Long-Baseline Neutrino Facility LBNF
LBNF Cryogenics (Current status) David Montanari Cryogenic - - PowerPoint PPT Presentation
LBNF Cryogenics (Current status) David Montanari Cryogenic - - PowerPoint PPT Presentation
LBNF Long-Baseline Neutrino Facility LBNF Cryogenics (Current status) David Montanari Cryogenic Instrumentation & Slow Controls Joint Consortium Meeting 22 December 2017 Outline Introduction. Proximity Cryogenics in Detector
LBNF
Outline
12.22.17 David M. | LBNF Cryogenics (Current Status) 2
- Introduction.
- Proximity Cryogenics in Detector Cavern.
- Internal Cryogenic.
- Cryostat feedthroughs.
- Proximity Cryogenics in CUC.
- LN2 Refrigeration System.
- Lar/LN2 Receiving Facilities on surface.
- Next Steps.
LBNF
Introduction
- Technical talk, no funding considerations.
- Information is current and design a draft/work in progress.
- Different design maturity for various parts.
- Designs based on LBNF/DUNE requirements and real size
components.
- All items transportable down the Ross Shaft.
- Preliminary installation sequences thought out (to be
finalized).
- Lifting eyes on roof of Detector’s cavern and CUC for
equipment lifting and positioning.
- Goal of design effort is to prepare design packages that
could be procured, by DOE and non-DOE parties.
12.22.17 3 David M. | LBNF Cryogenics (Current Status)
LBNF
Proximity Cryogenics in Detector’s Cavern
12.22.17 4 David M. | LBNF Cryogenics (Current Status)
Mezzanine LAr circulation pumps
LBNF
Proximity Cryogenics on Mezzanine – Iso View
12.22.17 5 David M. | LBNF Cryogenics (Current Status)
LBNF
Proximity Cryogenics on Mezzanine – Side View
7.7 m Envelope of I-Beam + Crane
12.22.17 6 David M. | LBNF Cryogenics (Current Status)
Stay clear zone
LBNF
Proximity Cryogenics on Mezzanine – Top View
35 m 12 m 2.9 m
12.22.17 7 David M. | LBNF Cryogenics (Current Status)
4.8 m +4.8 m for office type spaces 4.8 m
LBNF
Internal Cryogenics – 1
12.22.17 David M. | LBNF Cryogenics (Current Status) 8
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 a b c d e f g h i k l m n- p
- J. Mayolini
- LBNF ASSY Internal pipes cryostat
B C D
920 1600 2960 4320 6020 7380 9080 10780 12140 13500 14180 15100 580 1120 1590 61000 62000 5417 6932 8619E F Isometric view 1:200 B 1:10
70 65.55 180 580C 1:25
340 340 410 370 370 340 410 340D 1:25
400 340 340 410E 1:25
410 340 400 340F 1:25
GAr Purge: 2 in NPS (DN50) LAr Distribution: 3 in NPS (DN80) Elevation from floor: 180 mm (may grow)
LBNF
Internal Cryogenics – 2
12.22.17 David M. | LBNF Cryogenics (Current Status) 9
LBNF
Cryostat Cryogenic Feedthroughs (as of Dec 14, 2017)
12.22.17 David M. | LBNF Cryogenics (Current Status) 10
LBNF
List of Cryogenic Feedthroughs (as of Dec 14, 2017)
12.22.17 David M. | LBNF Cryogenics (Current Status) 11
LBNF
Cryostat Feedthroughs (as of Dec 14, 2017)
12.22.17 David M. | LBNF Cryogenics (Current Status) 12
LBNF
List of Feedthroughs (as of Dec 14, 2017)
12.22.17 David M. | LBNF Cryogenics (Current Status) 13
LBNF
Cryostat Feedthroughs (as of Oct 12, 2017)
12.22.17 David M. | LBNF Cryogenics (Current Status) 14
Not to scale Purge port Instrumentation
LBNF
LN2 Refrigeration System
12.22.17 David M. | LBNF Cryogenics (Current Status) 15
The LN2 refrigeration system did not change.
- 4 Commercial units:
- Cold boxes and gas
boosters in the cavern.
- GN2 compressors above
ground.
- Units assembled in
cavern, based on transport limits.
- 3 units for cryostats 1, 2
and 4th unit added for cryostats 3, 4.
- 4x97 kW units.
- Piping in shaft is CF
responsibility.
Cold boxes & Expanders Underground Big Compressors
- n Surface
LBNF
LAr/LN2 Receiving Facilities
12.22.17 David M. | LBNF Cryogenics (Current Status) 16
LN2 Storage Tank and Vaporizer LAr Storage Tanks and Vaporizers
LN2 System Compressors Building
Current Cryogens Storage and vaporizers Proposed additional temporary LAr Storage and Vaporizers (LAr fill only)
LBNF
Next Steps
12.22.17 David M. | LBNF Cryogenics (Current Status) 17
- Proximity Cryo in Detector’s cavern:
- Continue to add details to the cryogenics on the mezzanine.
- Prepare design documentation (Technical Specifications, 3D models with not-to-exceed envelopes, etc.) for non-DOE parties to take on.
- Implement new LAr pumps model (in progress).
- Internal Cryogenics:
- Update the height over the floor, if needed.
- Discuss with stakeholders and finalize the design.
- Prepare design documentation (Technical Specifications, 3D models with not-to-exceed envelopes, etc.) for procurement process.
- Proximity Cryogenics in CUC:
- Continue to prepare design documentation for LAr Purification #1:ICDs, Functional Requirements Specifications for LAr Purification Vessel.
- Prepare same documentation for Gar Purification #1, #2 and Regen #1.
- LN2 Refrigeration System:
- Continue the iteration with DOE on AP and RFP docs.
- Issue RFP, get bids, evaluate bids, and select a vendor.
- Award contract for design (full system) and fabrication of first 3 units.
- LAr/LN2 Receiving Facilities:
- Finalize the amount of LAr storage (in consultation with potential LAr vendors).
- Prepare AP and RFP docs and iterate with DOE.
- Issue RFP, get bids, evaluate bids, and select a vendor.
- Award contract for design (full system) and fabrication of first 3 units.
LBNF
Thanks
12.22.17 18 David M. | LBNF Cryogenics (Current Status)
LBNF
Backup Slides
12.22.17 19 David M. | LBNF Cryogenics (Current Status)
LBNF
LAr Receiving Facilities PFD with Mass and Energy Balance
12.22.17 David M. | LBNF Cryogenics (Current Status) 20
Dewars Purif Filter Pump s01 s02 s03 s05 s08 s09 s10 s00 Vaporizer CUC Cavern Updated 2017-01-17
condensers Parameter Pressure Heat duty Value 1.5
- 264.7
Unit psig kW
LBNF Argon gas Filling PFD
with mass and energy balance
Stream Pressure Temperature Flow rate Vapor phase Mole phase fraction Liquid phase Mole phase fraction s00 35 88 58.3 1 s01 15 300 58.3 1 s02 14.6 300 58.3 1 s03 19.2 300 58.3 1 s05 17.8 300 58.3 1 s08 11 300 58.3 1 s09 10.1 300 58.3 1 s10 1.5 88.2 58.3 1 Unit psig K kg / min
Surface 4850L Ross Shaft
Detector Cavern Cryostat