Cryogenic cavern in Asian site Conceptual design of the cryogenic - - PowerPoint PPT Presentation

cryogenic cavern in asian site
SMART_READER_LITE
LIVE PREVIEW

Cryogenic cavern in Asian site Conceptual design of the cryogenic - - PowerPoint PPT Presentation

Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system Storage of helium inventory Cooling water for cryogenic system


slide-1
SLIDE 1

Cryogenic cavern in Asian site

  • Conceptual design of the cryogenic system
  • Layout of the cryogenic plant for site A & B
  • New layout of the cryogenic system
  • Storage of helium inventory
  • Cooling water for cryogenic system
  • Summary & Future Plan

KEK

  • K. Hosoyama
slide-2
SLIDE 2

Conceptual Design of Cryogenic System 1

1 ~ 2 km

Cooling Tower

2K

Cooling Water Piping Cooling Tower 2 K and 4 K Ref. Cold Box ~ 5 MW x 2 units Helium Gas Compressor

4 K Ref. Cold Box Helium Gas Compressor SC Cavities 2 K Ref. Cold Box

4K Multi-transfer Line Helium Gas Piping

There are many option of layout of main components:

  • 4K cold boxes will be installed in the large caverns at the end of access.
  • Compressor units will be installed in underground tunnel.

2K Multi-transfer Line SC Cavities in Main Tunnel Helium Gas Compressor

underground ? surface ?

Access Tunnel

slide-3
SLIDE 3

Conceptual Design of Cryogenic System 2

5 km 4 K He Ref. Cryomodule ~ 5 MW x 2 He Compressor x 2 units 2K He Ref. x 2 units Access Tunnel Cooling Tower He Compressor x 2 units ~ 5 MW x 2 2K He Ref. x 2 units Cooling Tower Access Tunnel Cryomodule Cryomodule Cryomodule

  • 4K cold boxes will be installed in the large caverns at the end of access.
  • Two 2K cold boxes must be installed in the caverns at 5 km intervals

and each 2K cold box supports cooling of ~2.5 km long cryogenic unit.

  • Long multi-transfer line must be installed in the main tunnel

to connect 2K and 4K refrigerators.

  • We must carry in the 2K cold box and distribution box through main tunnel.

5 km 2.5 km 2.5 km Multi-transfer Line

slide-4
SLIDE 4

Layout of Cryogenic Plants for Mountain Site-B

Zone 1 5.4 km Zone 2 4.7 km Zone 3 5.1 km Zone 4 5.8 km Zone 5 4.8 km Zone 6 3.8 km 2.5 km 2.5 km 5 km 5 km 5 km 5 km 2.5 km 2.5 km 1.3 km 1.1 km 2.2 km 2 km 2.6 km 1.9 km 2K Ref.#6 2K Ref.#5 2K Ref.#4 2K Ref.#3 2K Ref.#2 2K Ref.#1 He Compressor

  • 2K cold boxes and distribution boxes will be installed in the cavern in the main tunnel
  • 4 K cold boxes & compressor units will be installed at the end of access tunnel

Comments : 1) Long multi-transfer line must be installed in the main tunnel 2) End of access tunnel a large space will be prepared for assembling a TBM. This space can be used for a 4.4 K cold box. 3) Compressor unit will be installed far away from main tunnel in the cavern near by access tunnel. 4) Helium will be recovered as liquid in the Dewar installed near by the 4 K refrigerator cold box.

2K Ref. cold box ( + cold compressor) 4 K Ref. cold box Access Tunnel

slide-5
SLIDE 5

Layout of Cryogenic Plants for Mountain Site-A

Zone 1 3.8 km Zone 2 3.5 km Zone 3 5.0km Zone 7 4.2 km Zone 8 4.1 km Zone 9 4.1 km 2.5 km 2.5 km 5 km 5 km 5 km 5 km 2.5 km 2.5 km 1.6 km 0.2 km 1.3 km 0.2km 2K Ref.#6 2K Ref.#5 2K Ref.#4 2K Ref.#3 2K Ref.#2 2K Ref.#1 He compressor unit 2K Ref. Cold box ( + cold compressor) 4.4 K Ref. cold box 0.7 km Zone 6 2.0 km Zone 5 1.9 km Zone 4 2.0 km 0.2km Shaft Access Tunnel

H = 50m H = 30 m H = 40m

  • 2K cold boxes and distribution boxes will be installed in the cavern in the main tunnel
  • 4 K cold boxes & compressor units will be installed at the end of access tunnel

Comments : 1) Long multi-transfer line must be installed in the main tunnel 2) End of access tunnel a large space will be prepared for assembling a TBM. This space can be used for a 4.4 K cold box. 3) Compressor unit will be installed far away from main tunnel in the cavern near by access tunnel. 4) Helium will be recovered as liquid in the Dewar installed near by the 4 K refrigerator cold box.

slide-6
SLIDE 6

Cryogenic Cavern (old version)

18kW Helium ref. cold box / CERN LHC Sub tunnel Main tunnel Access tunnel

  • The 4K ref. cold box can be installed in

cavern prepared for assembling TBM

  • The size of the cold box will be limited

by transportation on road from factory to the site

Cavern at the end of access tunnel: used for assembling TBM for the tunnels 4 K ref. cold box Transportation of the cold box

slide-7
SLIDE 7

Installation of Main Cryogenic Components

Sub tunnel Main tunnel Access tunnel

D 5.2 m D 4.1 m 10.2 m 7.2 m D 3.9 m Cold box for LHC 18 kW at 4.5K Ref. Cryo-module

  • 4K cold box will be carried through the access tunnel to the cavern at the end of

access tunnel.

  • - Enough cross section for transportation of 4K cold box and compressor unit!

Problems:

  • 2K cold box must be carried in and out through the main tunnel.
  • 2K caverns must be constructed for installation of 2K and distribution boxes.
  • Multi-transfer line must be installed in the crowded main tunnel.

Multi-transfer Line (between 4K and 2K cold boxes)

slide-8
SLIDE 8

New Layout of Cryogenic Plant

  • To solve following problems:

a) Installation of 2K cold through main tunnel b) Need the 2K cryogenic cavern and the long multi-transfer line.

  • -- We decide to change the route of access tunnels

to reach to the 2K cold boxes! New access tunnel plan:

  • Cryogenic caverns will be constructed at the end of the access tunnels

at every 5 km intervals in the tunnel.

  • Main components of two cryogenic plants:

compressor units, 4K refrigerator cold boxes, 2K cold boxes, distribution boxes, and multi-channel transfer line, will be installed in the cryogenic cavern.

slide-9
SLIDE 9

Concept of New Cryogenic Cavern

Access tunnel Access tunnel

56 m 30 m 20 m Main tunnel Sub tunnel

4K cold box Compressor 2K cold box

8 m 20 m

slide-10
SLIDE 10

Detailed Structure of Cryogenic Cavern

  • Temporary size of the cryogenic cavern is given here as for starting point.
  • To decide the shape and size of cavern, we need the detailed design study
  • f the main components and these layout in the cavern.
  • We must keep contact with cryogenic experts who designed, constructed

and has long operation experience of similar system.

  • We need close collaboration with industry to carry out the design study.
  • In designing the cryogenic system we must care about the safety and

maintenance. compressor unit x 2

4K cold box x 2 2K cold box x 2 2K distribution box liquid helium Dewar (50,000 L)

slide-11
SLIDE 11

Helium Compressor Unit

Helium compressor for18kW Helium Ref

/ CERN LHC

  • The helium compressor is installed in far end of the

cryogenic cavern

  • Location of the cavern is ~ 60 m away from the main

tunnel to avoid the vibration

26 m 12.5 m Compressor + Motor 5 m x 1.9 m x 2 m H 6 m

slide-12
SLIDE 12

4K Ref. Cold Box for LHC

Size of 4K cold box Linde 18kW@ 4.5K D4m x L18 m

slide-13
SLIDE 13

4.5K + 1.8K Cold Box and Distribution Box for LHC

slide-14
SLIDE 14

Cold Compressor for LHC 1.8K Refrigerator

Size of Impeller 104 115 165 251

slide-15
SLIDE 15

Storage of Helium Inventory

Vaporization loss: 50,000 L x 0.5%/day = 250 L / day ~10 L/hr

Small refrigerator can be used as “Baby-Sitter”

  • Required Liquid Helium ~ 650,000 L
  • Storage as gas:

standard 100 m3 gas storage tank (D3 m x L15 m) ~ 250 units

  • Storage as liquid:

~50,000 L liquid helium Dewar (D3 m x L10 m )

ILC Cryogenic Systems Reference Design T.J. Peterson et al. CEC Vol. 53

slide-16
SLIDE 16

Conceptual Design of Water Cooling System

1 ~ 2 km ~ 100 m

Cooling Tower A 4K cold box Compressor Access Tunnel Option Shaft for Cooling Tower Cooling Tower Cluster

1) Cooling tower at the entrance of access tunnel can support cooling of underground 2 cryogenic plants. 2) Cooling tower cluster can support cooling of ~ 8km long distributed heat

  • load. The cooling water circulate in 900 mm in diameter pipe.

3) By installation of the cooling tower in the tunnel, we can eliminate heat exchanger which need to cut the head pressure. But we need large bore shaft. 4) By using the “thermo-siphon” of refrigerant we can reduce the pipe size.

slide-17
SLIDE 17

Extraction of heat from the tunnel (1/2)

Plan A

32oC 32oC 37oC 42oC 37oC 37oC DH = 100 m ~150 m

Plan A’

37oC Circulation of water 1) Use the specific heat 2) Large amount of mass flow 3) Large size and long length piping 4) Heat exchanger to cut pressure Heat Exchanger 32oC 37oC 42oC DH = 100 m ~150 m Underground Cooling Tower 1) Eliminate the heat exchanger 2) Need large dia. shaft Cooling Tower Cooling Tower

Access tunnel Shaft

Latent Heat of Water Specific Heat of Water

slide-18
SLIDE 18

Conceptual Design of Underground Cooling Tower

Cooling Tower

~100 m

Cooling Water 37 ℃ 32 ℃ 1 L / sec = 539 kcal / sec = 2253 kW 1 MJ = 0.44 L / sec = 1.6 m3 / hr 5 MW Supply Water ~ 8 m3 / hr Cooling Tower Fan 2 m ~ 3 m2 0.5 MW 5 MW 30 m2 60 m2 ~ 9 m

7 m 10 m

Underground Surface

slide-19
SLIDE 19

Underground Cooling Tower

10 m 10 m

Top view

D 10 m D 7 m 5 m 5 m 7 m

Side view

D 7 m D 10 m 10 m

Cooling Tower Cooling Tower Cooling Tower

Cooling Tower Cooling Tower Cooling Tower Cooling Tower 10 m 5 m 21 m

scale 5 m x 5 m

slide-20
SLIDE 20

Extraction of heat from the tunnel (1/2)

Cooling Tower

Plan A

32oC 32oC 37oC 42oC 37oC

NH3, R410A, R32

37oC H = 100 m ~150 m

Plan B

h1 Te = 35oC 37oC Tc =32oC h2 h3 Cooling Tower Circulation of water 1) Use the specific heat 2) Large amount of mass flow 3) Large size piping 4) Heat exchanger to cut pressure Circulation of refrigerant 1) Use the vaporization heat 2) Small amount of mass flow 3) Small size piping 4) Eliminate the heat exchanger

Gas Liquid Pump Heat Exchanger

Latent Heat of Water

Latent Heat

  • f Refrigerant

At room temperature, the vapor pressure of water is very low. The capacity of heat flow is very small!

Condenser Evaporator

slide-21
SLIDE 21

Heat transfer capacity of refrigerants

WATER AIR NH3 R410A R32 Liquid Gas Liquid Gas Liquid Gas Te 37 37 35 35 35 35 35 35

Pe

  • 1350.8

2139.9

kPaA

Tc 32 32 32 32 32 32 32 32

Pe

  • 1238.2

1975.6

kPaA

Density 1 0.0012 0.587 0.0105 1.008 0.0883 0.912 0.0652

t/m3

Specific Heat 1 0.24

  • Mcal/t・℃

DT 5 5

Latent Heat

  • 268

40.5 59.0

Mcal/t

Velocity 1 5 1 5 1 5 1 5

m/s

Cooling Power 5 0.0072 157.3 14.1 40.8 17.9 53.8 19.2

Mcal/m2・h

slide-22
SLIDE 22

Motor power for circulation of water and refrigerants

WATER AIR NH3 R410A R32 Liquid Gas Liquid Gas Liquid Gas Mass Flow Rate 5160 21500 96.3 637.0 437.3

t/h

Velocity 1.0 5.0 1.0 5.0 1.0 5.0 1.0 5.0

m/s

Pipe Size 1.35 35.60 0.24 0.81 0.47 0.71 0.41 0.69

m

⊿P(@100m) 5 1.3 1.3 0.2 0.2

kPa

Pipe Size 1.00 35.60 0.24 0.81 0.47 0.71 0.41 0.69

m

Velocity 1.82 5.00 1.00 5.00 1.00 5.00 1.00 5.00

m/s

⊿P(@100m) 16.7 1.3 1.3 0.2 0.2

kPa

Pipe Length 4000 2000 100 100 100 100 500 500

m

⊿P 666.1 1.3 1.3 0.2 0.2

kPa

⊿H 0 * 100 100 100 100 100 100

m

Water Head 0 * 587 10.5 1008 88.3 912 65.2

kPa

⊿P at H.X. 100 50 50

kPa

Total ⊿P 766 588.3 61.8 1008.2 138.5 912 65.2

kPa

Pe-Pc 112.6 164.3

kPa

Pump Efficency 60%

%

Motor Power 1318 No Need No Need No Need No Need

kW

Moter Power 4.4% 0.0% 0.0% / Cooling Power

Ideal case: larger pipe size for water Water pipe size: 1m in dia.

Note: In the case of water ; head of flow and return cancelled

30 MW Heat Load Case

slide-23
SLIDE 23

Summary & Future Plan

  • Cryogenic caverns will be constructed at the end of the access

tunnels at every 5 km intervals of the main tunnel.

  • The 4K and 2K cold boxes and distribution box will be installed in

cryogenic caverns.

  • The compressors will be installed in the far end of cryogenic

cavern.

  • Large amount of helium inventory will be stored as liquid helium

for long shutdown of the cryogenic system.

  • The cooling water used at the cryogenic plant will be supplied by

cooling towers constructed at entrance of access tunnel.

  • We need detailed engineering design study of cryogenic system

collaboration with industry.

  • Extraction of heat from the deep tunnel economically is key issue.

We need more study including new idea.