 Piling o W14x120 Transfer Beam o  Two Request For Bids Currently Out Design Helical Anchors o Structural Steel (Bid Opening 10/31/17) o  Install New Bollards & Foundations – 8 EA  Steel Sheet Pile  Design & Install Camel System – 1 LS  HP10x42 Steel Piling for Tieback System  Demo portions of existing seawall  W14x120 Steel Transfer Beam for Tieback System  Demo Vista Fleet Building  3/8” Bent Steel Cap  Demo Vista Temporary Platform Application of High-Performance Coating (Bid Opening 11/7/17) o  Civil / Mechanical / Electrical Work  Alternatives ***All Owner furnished materials are based on Neat Line Quantities per the #1 – Curb & Gutter / Bike Path o Bid Form. The Contractor is responsible for any additional materials #2 – Remaining Concrete Flatwork & Sidewalks o including the installation of a high-performance coating on the steel sheet #3 – Mechanical Material Installation o piling per the technical specifications. #4 – Electrical Installation o BIDS D DUE 11/ 11/8/1 8/17 o

  5. SITE C CONDITIONS NS & & GENERAL I INFORMA MATION/CONT NT. SITE C CONDITI TIONS & & GENERAL AL I INFORMATI TION  Winter Work  Scope of Work Limits  Staging Areas MN Slip Inner End, and STA 0+00 to 12+08 o On-site – DECC o  Schedule Off-site o Substantial Completion by June 1, 2018  Permits o Final Completion by June 15, 2018 MPCA o o  Liquidated Damages Building Demo o $1,000 per Day after June 1, 2018 o Lane Closures o  Vista Fleet Building DNR, USACE – Pending o Asbestos o Underground Storage Tank o Electronics OWNER ER F FUR URNISHED ED M MATER ERIAL S SCHED EDUL ULE o  Contaminated Soils  Tight Work Area  City Council Meeting: November 20, 2017 May need to shore roadway during Helical  o Steel Sheet Piling & Cap, H Piling, W Beams Anchor Installation FOB DECC: December 18, 2017 o Work restricted within 30’ of existing retaining  o High-Performance Coating on Steel Sheet Piling structure FOB DECC: February 2, 2018 o  Wood Relieving Platform  One lane closure Harbor Drive

  6. Onsite Staging Area Limits of Construction: Inner End of MN Slip & STA 0+00 to 12+08

  7. MARINE W E WOR ORK

  8. MN SLIP INNER END  Existing Steel Sheet Pile  New Steel Sheet Pile Cap

  9. MN SLIP INNER END – Existing Steel Sheet Pile

  10. STA 0+00 to 6+02  Wakefield Piling  Pile Supported Concrete Dock Cap

  11. STA 0+00 to 6+02 – Wakefield Piling

  12. STA 0+00 to 6+02 – Pile Supported with Wakefield Piling

  13. STA 0+00 to 6+02 – Pile Supported with Wakefield Piling

  14. STA 6+02 to 9+00 & 9+25 to 9+85  Wood Relieving Platform  Partial Wall Demolition

  15. STA 6+02 to 9+00 & 9+25 to 9+85 – Wood Relieving Platform

  16. STA 6+02 to 9+00 & 9+25 to 9+85 – Wood Relieving Platform

  17. DOCK W WALL D LL DEMOLI LITION ∙ Demo Temporary Vista Platform ∙ Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

  18. DOCK W WALL D LL DEMOLI LITION  Demo Temporary Vista Platform  Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

  19. DOCK W WALL D LL DEMOLI LITION ∙ Demo Temporary Vista Platform ∙ Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

  20. STA 9+00 to 9+25  Slip Bridge Abutment

  21. STA 9+00 to 9+25 – Slip Bridge Abutment

  22. STA 9+00 to 9+25 – Slip Bridge Abutment

  23. STA 9+85 to 12+08  Crib Dock Wall

  24. STA 9+85 to 12+08 – Crib Supported Concrete Structure

  25. STA 9+85 to 12+08 – Crib Supported Concrete Structure

  26. OTHE HER R R REMA MARK RKS  Survey GPS Points for Seawall Example Shown at STA 6+02 o  Key Submittals Driving Logs & Alignment o Checks – SSP (Daily) Driving Logs & Alignment o Checks – H Piles (Daily) Experienced Surveyor o Helical Anchor Design o Camel System Design o  Irvin Cannot Leave Slip Prior to Dock Wall Rehabilitation  AMI Full Time Project Management

  27. QUESTIONS ON MARINE? Connect with us on:

  28. CIVIL / / ENV NVIRONM NMENT NTAL  Demolition  Grading  Concrete Flatwork  Concrete Sidewalks  Bike Path ELI R EL RUPNOW, P PE E AMI Consulting Engineers, PA

  29. CIVIL / / ENV NVIRONM NMENT NTAL  Demolition Base o  Vista Fleet Building  Irving Loading Platforms  Concrete flatwork, bollards, signage, and other misc. Items

  30. CIVIL / / ENV NVIRONM NMENT NTAL  Demolition Add Alt 1 o  1167 LF of Curb and Gutter  1200 SY of Concrete Pavement  Remove Storm Structure and Adjust Frame and Casting Add Alt 2 o ∙ Concrete Walks ∙ 400 SF

  31. CIVIL / / ENV NVIRONM NMENT NTAL  Site Base o  Vista Loading Ramps and Platform  Planter Boxes and Stairs  Irving Loading Platforms

  32. CIVIL / / ENV NVIRONM NMENT NTAL  Site Add Alt 1 o  1098 ft 8 in Curb  1208 LF of 10 ft Wide Bike Trail  6 Pedestrian Ramps  Storm Structure

  33. CIVIL / / ENV NVIRONM NMENT NTAL  Site Add Alt 2 o  10100 SF Concrete Sidewalk

  34. QUESTIONS ON CIVIL? Connect with us on:

  35. MECHAN ANICAL AL ADAM AM M MAR ARKSTE TEINER, PE AMI Consulting Engineers, PA

  36. MECHAN ANICAL AL ∙ Installation

  37. MECHAN ANICAL AL ∙ Installation

  38. QUESTIONS ON MECHANICAL? Connect with us on:

  39. ELECTR TRICAL AL ∙ Demolition ∙ Installation SCOTT H T HAEDTK TKE Gausman & Moore

  40. ELECTR TRICAL AL ∙ Demolition

  41. ELECTR TRICAL AL ∙ Installation

  42. ELECTR TRICAL AL ∙ Installation

  43. ELECTR TRICAL AL ∙ Installation

  44. ELECTR TRICAL AL ∙ Installation Details

  45. QUESTIONS ON ELECTRCAL?

  46. QUESTIONS Connect with us on:

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend