Customers and Networks: Energy Reforms in Great Britain Richard - - PowerPoint PPT Presentation

customers and networks
SMART_READER_LITE
LIVE PREVIEW

Customers and Networks: Energy Reforms in Great Britain Richard - - PowerPoint PPT Presentation

Customers and Networks: Energy Reforms in Great Britain Richard Green (from Sept 2011: Imperial College London) UK Electricity Prices p/kWh (2005) Source: DECC UK Electricity Prices p/kWh (2005) Source: DECC UK Electricity Prices p/kWh


slide-1
SLIDE 1

Customers and Networks:

Energy Reforms in Great Britain

Richard Green (from Sept 2011: Imperial College London)

slide-2
SLIDE 2

UK Electricity Prices

p/kWh (2005) Source: DECC

slide-3
SLIDE 3

UK Electricity Prices

p/kWh (2005) Source: DECC

slide-4
SLIDE 4

UK Electricity Prices

p/kWh (2005) Source: DECC

slide-5
SLIDE 5

Where are we coming from?

slide-6
SLIDE 6

Not the USA!

  • 1983: BT regulation should avoid the

failings of US-style regulation

– Cost-plus characteristics – Averch Johnson Effect

  • Fix prices, not profits
slide-7
SLIDE 7

RPI – X for electricity networks

  • 5-year price control periods

– Occasional “reopeners” for major projects

  • Distribution revenues linked to forecast

customer numbers and units distributed

  • Transmission revenues linked to forecast

peak demand

slide-8
SLIDE 8

Regulated prices, 1990=100

20 40 60 80 100 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010

Distribution (England and Wales average) Transmission (NGC)

slide-9
SLIDE 9

Electricity Distribution Investment

Forecasts

1000 1100 1200 1300 1400 1500 1600 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4

Actual Investment Company Forecast Regulator's Allowance Line 4 Line 5

£ million Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

slide-10
SLIDE 10

Electricity Distribution Investment

Forecasts

1000 1100 1200 1300 1400 1500 1600 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4

Actual Investment Company Forecast Regulator's Allowance Line 4 Line 5

£ million Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

slide-11
SLIDE 11

Electricity Distribution Investment

Forecasts

1000 1100 1200 1300 1400 1500 1600 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4

Actual Investment Company Forecast Regulator's Allowance Line 4 Line 5

£ million Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

slide-12
SLIDE 12

Electricity Distribution Investment

Forecasts

1000 1100 1200 1300 1400 1500 1600 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4

Actual Investment Company Forecast Regulator's Allowance Line 4 Line 5

£ million Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

slide-13
SLIDE 13

Electricity Distribution Investment

Forecasts

1000 1100 1200 1300 1400 1500 1600 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4

Actual Investment Company Forecast Regulator's Allowance Line 4 Line 5

£ million Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

slide-14
SLIDE 14

Electricity Distribution Investment

Forecasts

1000 1100 1200 1300 1400 1500 1600 89/90 91/2 93/4 95/6 97/8 99/00 '01/2 '03/4

Actual Investment Company Forecast Regulator's Allowance Line 4 Line 5

£ million Source: Offer, Distribution Price Control, May Consultation & Dec Proposals, 1999

slide-15
SLIDE 15

A menu of tariffs

  • 40
  • 20

20 40 60 300 350 400 450 500 550 600

Option A Option B

Reward (£m) Cost (£m)

Incentive scheme for National Grid System Operator Costs, c.2002 (?)

slide-16
SLIDE 16

Information Quality Incentive

100 105 110 115 120 95 100 105 110 115 120 Permitted Revenue Actual Spend c4 100% 110% 120% Company request relative to regulator’s forecast:

slide-17
SLIDE 17

Information Quality Incentive

100 105 110 115 120 95 100 105 110 115 120 Permitted Revenue Actual Spend c4 100% 110% 120% c5 Company request relative to regulator’s forecast: (illustrative figures)

slide-18
SLIDE 18

Information Quality Incentive

100 105 110 115 120 95 100 105 110 115 120 Permitted Revenue Actual Spend c4 100% 110% 120% c5 Company request relative to regulator’s forecast: (illustrative figures)

slide-19
SLIDE 19

Information Quality Incentive

100 105 110 115 120 95 100 105 110 115 120 Permitted Revenue Actual Spend c4 100% 110% 120% c5 Company request relative to regulator’s forecast: (illustrative figures)

slide-20
SLIDE 20

Information Quality Incentive

100.0 105.0 110.0 115.0 120.0 95 100 105 110 115 120 Permitted Revenue Actual Spend c4 100% 110% 120% c5 Company request relative to regulator’s forecast: (illustrative figures)

slide-21
SLIDE 21

Information Quality Incentive

100.0 105.0 110.0 115.0 120.0 95 100 105 110 115 120 Permitted Revenue Actual Spend c4 100% 110% 120% c5 Company request relative to regulator’s forecast: (illustrative figures)

slide-22
SLIDE 22

Information Quality Incentive

100.0 105.0 110.0 115.0 120.0 95 100 105 110 115 120 Permitted Revenue Actual Spend c4 100% 110% 120% c5 Company request relative to regulator’s forecast: (actual figures)

slide-23
SLIDE 23

Future challenges

  • Ageing infrastructure
  • New generation sites

– Wind in Scotland and offshore – Distributed generation

  • The opportunity for a smarter grid
  • Investment need: £32 bn by 2020

– Current RAV £43 bn (all energy networks)

slide-24
SLIDE 24

The Response: RIIO

slide-25
SLIDE 25

The Response: RIIO

Revenue = Incentives + Innovation + Outputs

slide-26
SLIDE 26

RIIO building blocks

  • 8-year price control periods
  • Companies to deliver specified outputs
  • Outputs can be adjusted mid-period
  • No difference between Capex and Opex

– Fixed proportion of total spend added to Regulatory Asset Value

  • Cost of capital adjusted each year
slide-27
SLIDE 27

Output-led

  • Primary outputs:
  • 1. Customer satisfaction
  • 2. Safety
  • 3. Reliability and availability
  • 4. Conditions for connection
  • 5. Environmental impact
  • 6. Social obligations

– Secondary deliverables that provide options for the next control period can be added

slide-28
SLIDE 28

Output criteria

  • Material
  • Controllable
  • Measurable
  • Comparable
  • Applicable
  • Compatible with promoting competition
  • Legally compliant
slide-29
SLIDE 29

Possible output measures

Distribution Transmission Customer satisfaction

  • 1. Broad measures of satisfaction reflecting

consumer and network user experience

  • 2. Qualitative survey evidence

Safety

  • 1. Legal compliance with minimum requirements
  • 2. Additional initiatives if in public interest

Reliability and availability 1. Customer interruptions

  • 2. Customer mins lost /

Energy Not Supplied

  • 1. Energy Not Supplied
  • 2. Constraint measure

Conditions for connections Time to connect

  • 1. Generation
  • 2. Demand

Time to connect

  • 1. Generation
  • 2. Demand
slide-30
SLIDE 30

Possible output measures

Distribution Transmission Environmental Impact

  • 1. Carbon footprint of

network including losses

  • 2. Proportion of new low

carbon generation

  • 3. Other emissions
  • 4. Visual impacts
  • 5. Role in consumer

energy efficiency

  • 1. Carbon footprint of

network including losses

  • 2. Proportion of new low

carbon generation

  • 3. Other emissions
  • 4. Visual impacts

Social Obligations

  • 1. Targets for vulnerable customers such as Public

Service Obligations

slide-31
SLIDE 31

Well-justified business plans

  • Companies to develop plans

– Focus on outputs – Consider the longer term – Consider alternative options – Link costs to outputs

  • Ofgem will scrutinise or fast-track
slide-32
SLIDE 32

Engaging stakeholders

  • Civil Aviation Authority encouraged

“constructive engagement” at airports

  • Ofgem wants companies and itself to

engage with stakeholders

  • Stakeholders have the right to ask for a

Competition Commission Review

– If they have engaged and can pay the costs

slide-33
SLIDE 33

Incentives for companies

  • Information Quality Incentive for good

forecasts

  • Incentives & penalties on deliverables
  • Gain-sharing incentive for efficiency
  • Possible uncertainty mechanism for large

unanticipated changes

slide-34
SLIDE 34

Evolution or Revolution?

slide-35
SLIDE 35

Moving the wind to the customers

slide-36
SLIDE 36

Where should I build my power station?

Wind resource map Source: GL Garrad Hassan

slide-37
SLIDE 37

Where should I build my power station?

Wind resource map Source: GL Garrad Hassan Opportunities to connect power stations Source: National Grid

slide-38
SLIDE 38

Transmission arrangements

  • Charges based on long-run incremental

cost, £/kW of generation capacity

  • Various tries at charging for losses failed
  • New plant had to join the GB queue:

“invest then connect”

slide-39
SLIDE 39

Transmission arrangements

  • Charges based on long-run incremental

cost, £/kW of generation capacity

  • Various tries at charging for losses failed
  • New plant had to join the GB queue:

“invest then connect”

  • Policy is now “connect and manage”
slide-40
SLIDE 40

Transmission arrangements

  • Charges based on long-run incremental

cost, £/kW of generation capacity

  • Various tries at charging for losses failed
  • New plant had to join the GB queue:

“invest then connect”

  • Policy is now “connect and manage”

(and socialise)

slide-41
SLIDE 41

Who should pay for congestion?

  • New generators in a constrained area?

– Reduces profitability of entrants for a given market price and level of renewable support

slide-42
SLIDE 42

Who should pay for congestion?

  • New generators in a constrained area?

– Reduces profitability of entrants for a given market price and level of renewable support

  • All the generators in a constrained area?

– Better for entrants (see above); reduces incentive to avoid poor areas

slide-43
SLIDE 43

Who should pay for congestion?

  • New generators in a constrained area?

– Reduces profitability of entrants for a given market price and level of renewable support

  • All the generators in a constrained area?

– Better for entrants (see above); reduces incentive to avoid poor areas

  • All generators
slide-44
SLIDE 44

Who should pay for congestion?

  • New generators in a constrained area?

– Reduces profitability of entrants for a given market price and level of renewable support

  • All the generators in a constrained area?

– Better for entrants (see above); reduces incentive to avoid poor areas

  • All generators customers
slide-45
SLIDE 45

Project TransmiT

  • Ofgem review of transmission charging etc.
  • Facilitate timely move to low carbon

electricity with value for money

  • Connection policy – should users commit?

Should the TSO compensate for delay?

  • Charging – should this be on energy or

capacity? Should there be more geographical differentiation?

slide-46
SLIDE 46

Academic Reports

  • Cambridge, US, Strathclyde/Birmingham
  • Two reports favoured nodal pricing
  • One noted its advantage of cost reflectivity

but its lack of stakeholder support

– Energy-based charges are good for stations with low load factors – EMR allows for compensating changes in support to low-carbon generators

slide-47
SLIDE 47

Ofgem’s response

slide-48
SLIDE 48

Retail market competition

slide-49
SLIDE 49

Britain’s electricity markets

E Midlands Northern Yorkshire Eastern London Seeboard Southern SWEB Swalec Midlands Manweb Norweb Scottish Power Hydro- Electric RWE npower RWE npower RWE npower Scottish Power Scottish Power Scottish and Southern Scottish and Southern E.On UK Scottish and Southern E.On UK E.On UK EdF Energy EdF Energy EdF Energy

slide-50
SLIDE 50

Retail Competition

  • Large customers (1 MW) from 1990
  • Medium customers (100 kW) from 1994
  • “1998” happened in phases in 1998-99

– Electricity regional incumbents could not compete until their own market was open

  • Price caps set for 1998-2000 and 2000-02
  • Price regulation lifted in 2002
slide-51
SLIDE 51

Incumbent market shares

10 20 30 40 50 60 70 80

Q1 2001 Q1 2003 Q1 2005 Q1 2007 Q1 2009 Q1 2011

Standard Credit Prepayment Direct Debit %

Source: DUKES

slide-52
SLIDE 52

Domestic energy market shares

August 2010, Great Britain

British Gas Other Big Six Company Local Electricity Incumbent Dual Fuel Customers Buying Gas Separately Not on Gas Grid Buying Electricity Separately Single Fuel Customers Millions of customers

Source: Ofgem

slide-53
SLIDE 53

Dual Fuel bills

National Averages Source: Ofgem

slide-54
SLIDE 54

The regulator’s concerns

  • Non-switching customers get a bad deal

– Action to reduce price differentials

slide-55
SLIDE 55

The cost of not switching

Differences between areas in which each company is an incumbent and those where it is an entrant, annual bill for credit electricity customers, corrected for network charges

slide-56
SLIDE 56

The regulator’s concerns

  • Non-switching customers get a bad deal

– Action to reduce price differentials

  • nb there are two ways to reduce (A – B) …
slide-57
SLIDE 57

Dual Fuel bills

National Averages Source: Ofgem

slide-58
SLIDE 58

The cost of not switching

Differences between areas in which each company is an incumbent and those where it is an entrant, annual bill for credit electricity customers, corrected for network charges

slide-59
SLIDE 59

The cost of not switching

Differences between areas in which each company is an incumbent and those where it is an entrant, annual bill for credit electricity customers, corrected for network charges

slide-60
SLIDE 60

The regulator’s concerns

  • Non-switching customers get a bad deal

– Action to reduce price differentials

  • nb there are two ways to reduce (A – B) …
  • Vertical integration reduces wholesale

market volume and transparency

– Proposing Mandatory Market Making and Mandatory Auctions by incumbents

slide-61
SLIDE 61

The elephant in the room…

slide-62
SLIDE 62

Energy efficiency policies

  • Carbon Emissions Reduction Target

– Obligation on energy suppliers, now targeted

  • n insulation and low-income customers
  • Community Energy Saving Programme

– Energy saving measures in targeted areas installed on a street-by-street basis

  • Warm Front grants from DECC

– Insulation for low-income consumers

slide-63
SLIDE 63

Price predictions - DECC

“Time-weighted consumer electricity prices” Sources: DECC, EMR Consultation & “Estimated Impacts”, 2010

Baseline Preferred policy package

* Counter-factual without climate policy (?)

slide-64
SLIDE 64

Impact on bills by income

Household receives insulation Household receives no insulation Average

Source: DECC, 2010 “Estimated Impacts

  • f Energy and Climate Change Policies”
slide-65
SLIDE 65

Impact on bills by income

Household receives insulation Household receives no insulation Average

Source: DECC, 2010 “Estimated Impacts

  • f Energy and Climate Change Policies”
slide-66
SLIDE 66

Impact on bills by income

Household receives insulation Household receives no insulation Average

Source: DECC, 2010 “Estimated Impacts

  • f Energy and Climate Change Policies”
slide-67
SLIDE 67

The Green Deal

  • Investments in energy efficiency at no

upfront cost to the customer

  • Expected savings should exceed cost
  • Repaid through future energy bills
  • Energy Company Obligation

– Additional support for consumers with low incomes or hard-to-treat homes

slide-68
SLIDE 68