DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, - - PowerPoint PPT Presentation

decc cc se seawall pr project ct
SMART_READER_LITE
LIVE PREVIEW

DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, - - PowerPoint PPT Presentation

DECC CC SE SEAWALL PR PROJECT CT Duluth, MN CH CHAD S SCOTT, P PE E CHASE D DEWHIRS RST, P PE AMI Consulting Engineers, PA - Multidiscipline Engineering Firm Marine Civil Structural Mechanical Environmental OWNE NER City


slide-1
SLIDE 1

DECC CC SE SEAWALL PR PROJECT CT

Duluth, MN

CH CHAD S SCOTT, P PE E CHASE D DEWHIRS RST, P PE AMI Consulting Engineers, PA - Multidiscipline Engineering Firm Marine Civil Structural Mechanical Environmental

slide-2
SLIDE 2

OWNE NER

∙ City of Duluth / DECC EN ENGINEER ER: ∙ Civil, Marine, Mechanical, Environmental – AMI ∙ Electrical – Gausman & Moore

slide-3
SLIDE 3

Limits of Construction: Inner End of MN Slip & STA 0+00 to 12+08

slide-4
SLIDE 4

GENERAL C CONSTRUCTION ON OV OVERVI VIEW

  • Install New Epoxy Coated Seawall – 54,810 SF
  • 1,218 LF x 45’ Length SSP
  • C12x30 Double Wale
  • 1-3/4” Tierods
  • Timber Rub Rails
  • Install New Tieback System – 1,140 LF
  • HP10x42 Piling
  • W14x120 Transfer Beam
  • Design Helical Anchors
  • Install New Bollards & Foundations – 8 EA
  • Design & Install Camel System – 1 LS
  • Demo portions of existing seawall
  • Demo Vista Fleet Building
  • Demo Vista Temporary Platform
  • Civil / Mechanical / Electrical Work
  • Alternatives
  • #1 – Curb & Gutter / Bike Path
  • #2 – Remaining Concrete Flatwork & Sidewalks
  • #3 – Mechanical Material Installation
  • #4 – Electrical Installation
  • BIDS D

DUE 11/ 11/8/1 8/17

OWNER ER F FUR URNISHED ED M MATER ERIALS

  • Two Request For Bids Currently Out
  • Structural Steel (Bid Opening 10/31/17)

 Steel Sheet Pile  HP10x42 Steel Piling for Tieback System  W14x120 Steel Transfer Beam for Tieback System  3/8” Bent Steel Cap

  • Application of High-Performance Coating (Bid Opening 11/7/17)

***All Owner furnished materials are based on Neat Line Quantities per the Bid Form. The Contractor is responsible for any additional materials including the installation of a high-performance coating on the steel sheet piling per the technical specifications.

GENERAL CONSTRUCTION OVERVIEW/CONT

  • ADDENNDUMS
  • Bid form to include Electrical & Updated Quantities
  • Documentation further explaining what is included in each bid item
  • Final Construction Documents
  • Historical Documents
slide-5
SLIDE 5

SITE C CONDITI TIONS & & GENERAL AL I INFORMATI TION

  • Scope of Work Limits
  • MN Slip Inner End, and STA 0+00 to 12+08
  • Schedule
  • Substantial Completion by June 1, 2018
  • Final Completion by June 15, 2018
  • Liquidated Damages
  • $1,000 per Day after June 1, 2018
  • Vista Fleet Building
  • Asbestos
  • Underground Storage Tank
  • Electronics
  • Contaminated Soils
  • Tight Work Area
  • May need to shore roadway during Helical

Anchor Installation

  • Work restricted within 30’ of existing retaining

structure  Wood Relieving Platform  One lane closure Harbor Drive

OWNER ER F FUR URNISHED ED M MATER ERIAL S SCHED EDUL ULE

  • City Council Meeting: November 20, 2017
  • Steel Sheet Piling & Cap, H Piling, W Beams
  • FOB DECC: December 18, 2017
  • High-Performance Coating on Steel Sheet Piling
  • FOB DECC: February 2, 2018

SITE C CONDITIONS NS & & GENERAL I INFORMA MATION/CONT NT.

  • Winter Work
  • Staging Areas
  • On-site – DECC
  • Off-site
  • Permits
  • MPCA
  • Building Demo
  • Lane Closures
  • DNR, USACE – Pending
slide-6
SLIDE 6

Limits of Construction: Inner End of MN Slip & STA 0+00 to 12+08 Onsite Staging Area

slide-7
SLIDE 7

MARINE W E WOR ORK

slide-8
SLIDE 8

MN SLIP INNER END

  • Existing Steel Sheet Pile
  • New Steel Sheet Pile Cap
slide-9
SLIDE 9

MN SLIP INNER END – Existing Steel Sheet Pile

slide-10
SLIDE 10

STA 0+00 to 6+02

  • Wakefield Piling
  • Pile Supported Concrete

Dock Cap

slide-11
SLIDE 11

STA 0+00 to 6+02 – Wakefield Piling

slide-12
SLIDE 12

STA 0+00 to 6+02 – Pile Supported with Wakefield Piling

slide-13
SLIDE 13

STA 0+00 to 6+02 – Pile Supported with Wakefield Piling

slide-14
SLIDE 14

STA 6+02 to 9+00 & 9+25 to 9+85

  • Wood Relieving Platform
  • Partial Wall Demolition
slide-15
SLIDE 15

STA 6+02 to 9+00 & 9+25 to 9+85 – Wood Relieving Platform

slide-16
SLIDE 16

STA 6+02 to 9+00 & 9+25 to 9+85 – Wood Relieving Platform

slide-17
SLIDE 17

DOCK W WALL D LL DEMOLI LITION

∙ Demo Temporary Vista Platform ∙ Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

slide-18
SLIDE 18

DOCK W WALL D LL DEMOLI LITION

  • Demo Temporary Vista Platform
  • Remove wood platform, Vertical Piling,

portions of wall, and misc. debris as noted.

slide-19
SLIDE 19

DOCK W WALL D LL DEMOLI LITION

∙ Demo Temporary Vista Platform ∙ Remove wood platform, Vertical Piling, portions of wall, and misc. debris as noted.

slide-20
SLIDE 20

STA 9+00 to 9+25

  • Slip Bridge Abutment
slide-21
SLIDE 21

STA 9+00 to 9+25 – Slip Bridge Abutment

slide-22
SLIDE 22

STA 9+00 to 9+25 – Slip Bridge Abutment

slide-23
SLIDE 23

STA 9+85 to 12+08

  • Crib Dock Wall
slide-24
SLIDE 24

STA 9+85 to 12+08 – Crib Supported Concrete Structure

slide-25
SLIDE 25

STA 9+85 to 12+08 – Crib Supported Concrete Structure

slide-26
SLIDE 26

OTHE HER R R REMA MARK RKS

  • Survey GPS Points for Seawall
  • Example Shown at STA 6+02
  • Key Submittals
  • Driving Logs & Alignment

Checks – SSP (Daily)

  • Driving Logs & Alignment

Checks – H Piles (Daily)

  • Experienced Surveyor
  • Helical Anchor Design
  • Camel System Design
  • Irvin Cannot Leave Slip Prior to

Dock Wall Rehabilitation

  • AMI Full Time Project Management
slide-27
SLIDE 27

Connect with us on:

QUESTIONS ON MARINE?

slide-28
SLIDE 28

EL ELI R RUPNOW, P PE E AMI Consulting Engineers, PA CIVIL / / ENV NVIRONM NMENT NTAL

  • Demolition
  • Grading
  • Concrete Flatwork
  • Concrete Sidewalks
  • Bike Path
slide-29
SLIDE 29

CIVIL / / ENV NVIRONM NMENT NTAL

  • Demolition
  • Base

 Vista Fleet Building  Irving Loading Platforms  Concrete flatwork, bollards, signage, and

  • ther misc. Items
slide-30
SLIDE 30

CIVIL / / ENV NVIRONM NMENT NTAL

  • Demolition
  • Add Alt 1

 1167 LF of Curb and Gutter  1200 SY of Concrete Pavement  Remove Storm Structure and Adjust Frame and Casting

  • Add Alt 2

∙ Concrete Walks ∙ 400 SF

slide-31
SLIDE 31

CIVIL / / ENV NVIRONM NMENT NTAL

  • Site
  • Base

 Vista Loading Ramps and Platform  Planter Boxes and Stairs  Irving Loading Platforms

slide-32
SLIDE 32

CIVIL / / ENV NVIRONM NMENT NTAL

  • Site
  • Add Alt 1

 1098 ft 8 in Curb  1208 LF of 10 ft Wide Bike Trail  6 Pedestrian Ramps  Storm Structure

slide-33
SLIDE 33

CIVIL / / ENV NVIRONM NMENT NTAL

  • Site
  • Add Alt 2

 10100 SF Concrete Sidewalk

slide-34
SLIDE 34

Connect with us on:

QUESTIONS ON CIVIL?

slide-35
SLIDE 35

ADAM AM M MAR ARKSTE TEINER, PE AMI Consulting Engineers, PA MECHAN ANICAL AL

slide-36
SLIDE 36

MECHAN ANICAL AL

∙ Installation

slide-37
SLIDE 37

MECHAN ANICAL AL

∙ Installation

slide-38
SLIDE 38

Connect with us on:

QUESTIONS ON MECHANICAL?

slide-39
SLIDE 39

SCOTT H T HAEDTK TKE Gausman & Moore ELECTR TRICAL AL

∙ Demolition ∙ Installation

slide-40
SLIDE 40

ELECTR TRICAL AL

∙ Demolition

slide-41
SLIDE 41

ELECTR TRICAL AL

∙ Installation

slide-42
SLIDE 42

ELECTR TRICAL AL

∙ Installation

slide-43
SLIDE 43

ELECTR TRICAL AL

∙ Installation

slide-44
SLIDE 44

ELECTR TRICAL AL

∙ Installation Details

slide-45
SLIDE 45

QUESTIONS ON ELECTRCAL?

slide-46
SLIDE 46

Connect with us on:

QUESTIONS