lbnf cryogenics progress
play

LBNF Cryogenics Progress David Montanari FS Integration 21 - PowerPoint PPT Presentation

LBNF Long-Baseline Neutrino Facility LBNF Cryogenics Progress David Montanari FS Integration 21 February 2018 Thanks to Mark Adamowski (Fermilab). Jean-Baptiste Mayolini (CERN). Mike Delaney (Fermilab). Aurlien Diaz (CERN).


  1. LBNF Long-Baseline Neutrino Facility LBNF Cryogenics Progress David Montanari FS Integration 21 February 2018

  2. Thanks to • Mark Adamowski (Fermilab). • Jean-Baptiste Mayolini (CERN). • Mike Delaney (Fermilab). • Aurélien Diaz (CERN). • Roza Doubnik (Fermilab). • Jack Fowler (Duke University). • Kevin Haaf (Fermilab). • Marzio Nessi (CERN). • Adrien Parchet (CERN). • Erik Voirin (Fermilab). 2 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  3. Proximity Cryogenics in Detector’s Cavern 3 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  4. Proximity Cryogenics on Mezzanine – Iso View (as Oct 2017) 7.7 m 4.8 m 35 m 12 m Added 4.8 m to access detector feedthroughs 4 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  5. Proximity Cryogenics on Mezzanine – Iso View (Current) 4.8 m 44.6 m 12 m 5 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  6. Proximity Cryogenics on Mezzanine – Iso View (Current) 4.8 m m 6 . 4 4 12 m 6 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  7. Proximity Cryogenics on Mezzanine – Side View (Current) Envelope of I-Beam + Crane Stay clear zone 7.7 m 7 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  8. Proximity Cryogenics on Mezzanine – Top View 12 m 2.9 m 44.6 m 4.8 m 8 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  9. Transformers Requirements From: Theresa M Shaw tshaw@fnal.gov Subject: RE: LBNF Transformers on mezzanine? Date: February 21, 2018 at 9:37 AM To: David Montanari dmontana@fnal.gov Cc: Theresa M Shaw tshaw@fnal.gov, Steve J Chappa chappa@fnal.gov, Arnab Ghosh arnabg@fnal.gov Hi David, Our proposed DUNE Detector AC distribution is in docdb 6922. What is proposed for placement on the mezzanine are the (4) 112.5KVA transformers each paired with a Rack (4 total) which holds the Saturable Inductor and Impedance Monitor. So, similar to ProtoDUNE x 4. Each transformer: Weight ~810 lbs 30” (w) x30” (d) X37” (h) Rack: Weight ~700 lbs (guess) 24” (w) x 30 (d) x 79” (h) Note that there are also codes for working areas or “stay clear” areas around the transformers of – “ The general distances for working clearance are 3 feet in front and a minimum width of 30 inches”. Steve Chappa is thinking about the best locations for this equipment on the mezzanine, but I wanted to get you these initial numbers. -Terri 9 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  10. Proximity Cryogenics on Mezzanine – Highlights • Extended mezzanine platform by 9.6 m (Was 39.8 m, now 49.4). • Added two office-type spaces. • Increased number of controls racks (from 4 to 8). • Added collectors for purges in feedthroughs. • Added panel for GAr Analyzers to collect lines from purges. • Cleanup and minor modifications to pipe routing. • Getting requirements on transformers and racks to be places on mezzanine. Will be implemented soon. 10 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  11. LAr Pumps 11 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  12. LAr Pumps Configuration (as of Oct 2017) Mezzanine LAr circulation pumps 12 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  13. LAr Pumps Configuration (Current) – 1/2 Space for lifting device Current clearance: 0.8 m 2.0 m x 2.0 m (Alimak, etc.) 13 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  14. LAr Pumps Configuration (Current) – 2/2 Current Equipment height: 4.2 m 14 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  15. NP-04 – Protection for Protego + Valve Box 15 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

  16. LAr Pumps – Highlights • Removed pump towers and replaced with inline pumps + valve boxes. • Verified size of pipes and updated model. Inlet/outlet to/from LAr pumps are now smaller: - 3 in SCH 10 (DN 80) process. - 5 in SCH 10 (DN 125) vacuum jacket. • Left 2.0 m x 2.0 m in NE corner for lifting device/stairs. • Need to add protective structure that might be 5.0-5.5 m high. • Working with Far Detector on Clean Room requirements and interfaces. Access and space are shared in this area. • Working with Cryostat, Far Detector, Systems Engineering on installation sequence. • Ongoing discussion on rock septum and whether it is removed. 16 02.21.18 David Montanari | LBNF Cryogenics Progress LBNF

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend