De la wa re Co unty DPW F a c ility Site s T o p Site s Hyb rid - PowerPoint PPT Presentation

De la wa re Co unty DPW F a c ility Site s T o p Site s Hyb rid Site # 11A & 7A a nd Site # 3 March 14, 2018 How We Got Here Site Selection Process Original 12 sites 1. Facility Programing 5. Score Sites (1 10) Site


  1. De la wa re Co unty DPW F a c ility Site s T o p Site s Hyb rid Site # 11A & 7A a nd Site # 3 March 14, 2018

  2. How We Got Here Site Selection Process – Original 12 sites 1. Facility Programing 5. Score Sites (1 – 10) • Site visits on 5/30/17 and 5/31/17 2. Typical Building/Site Layout 6. Establish Criteria Weight 3. Candidate Sites Parameters • Sites 3, 4 and 6 originally by • Supervisor Input County Planning, 7. Ranking of Sites • plus 8 volunteered sites and existing site • (Score x Average Weighting) • Confirmed availability of all 8. Board Direction 6/28/17 • Site 6 off list due to unavailability • Due diligence on top 4 ranked sites 4. Establish Selection Criteria 9. Public Meeting 7/12/17 • Supervisor Input 10.Board Meeting 9/27/17

  3. We Re vie we d a L ist o f E nviro nme nta l I mpa c t F a c to rs • Environmental Fatal Flaw • Historic Buildings • Floodplain • Agricultural District • Steep Slopes • Critical Environmental Area • Federal Wetlands • Principal Aquifer • State Wetlands • Streams/Waterbodies • Archaeology • NYC Watershed

  4. Dire c tio n Sinc e Se pte mb e r 27, 2017 Bo a rd Me e ting • Committee moved to further evaluate Hybrid Site #11A and #7A and Site # 3

  5. Hyb rid Site Optio n Sites # 11A plus Site # 7A: • Rather than relocate all Existing DPW operations to a single site, Wendel was directed by the DPW Committee to prepare a Hybrid Option that distributed the Program to two (2) sites as follows: • Site # e # 7A (Existing S g Site): : Construct an approximately 12,000 SF structure for two (2) Road Patrols to serve their respective areas east of Delhi • Salt shed and cold storage remain in flood way • Incorporate Oil Water Separator pump-outs from other DPW facilities to be discharged into the Village sanitary as • currently permitted Existing Wickham building, DPW Administration and Elections, VA and OET would be maintained in their current • locations temporarily, but demolish and remove structurally compromised existing Patrols Building Relocate heavy/light maintenance garage to site #11A • Relocate DPW Administration on site TBD outside of flood way • Elections, VA and OET to be determined • • Site # # 11A ( (Bishop S Site): Construct the balance of the DPW program including heavy and light maintenance, wash bay, sign and guiderail • shops, storage and parts, paint striper, vacuum truck, etc. – plus a fuel depot Provisions for a future salt shed, bridge fabrication shop and additional Road Patrols space • • Offsite Im Improvement: Reconstruction of Hoags Crossing Bridge Structure approach roadway •

  6. Site # 7A E xisting Co nditio ns

  7. Site # 7A Positive A e Attributes es Negative A e Attributes es • Owned by County • Entire site in Floodplain • Utilities Present • Capital Costs: Build-up Site • Distance to C.O. • Fill at Old Mill Pond – Deep Foundation Costs • Existing Adjacent Neighborhood • Must retain Patrols at this location to serve their respective areas east of Delhi

  8. Site # 11A E xisting Co nditio ns

  9. Site # 11A Hyb rid Positive A e Attributes es Negative A e Attributes es • Distance to C.O. (10 Miles) • Capital Costs • Capital Cost – Bridge/Road Required • Flat area for Development • Does not include new salt shed • Development area Out of Floodplain • Neighborhood and Historic Structure • NYSEG/ARC & Commercial Enterprises in • Access, Speed Limit & Sight Distance Proximity • Acquisition and Demolition

  10. Site # 7A Hyb rid Pa tro l Ga ra g e Only

  11. Site 7A-1

  12. Site 7A-2

  13. NY Route 10 Site # 11A NY Route 10 Hyb rid Ba la nc e Of Pro g ra m

  14. Site # 11A Ho a g s Cro ssing E xisting

  15. Site # 11A Ho a g s Cro ssing Pro po se d

  16. Site # 3 E xisting Co nditio ns

  17. Site # 3 F ull Build Out Positive A e Attributes es Negative A e Attributes es Distance to C.O. Approximately 2 Miles • Access and Acquisition • Flat area for development • • Capital Cost – Bridge/Road Required Useable area out of Floodplain • • Neighborhood Gravel Soils • Alternate Access to CR18 • Archaeological • Includes new salt shed •

  18. Site # 3 NY Route 10 F ull Build Out County Route 18

  19. Site # 3 F lyo ve r

  20. Pro b a b le Ca pito l Co st Summa ry • Site e # 3: # 3: $26. $26.30 30 Million ( (Phase 1 1 ) • Br Bridg dge an and d Road ad in include ded in in this is c cost st • Hybrid S Site # # 11A 1A & Site #7A: #7A: $27.47 Milli lion ( (Pha hase 1 1) • $6.96m Br Brid idge an and d Road ad at at Hoag ags Cr Crossing ar are n not in included in in this c cost st

  21. O&M Co st Summa ry o f Mo ve • Si Site # 3: $240,426 A Additional - 20 y year ars in includes v vehic icle an and plo low • Hybrid Si Site # 11A & Si Site #7A: $1,940,260 A Additional - 20 yea ears vehic icle maintenan ance only • Plows maintained in Delhi

  22. OM F o r Ma inta ining Co unty F le e t a t 11A Used Average 130 Vehicles = 680 Trips Annually Used 10 Miles ($0.60 mi) $20.00 HR x 2 Personnel = $40.00 Total Average Cost for Mileage $24,410 Total Personnel Cost $72,533 Total Annually $97,013 vehicle maintenance moving to 11A 20 20 Yea ears = = $1 $1,940, 40,260 260 a at 20 2018 8 co costs

  23. Ne xt Ste ps TOP RANKED ALTERNATIVE • Maintain Administration, Temporary Patrols Operation and Demolition of Patrols Building • Preliminary Design/Cost Estimate • SEQR • Detailed Impact Assessments • Acquisition • Final Design/Cost Estimate • Bidding • Construction

  24. Que stio ns

  25. Site # 11 F ull Build Out

  26. OM I mpa c t o n Plo w Ro ute s mo ving to 11A Delhi Total Miles: 193.7 Labor 2 Persons $61.07 Per Hour Truck (Fuel, Repairs, Oil) $1.50 Per Mile Hamden Total Miles: 228 35 Miles x Labor x Equipment Cost = $160.00 Average of 145 Trips x $160.00 = Approx. $23,200 Per Year $23,200 x 20 = $464,000 at Today’s Cost

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.