H667 Priority Trunk Mains Rehabilitation PHASE 1 (Option 2) Proposed Start Date 18 th March 30 th April 2019 Notes: 1, Bus lane closure is subject to TTRO. Currently waiting to speak to Rachael Goddard to Graeme


slide-1
SLIDE 1

1

H667 Priority Trunk Mains Rehabilitation – PHASE 1 (Option 2) Proposed Start Date 18th March – 30th April 2019 Notes:

1, Bus lane closure is subject to TTRO. Currently waiting to speak to Rachael Goddard to confirm date for start on 20th March. Alternative start date 6th April. 2, UTC to be consulted regarding the traffic signal

  • peration on the junction
  • f Christchurch/Norwood

Road. 3, Cycle Diversion around gyratory.

Graeme Oddy – Senior Traffic Manager Mo Arshid – Site Manager Aghogho Amelia Asagba – Customer & Stakeholder Co-ordinator

slide-2
SLIDE 2

2

Your Team on Norwood Road

(The dream Team)

Graeme Oddy

Senior Traffic Manager

Phil Hawley

Construction Manager

Ian Welch Project

Manager

Mo Arshid Site

Manager

Dan Walsh

Construction Manager (Instalcom)

Dean Freedman

Construction Manager (Instalcom)

slide-3
SLIDE 3

3

slide-4
SLIDE 4

4

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

Where are we now ?

slide-8
SLIDE 8

8

Where are we now ?

slide-9
SLIDE 9

9

Phase 2/1 & 1A Challenges (Unchartered Services)

  • Low pressure 18” Gas Main
  • Existing 8” Cast iron water main (below Gas)
  • 640mm between Gas & Water pipes
  • Hand dig around existing services
  • Redesign of trunk main to go below existing
  • Existing water pipe burst by Parade Mews
slide-10
SLIDE 10

10

Phase 2/1 Pipe Burst

slide-11
SLIDE 11

11

Phase 2/1 Pipe Burst

slide-12
SLIDE 12

12

Phase 2/1 Pipe Burst

slide-13
SLIDE 13

13

Phase 1A Challenges (Unchartered Services)

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

H667 Priority Trunk Mains Rehabilitation – Options 1 & 2 Work Areas

slide-16
SLIDE 16

16