LBNF Cryogenics Progress David Montanari FS Integration 21 - - PowerPoint PPT Presentation

lbnf cryogenics progress
SMART_READER_LITE
LIVE PREVIEW

LBNF Cryogenics Progress David Montanari FS Integration 21 - - PowerPoint PPT Presentation

LBNF Long-Baseline Neutrino Facility LBNF Cryogenics Progress David Montanari FS Integration 21 February 2018 Thanks to Mark Adamowski (Fermilab). Jean-Baptiste Mayolini (CERN). Mike Delaney (Fermilab). Aurlien Diaz (CERN).


slide-1
SLIDE 1

Long-Baseline Neutrino Facility LBNF

LBNF Cryogenics Progress

David Montanari FS Integration 21 February 2018

slide-2
SLIDE 2

LBNF

Thanks to

02.21.18 David Montanari | LBNF Cryogenics Progress 2

  • Mark Adamowski (Fermilab).
  • Jean-Baptiste Mayolini (CERN).
  • Mike Delaney (Fermilab).
  • Aurélien Diaz (CERN).
  • Roza Doubnik (Fermilab).
  • Jack Fowler (Duke University).
  • Kevin Haaf (Fermilab).
  • Marzio Nessi (CERN).
  • Adrien Parchet (CERN).
  • Erik Voirin (Fermilab).
slide-3
SLIDE 3

LBNF

Proximity Cryogenics in Detector’s Cavern

02.21.18 David Montanari | LBNF Cryogenics Progress 3

slide-4
SLIDE 4

LBNF

Proximity Cryogenics on Mezzanine – Iso View (as Oct 2017)

35 m 12 m 7.7 m

02.21.18 4 David Montanari | LBNF Cryogenics Progress

4.8 m

Added 4.8 m to access detector feedthroughs

slide-5
SLIDE 5

LBNF

Proximity Cryogenics on Mezzanine – Iso View (Current)

44.6 m 12 m

02.21.18 5 David Montanari | LBNF Cryogenics Progress

4.8 m

slide-6
SLIDE 6

LBNF

Proximity Cryogenics on Mezzanine – Iso View (Current)

4 4 . 6 m 12 m

02.21.18 6 David Montanari | LBNF Cryogenics Progress

4.8 m

slide-7
SLIDE 7

LBNF

Proximity Cryogenics on Mezzanine – Side View (Current)

7.7 m Envelope of I-Beam + Crane

02.21.18 7 David Montanari | LBNF Cryogenics Progress

Stay clear zone

slide-8
SLIDE 8

LBNF

Proximity Cryogenics on Mezzanine – Top View

44.6 m 12 m 2.9 m

02.21.18 8 David Montanari | LBNF Cryogenics Progress

4.8 m

slide-9
SLIDE 9

LBNF

Transformers Requirements

02.21.18 9 David Montanari | LBNF Cryogenics Progress

From: Theresa M Shaw tshaw@fnal.gov Subject: RE: LBNF Transformers on mezzanine? Date: February 21, 2018 at 9:37 AM To: David Montanari dmontana@fnal.gov Cc: Theresa M Shaw tshaw@fnal.gov, Steve J Chappa chappa@fnal.gov, Arnab Ghosh arnabg@fnal.gov

Hi David, Our proposed DUNE Detector AC distribution is in docdb 6922. What is proposed for placement on the mezzanine are the (4) 112.5KVA transformers each paired with a Rack (4 total) which holds the Saturable Inductor and Impedance Monitor. So, similar to ProtoDUNE x 4. Each transformer: Weight ~810 lbs 30” (w) x30” (d) X37” (h) Rack: Weight ~700 lbs (guess) 24” (w) x 30 (d) x 79” (h) Note that there are also codes for working areas or “stay clear” areas around the transformers of – “The general distances for working clearance are 3 feet in front and a

minimum width of 30 inches”. Steve Chappa is thinking about the best locations for this equipment on the mezzanine, but I wanted to get you these initial numbers.

  • Terri
slide-10
SLIDE 10

LBNF

Proximity Cryogenics on Mezzanine – Highlights

02.21.18 David Montanari | LBNF Cryogenics Progress 10

  • Extended mezzanine platform by 9.6 m (Was 39.8 m, now 49.4).
  • Added two office-type spaces.
  • Increased number of controls racks (from 4 to 8).
  • Added collectors for purges in feedthroughs.
  • Added panel for GAr Analyzers to collect lines from purges.
  • Cleanup and minor modifications to pipe routing.
  • Getting requirements on transformers and racks to be places on
  • mezzanine. Will be implemented soon.
slide-11
SLIDE 11

LBNF

LAr Pumps

02.21.18 David Montanari | LBNF Cryogenics Progress 11

slide-12
SLIDE 12

LBNF

LAr Pumps Configuration (as of Oct 2017)

02.21.18 12 David Montanari | LBNF Cryogenics Progress

Mezzanine LAr circulation pumps

slide-13
SLIDE 13

LBNF

LAr Pumps Configuration (Current) – 1/2

02.21.18 13 David Montanari | LBNF Cryogenics Progress

Space for lifting device 2.0 m x 2.0 m (Alimak, etc.) Current clearance: 0.8 m

slide-14
SLIDE 14

LBNF

LAr Pumps Configuration (Current) – 2/2

02.21.18 14 David Montanari | LBNF Cryogenics Progress

Current Equipment height: 4.2 m

slide-15
SLIDE 15

LBNF

NP-04 – Protection for Protego + Valve Box

02.21.18 15 David Montanari | LBNF Cryogenics Progress

slide-16
SLIDE 16

LBNF

LAr Pumps – Highlights

02.21.18 David Montanari | LBNF Cryogenics Progress 16

  • Removed pump towers and replaced with inline pumps + valve

boxes.

  • Verified size of pipes and updated model. Inlet/outlet to/from LAr

pumps are now smaller:

  • 3 in SCH 10 (DN 80) process.
  • 5 in SCH 10 (DN 125) vacuum jacket.
  • Left 2.0 m x 2.0 m in NE corner for lifting device/stairs.
  • Need to add protective structure that might be 5.0-5.5 m high.
  • Working with Far Detector on Clean Room requirements and
  • interfaces. Access and space are shared in this area.
  • Working with Cryostat, Far Detector, Systems Engineering on

installation sequence.

  • Ongoing discussion on rock septum and whether it is removed.