customers and networks
play

Customers and Networks: Energy Reforms in Great Britain Richard - PowerPoint PPT Presentation

Customers and Networks: Energy Reforms in Great Britain Richard Green (from Sept 2011: Imperial College London) UK Electricity Prices p/kWh (2005) Source: DECC UK Electricity Prices p/kWh (2005) Source: DECC UK Electricity Prices p/kWh


  1. Customers and Networks: Energy Reforms in Great Britain Richard Green (from Sept 2011: Imperial College London)

  2. UK Electricity Prices p/kWh (2005) Source: DECC

  3. UK Electricity Prices p/kWh (2005) Source: DECC

  4. UK Electricity Prices p/kWh (2005) Source: DECC

  5. Where are we coming from?

  6. Not the USA! • 1983: BT regulation should avoid the failings of US-style regulation – Cost-plus characteristics – Averch Johnson Effect • Fix prices, not profits

  7. RPI – X for electricity networks • 5-year price control periods – Occasional “reopeners” for major projects • Distribution revenues linked to forecast customer numbers and units distributed • Transmission revenues linked to forecast peak demand

  8. Regulated prices, 1990=100 100 80 Transmission (NGC) 60 Distribution (England and Wales average) 40 20 0 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010

  9. Electricity Distribution Investment Forecasts £ million Actual 1600 Investment Company 1500 Forecast 1400 Regulator's Allowance 1300 Line 4 1200 Line 5 1100 1000 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4 Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

  10. Electricity Distribution Investment Forecasts £ million Actual 1600 Investment Company 1500 Forecast 1400 Regulator's Allowance 1300 Line 4 1200 Line 5 1100 1000 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4 Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

  11. Electricity Distribution Investment Forecasts £ million Actual 1600 Investment Company 1500 Forecast 1400 Regulator's Allowance 1300 Line 4 1200 Line 5 1100 1000 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4 Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

  12. Electricity Distribution Investment Forecasts £ million Actual 1600 Investment Company 1500 Forecast 1400 Regulator's Allowance 1300 Line 4 1200 Line 5 1100 1000 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4 Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

  13. Electricity Distribution Investment Forecasts £ million Actual 1600 Investment Company 1500 Forecast 1400 Regulator's Allowance 1300 Line 4 1200 Line 5 1100 1000 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4 Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

  14. Electricity Distribution Investment Forecasts £ million Actual 1600 Investment Company 1500 Forecast 1400 Regulator's Allowance 1300 Line 4 1200 Line 5 1100 1000 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4 Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

  15. A menu of tariffs Reward (£m) 60 Option A 40 Option B 20 0 Cost 300 350 400 450 500 550 600 (£m) -20 -40 Incentive scheme for National Grid System Operator Costs, c.2002 (?)

  16. Information Quality Incentive Permitted Company Revenue request relative to 120 regulator’s forecast: 115 c4 100% 110 110% 120% 105 100 95 100 105 110 115 120 Actual Spend

  17. Information Quality Incentive Permitted Company Revenue request relative to 120 regulator’s forecast: c4 115 100% 110% 110 120% c5 105 (illustrative figures) 100 95 100 105 110 115 120 Actual Spend

  18. Information Quality Incentive Permitted Company Revenue request relative to 120 regulator’s forecast: c4 115 100% 110% 110 120% c5 105 (illustrative figures) 100 95 100 105 110 115 120 Actual Spend

  19. Information Quality Incentive Permitted Company Revenue request relative to 120 regulator’s forecast: c4 115 100% 110% 110 120% c5 105 (illustrative figures) 100 95 100 105 110 115 120 Actual Spend

  20. Information Quality Incentive Permitted Company Revenue request relative to 120.0 regulator’s forecast: c4 115.0 100% 110% 110.0 120% c5 105.0 (illustrative figures) 100.0 95 100 105 110 115 120 Actual Spend

  21. Information Quality Incentive Permitted Company Revenue request relative to 120.0 regulator’s forecast: c4 115.0 100% 110% 110.0 120% c5 105.0 (illustrative figures) 100.0 95 100 105 110 115 120 Actual Spend

  22. Information Quality Incentive Permitted Company Revenue request relative to 120.0 regulator’s forecast: c4 115.0 100% 110% 110.0 120% c5 105.0 (actual figures) 100.0 95 100 105 110 115 120 Actual Spend

  23. Future challenges • Ageing infrastructure • New generation sites – Wind in Scotland and offshore – Distributed generation • The opportunity for a smarter grid • Investment need: £32 bn by 2020 – Current RAV £43 bn (all energy networks)

  24. The Response: RIIO

  25. The Response: RIIO Revenue = Incentives + Innovation + Outputs

  26. RIIO building blocks • 8-year price control periods • Companies to deliver specified outputs • Outputs can be adjusted mid-period • No difference between Capex and Opex – Fixed proportion of total spend added to Regulatory Asset Value • Cost of capital adjusted each year

  27. Output-led • Primary outputs: 1. Customer satisfaction 2. Safety 3. Reliability and availability 4. Conditions for connection 5. Environmental impact 6. Social obligations – Secondary deliverables that provide options for the next control period can be added

  28. Output criteria • Material • Controllable • Measurable • Comparable • Applicable • Compatible with promoting competition • Legally compliant

  29. Possible output measures Distribution Transmission Customer satisfaction 1. Broad measures of satisfaction reflecting consumer and network user experience 2. Qualitative survey evidence Safety 1. Legal compliance with minimum requirements 2. Additional initiatives if in public interest Reliability and availability 1. Customer 1. Energy Not Supplied interruptions 2. Constraint measure 2. Customer mins lost / Energy Not Supplied Conditions for Time to connect Time to connect connections 1. Generation 1. Generation 2. Demand 2. Demand

  30. Possible output measures Distribution Transmission Environmental Impact 1. Carbon footprint of 1. Carbon footprint of network including network including losses losses 2. Proportion of new low 2. Proportion of new low carbon generation carbon generation 3. Other emissions 3. Other emissions 4. Visual impacts 4. Visual impacts 5. Role in consumer energy efficiency Social Obligations 1. Targets for vulnerable customers such as Public Service Obligations

  31. Well-justified business plans • Companies to develop plans – Focus on outputs – Consider the longer term – Consider alternative options – Link costs to outputs • Ofgem will scrutinise or fast-track

  32. Engaging stakeholders • Civil Aviation Authority encouraged “constructive engagement” at airports • Ofgem wants companies and itself to engage with stakeholders • Stakeholders have the right to ask for a Competition Commission Review – If they have engaged and can pay the costs

  33. Incentives for companies • Information Quality Incentive for good forecasts • Incentives & penalties on deliverables • Gain-sharing incentive for efficiency • Possible uncertainty mechanism for large unanticipated changes

  34. Evolution or Revolution?

  35. Moving the wind to the customers

  36. Where should I build my power station? Wind resource map Source: GL Garrad Hassan

  37. Where should I build my power station? Opportunities to connect power stations Source: National Grid Wind resource map Source: GL Garrad Hassan

  38. Transmission arrangements • Charges based on long-run incremental cost, £/kW of generation capacity • Various tries at charging for losses failed • New plant had to join the GB queue: “invest then connect”

  39. Transmission arrangements • Charges based on long-run incremental cost, £/kW of generation capacity • Various tries at charging for losses failed • New plant had to join the GB queue: “invest then connect” • Policy is now “connect and manage”

  40. Transmission arrangements • Charges based on long-run incremental cost, £/kW of generation capacity • Various tries at charging for losses failed • New plant had to join the GB queue: “invest then connect” • Policy is now “connect and manage” (and socialise)

  41. Who should pay for congestion? • New generators in a constrained area? – Reduces profitability of entrants for a given market price and level of renewable support

  42. Who should pay for congestion? • New generators in a constrained area? – Reduces profitability of entrants for a given market price and level of renewable support • All the generators in a constrained area? – Better for entrants (see above); reduces incentive to avoid poor areas

  43. Who should pay for congestion? • New generators in a constrained area? – Reduces profitability of entrants for a given market price and level of renewable support • All the generators in a constrained area? – Better for entrants (see above); reduces incentive to avoid poor areas • All generators

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend