Cryogenic Instrumentation & Slow Controls (CISC)
Overview & Status
Sowjanya Gollapinni (UTK)
CISC Scope Review Meeting CERN, June 19, 2019
Cryogenic Instrumentation & Slow Controls (CISC) Overview & - - PowerPoint PPT Presentation
Cryogenic Instrumentation & Slow Controls (CISC) Overview & Status Sowjanya Gollapinni (UTK) CISC Scope Review Meeting CERN, June 19, 2019 CISC Primary goals DUNE CPV and other physics goals require at least a decade of running the
Overview & Status
CISC Scope Review Meeting CERN, June 19, 2019
FD during which time we don’t have access to the interior of the cryostat
and reported quickly and reliably during this time
primarily through the maintenance of high detector live time
for LAr quality and behavior (can be used to constrain detection efficiency and fiducial volume), and a control system for many of the detector components
2
3
(from Glenn; format modified)
(Single-Phase)
validation and testing at ProtoDUNE-I (ongoing) and ProtoDUNE-II (anticipated)
LBNF scope
4
Pressure Meters (GAr; LBNF)
(D. Montanari for LBNF)
5
Spain (2), UK (2) and USA (15)
6
Spain (2), UK (2) and USA (15)
7
flow simulations needed for the consortium for ProtoDUNE and FD, for both SP and DP
better integrate into CISC activities
confirmations/verifications on simulations
CFD Simulations
Note: DP not as advanced as SP — final configuration and some design aspects need more work
8
Pressure Meters (GAr; LBNF) Pressure Meters (GAr; LBNF)
clashes and other installation interfaces
locations) for DP which needs to be confirmed later once more information is available.
9
meeting all deadlines!
currently under LBNC review, submitted on May 3
documents going through final review TDR draft SP DP 1st draft 30-Nov-18 5-April-19 2nd draft 11-Jan-19 1-May-19 LBNC-1 25-Jan-19 3-May-19 LBNC-review-1 28-Feb-19 N/A 3rd draft 15-April-19 N/A Collaboration Internal review 3-May-19 3-May-19 LBNC-2 3-May-19 TBD LBNC-review-2 TBD TBD
10
Note: The CISC scope and plans presented today follow what we have in the TDR currently plus some additional studies to further motivate the systems
lifetime of the experiment but would be great if they did!
this)
11
distribution:
ProtoDUNE-SP
12
ProtoDUNE-SP
Includes statistical errors (see backup)
13
PrM PrM
Use opposite set of human access ports
string with monitors at different heights enables addressing any stratification issues
ports are the current option
values, improved light source etc. — The PD-SP-II and PD-DP-II runs post-LS2 will provide opportunities to test improved designs.
14
Detailed talk by Jianming Bian in the dedicated Purity Monitors talk in the afternoon
measurements
precision
15
(Slide from A. Cervera)
16
(From Anselmo)
ProtoDUNE-SP Detector
17
Static T-gradient system Several calibration methods being deployed (laboratory Vs pump on/off) 2-3 mK relative precision achieved Comparison to CFD has reasonable agreement, more work ongoing to better understand boundary conditions e.g. pressure, heat load etc.
18
Update with most up-to- date plots from ACV
(From Anselmo)
19
Maximum sensor configuration, probably not all needed (see alternative configuration in backup)
To-do: update with the less-busy version from Anselmo
20
Distribution yet to be finalized, expect might need fewer thermometers in the end
FD-DP FD-SP
*Dynamic T-gradient thermometers not shown in DP — yet to be understood
To-do: for the top one, update with the less-busy version from Anselmo
DP as it effects LEM gain calibration — Static T-gradient profilers in LAr can be used for this
, the region above the CRP (about 40 cm) will be instrumented to understand the behavior of mechanical structure — 20 arrays with 8 sensors/array (with increasing pitch)
in GAr is rapid w.r.t. height so 0.1K relative precision is sufficient
21
ProtoDUNE-DP
PD-DP
T-Gradient profilers deployed in LAr in PD-DP, so needs to be validated in post-LS2 PD-DP-II run
22
23
Detailed talk by A. Cervera and J. Maricic
Two types of cameras
detector components
24
ProtoDUNE-SP
current run
PD-SP camera design from Bo ProtoDUNE-DP
aspect, depends on replaceability, will need R&D
25
Acrylic Vacuum tight
PD-SP inspection (warm) camera in acrylic tube before installation
26
One key specification Full Coverage with 12 cold cameras in the FD
(8 in corners 4 in long edge centers)
27
Detailed talk by G. Horton-Smith in the dedicated Cameras talk in the afternoon
therefore the LEM gain calibration
this provides a better picture of temperature gradients and CFD simulations
0.1% needed
can be used
ProtoDUNE SP/DP: two pressure sensors and a pressure switch are installed in a dedicated flange (see the image on the right)
28
ProtoDUNE
flanges with pressure meters on opposite sides of the cryostat
pressure sensors — provides redundancy, independent measurements and cross checks.
29
(The level meters are complemented by vertical thermometer arrays and cameras)
30
Level Meter Type (Scope) Precision Primary Purpose Comment Differential Level Meters (LBNF) 14 mm During LAr filling PD-SP/DP use the same design which will be used in the FD Capacitive Level Meters (CISC) < 5 mm Finer tuning of LAr; safety interlocking; cross-check with LBNF level meters High-Precision Capacitive Level Meters (CRP) < 1 mm For sub-mm control of LAr surface Level meters attached to the inner membrane of the cryostat High-Precision Capacitive Level Meters (CRP) < 1 mm For controlling CRP alignment with liquid
31
Level Meter Type (Scope) Precision Primary Purpose Comment Differential Level Meters (LBNF) 14 mm During LAr filling PD-SP/DP use the same design which will be used in the FD Capacitive Level Meters (CISC) < 5 mm Finer tuning of LAr; safety interlocking; cross-check with LBNF level meters High-Precision Capacitive Level Meters (CRP) < 1 mm For sub-mm control of LAr surface Level meters attached to the inner membrane of the cryostat High-Precision Capacitive Level Meters (CRP) < 1 mm For controlling CRP alignment with liquid
Level meters cost is very minimal: M&S <$1500/unit
(based on PD-DP)
(from ProtoDUNE to DUNE)
Sub-system
Quantity (ProtoDUNE-SP) Quantity (ProtoDUNE-DP)
Quantity (FD-SP) Quantity (FD-DP) Baseline design Purity Monitors 3 (cryostat) 0 (inline) 2 (cryostat) 0 (inline) 6 (cryostat) 2 (inline) 6 (cryostat) 2 (inline) PD-SP Static Profilers 2 6 6 PD-SP Dynamic Profilers 1 2 (ideal) 1 (minimal) 2 (ideal) 1 (minimal) PD-SP Individual Sensors 38 Ask Filippo? 175 (max.) 127 (min.) 148 (max.) ?? (min.) PD-SP GAr Temp. Arrays Ask Filippo? 20 arrays (8 sensors/ array) PD-DP Capacitive Level Meters 1 (1m long; commercial) 1 (4 m long; custom built) 2 2 PD-DP Pressure Meters 3 3 6 6 PD-SP & PD-DP Cold Cameras 8 (2 designs) 11 (1 design) 12 12 PD-SP & PD-DP Warm Cameras 3 (1 design) 3 3 PD-SP & PD-DP
32
Sub-system PD-SP-I PD-DP-I PD-SP-II PD-DP-II Purity Monitors
✔ ✔ * ✔
Static Profilers
✔ ✔ * ✔
Dynamic Profilers
✔ ✔ * ✔
GAr Temp. arrays
✔ ✔
Level Meters
✔ ✔
Pressure Meters
✔ ✔
Gas analyzers
✔ ✔
Cameras
✔ ✔ ✔ * ✔ *
33
* = improved designs
34
35
36
37
Add table from TDR and highlight top-level requirements
(From Anselmo) 38
Conceptual design stage — under development
39
Example shown: Static T-gradient Thermometer system
(From Jelena) 40
41
42
Add table from TDR and highlight top-level requirements
Only showing SP here. For DP , we have CRP and DP-PDS in addition to what is listed here
43
(only listing Medium-level risks post-mitigation)
44
Key CISC Milestones (SP)
45
Key CISC Milestones (DP)
46
case of questions
47