LBNF Cryogenics (Current status) David Montanari Cryogenic - - PowerPoint PPT Presentation

lbnf cryogenics current status
SMART_READER_LITE
LIVE PREVIEW

LBNF Cryogenics (Current status) David Montanari Cryogenic - - PowerPoint PPT Presentation

LBNF Long-Baseline Neutrino Facility LBNF Cryogenics (Current status) David Montanari Cryogenic Instrumentation & Slow Controls Joint Consortium Meeting 22 December 2017 Outline Introduction. Proximity Cryogenics in Detector


slide-1
SLIDE 1

Long-Baseline Neutrino Facility LBNF

LBNF Cryogenics (Current status)

David Montanari Cryogenic Instrumentation & Slow Controls Joint Consortium Meeting 22 December 2017

slide-2
SLIDE 2

LBNF

Outline

12.22.17 David M. | LBNF Cryogenics (Current Status) 2

  • Introduction.
  • Proximity Cryogenics in Detector Cavern.
  • Internal Cryogenic.
  • Cryostat feedthroughs.
  • Proximity Cryogenics in CUC.
  • LN2 Refrigeration System.
  • Lar/LN2 Receiving Facilities on surface.
  • Next Steps.
slide-3
SLIDE 3

LBNF

Introduction

  • Technical talk, no funding considerations.
  • Information is current and design a draft/work in progress.
  • Different design maturity for various parts.
  • Designs based on LBNF/DUNE requirements and real size

components.

  • All items transportable down the Ross Shaft.
  • Preliminary installation sequences thought out (to be

finalized).

  • Lifting eyes on roof of Detector’s cavern and CUC for

equipment lifting and positioning.

  • Goal of design effort is to prepare design packages that

could be procured, by DOE and non-DOE parties.

12.22.17 3 David M. | LBNF Cryogenics (Current Status)

slide-4
SLIDE 4

LBNF

Proximity Cryogenics in Detector’s Cavern

12.22.17 4 David M. | LBNF Cryogenics (Current Status)

Mezzanine LAr circulation pumps

slide-5
SLIDE 5

LBNF

Proximity Cryogenics on Mezzanine – Iso View

12.22.17 5 David M. | LBNF Cryogenics (Current Status)

slide-6
SLIDE 6

LBNF

Proximity Cryogenics on Mezzanine – Side View

7.7 m Envelope of I-Beam + Crane

12.22.17 6 David M. | LBNF Cryogenics (Current Status)

Stay clear zone

slide-7
SLIDE 7

LBNF

Proximity Cryogenics on Mezzanine – Top View

35 m 12 m 2.9 m

12.22.17 7 David M. | LBNF Cryogenics (Current Status)

4.8 m +4.8 m for office type spaces 4.8 m

slide-8
SLIDE 8

LBNF

Internal Cryogenics – 1

12.22.17 David M. | LBNF Cryogenics (Current Status) 8

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 a b c d e f g h i k l m n
  • p
q REF.CERN OBSERVATIONS MAT. POS QUA S.ENS/S.ASS DESCRIPTION ENS/ASS ST0899069_02 CAD Document Number 2017-11-03
  • J. Mayolini
1:50
  • LBNF ASSY Internal pipes cryostat
CONTROLLED DRAWN RELEASED APPROVED REPLACES SIZE IND. NOT VALID FOR EXECUTION NON VALABLE POUR EXECUTION QAC CERN SCALE NORMES ISO ISO STANDARDS PROJECTION DESSIN, RUGOSITE, TOLERANCES SELON DRAWING, RUGOSITY, TOLERANCES ACCORDING TO GENEVE CERN Ce dessin ne peut etre utilise a des fins commerciales sans autorisation ecrite This drawing may not be used for commercial purposes without written authorisation ORGANISATION EUROPEENNE POUR LA RECHERCHE NUCLEAIRE EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH 1 1 14000

B C D

920 1600 2960 4320 6020 7380 9080 10780 12140 13500 14180 15100 580 1120 1590 61000 62000 5417 6932 8619

E F Isometric view 1:200 B 1:10

70 65.55 180 580

C 1:25

340 340 410 370 370 340 410 340

D 1:25

400 340 340 410

E 1:25

410 340 400 340

F 1:25

GAr Purge: 2 in NPS (DN50) LAr Distribution: 3 in NPS (DN80) Elevation from floor: 180 mm (may grow)

slide-9
SLIDE 9

LBNF

Internal Cryogenics – 2

12.22.17 David M. | LBNF Cryogenics (Current Status) 9

slide-10
SLIDE 10

LBNF

Cryostat Cryogenic Feedthroughs (as of Dec 14, 2017)

12.22.17 David M. | LBNF Cryogenics (Current Status) 10

slide-11
SLIDE 11

LBNF

List of Cryogenic Feedthroughs (as of Dec 14, 2017)

12.22.17 David M. | LBNF Cryogenics (Current Status) 11

slide-12
SLIDE 12

LBNF

Cryostat Feedthroughs (as of Dec 14, 2017)

12.22.17 David M. | LBNF Cryogenics (Current Status) 12

slide-13
SLIDE 13

LBNF

List of Feedthroughs (as of Dec 14, 2017)

12.22.17 David M. | LBNF Cryogenics (Current Status) 13

slide-14
SLIDE 14

LBNF

Cryostat Feedthroughs (as of Oct 12, 2017)

12.22.17 David M. | LBNF Cryogenics (Current Status) 14

Not to scale Purge port Instrumentation

slide-15
SLIDE 15

LBNF

LN2 Refrigeration System

12.22.17 David M. | LBNF Cryogenics (Current Status) 15

The LN2 refrigeration system did not change.

  • 4 Commercial units:
  • Cold boxes and gas

boosters in the cavern.

  • GN2 compressors above

ground.

  • Units assembled in

cavern, based on transport limits.

  • 3 units for cryostats 1, 2

and 4th unit added for cryostats 3, 4.

  • 4x97 kW units.
  • Piping in shaft is CF

responsibility.

Cold boxes & Expanders Underground Big Compressors

  • n Surface
slide-16
SLIDE 16

LBNF

LAr/LN2 Receiving Facilities

12.22.17 David M. | LBNF Cryogenics (Current Status) 16

LN2 Storage Tank and Vaporizer LAr Storage Tanks and Vaporizers

LN2 System Compressors Building

Current Cryogens Storage and vaporizers Proposed additional temporary LAr Storage and Vaporizers (LAr fill only)

slide-17
SLIDE 17

LBNF

Next Steps

12.22.17 David M. | LBNF Cryogenics (Current Status) 17

  • Proximity Cryo in Detector’s cavern:
  • Continue to add details to the cryogenics on the mezzanine.
  • Prepare design documentation (Technical Specifications, 3D models with not-to-exceed envelopes, etc.) for non-DOE parties to take on.
  • Implement new LAr pumps model (in progress).
  • Internal Cryogenics:
  • Update the height over the floor, if needed.
  • Discuss with stakeholders and finalize the design.
  • Prepare design documentation (Technical Specifications, 3D models with not-to-exceed envelopes, etc.) for procurement process.
  • Proximity Cryogenics in CUC:
  • Continue to prepare design documentation for LAr Purification #1:ICDs, Functional Requirements Specifications for LAr Purification Vessel.
  • Prepare same documentation for Gar Purification #1, #2 and Regen #1.
  • LN2 Refrigeration System:
  • Continue the iteration with DOE on AP and RFP docs.
  • Issue RFP, get bids, evaluate bids, and select a vendor.
  • Award contract for design (full system) and fabrication of first 3 units.
  • LAr/LN2 Receiving Facilities:
  • Finalize the amount of LAr storage (in consultation with potential LAr vendors).
  • Prepare AP and RFP docs and iterate with DOE.
  • Issue RFP, get bids, evaluate bids, and select a vendor.
  • Award contract for design (full system) and fabrication of first 3 units.
slide-18
SLIDE 18

LBNF

Thanks

12.22.17 18 David M. | LBNF Cryogenics (Current Status)

slide-19
SLIDE 19

LBNF

Backup Slides

12.22.17 19 David M. | LBNF Cryogenics (Current Status)

slide-20
SLIDE 20

LBNF

LAr Receiving Facilities PFD with Mass and Energy Balance

12.22.17 David M. | LBNF Cryogenics (Current Status) 20

Dewars Purif Filter Pump s01 s02 s03 s05 s08 s09 s10 s00 Vaporizer CUC Cavern Updated 2017-01-17

condensers Parameter Pressure Heat duty Value 1.5

  • 264.7

Unit psig kW

LBNF Argon gas Filling PFD

with mass and energy balance

Stream Pressure Temperature Flow rate Vapor phase Mole phase fraction Liquid phase Mole phase fraction s00 35 88 58.3 1 s01 15 300 58.3 1 s02 14.6 300 58.3 1 s03 19.2 300 58.3 1 s05 17.8 300 58.3 1 s08 11 300 58.3 1 s09 10.1 300 58.3 1 s10 1.5 88.2 58.3 1 Unit psig K kg / min

Surface 4850L Ross Shaft

Detector Cavern Cryostat