Constant Terminal Voltage Working Group Meeting 3 19 th June 2014 - - PowerPoint PPT Presentation

constant terminal voltage
SMART_READER_LITE
LIVE PREVIEW

Constant Terminal Voltage Working Group Meeting 3 19 th June 2014 - - PowerPoint PPT Presentation

Constant Terminal Voltage Working Group Meeting 3 19 th June 2014 Overview Options Study results Theoretical Analysis Summary 2 Options Option 1 Constant Terminal Voltage controlled to 1 p.u with full Transformer Tapping


slide-1
SLIDE 1

Constant Terminal Voltage

Working Group Meeting 3 19th June 2014

slide-2
SLIDE 2

2

Overview

Options Study results Theoretical Analysis Summary

slide-3
SLIDE 3

3

Options

Option 1 – Constant Terminal Voltage controlled to 1 p.u with full Transformer Tapping Option 2 - Adjustable Terminal Voltage with a limited Transformer Tapping Range Option 3 – Limited Transformer Tapping Range only

slide-4
SLIDE 4

4

Advantages / Disadvantages

Option Advantages Disadvantages 1 i) Generator Terminal voltage continuously controlled to 1p.u ii) Maintains current Dynamic Reserve provision post fault. iii) Maintains Stability margin i) Potentially more expensive than other options (eg Transformer required with wider tapping range). ii) References to BCA – Loss of Transparency iii) Does not fully address Derogation issue 2 i) Potentially cheaper Generator Transformer with lower tapping range. ii) Preserves the total reactive capability (ie operating envelope still maintained) i) Less dynamic MVAr reserve provision post fault. ii) Lower Stability Margin iii) More complex to define minimum requirements of Generator transformer tapping range and Generating Unit target voltage range. iv) Wider System implications would need to be understood eg would more reactive compensation equipment be required on the System or would enhanced excitation performance requirements be necessary. 3 i) Potentially cheaper Transformer with lower tapping range i) As per option 2 in particular iv) which is likely to result in potentially greater costs to both NGET and Generators

slide-5
SLIDE 5

5

Summary from Previous Meeting

Each option does have an effect on the terminal voltage of the Generator and the System Operators ability to control system voltage Impact on Excitation voltage and MVAr reserves Whilst impact on a machine basis is small this would be more significant across the total System National Grid’s preferred approach is Option 1 Constant Terminal Voltage controlled to 1 p.u with full Transformer Tapping. Applies to new plant with relaxations permitted for existing plant who are unable to meet the current GB requirements

slide-6
SLIDE 6

6

Multi Machine Study

slide-7
SLIDE 7

Study Statistics

Winter Peak 2014 Study Peak Demand = 54.4GW MVAr Demand = 14.8 MVAr Double circuit fault applied to Canterbury – Kemsley, Canterbury - Cleeve Hill Test Station – Marchwood - run at maximum reactive

  • utput - full lag (0.85 PF lag).

Generator limits not modelled

slide-8
SLIDE 8

8

Option 1 - Full Generator tapping range (±13 taps) – 1.25% tap step size on transformer voltage rating Option 2 - Limited tapping range (±6 taps) and terminal voltage adjusted to 1.0118 p.u – 1.25% tap step size

  • n transformer voltage rating

Option 3A – Limited tapping range (±6 taps) and terminal voltage adjusted to 1.0 p.u – 1.25% tap step size on transformer voltage rating Option 3B – limited tapping range and 1.0 p.u voltage (±6 taps) – 2.5% tap step size on transformer rating

Options – Test Generator - Marchwood

slide-9
SLIDE 9

9

Reactive Power Output - Marchwood

Option 1

slide-10
SLIDE 10

10

Marchwood – Terminal Voltage

Option 2 Option 3B

slide-11
SLIDE 11

11

400kV Voltage - Marchwood

Option 3B Option 2 Option 3A

slide-12
SLIDE 12

12

400kV Voltage - Bolney

Option 1 Option 3B

slide-13
SLIDE 13

13

400kV Voltage - Canterbury

Option 1 Option 1 Option 2 Option 3B Option 3A

slide-14
SLIDE 14

14

Theoretical Analysis

Single line diagram Equivalent circuit Data from a typical Generator Transformer Copper losses neglected Generator not modelled

slide-15
SLIDE 15

0.94 0.96 0.98 1 1.02 1.04 1.06

  • 400
  • 300
  • 200
  • 100

100 200 300 400 System Voltage (pu) Qg (MVAr)

15

Machine MVAr Output

a P aX V V X V Q

g tr s g tr g

g

=

2 2

Position 0 Position -6 Position -10 Position 10 Position 6 Increase Tap Decrease Tap

slide-16
SLIDE 16

16

Setting the terminal voltage ( )

2 2 4 2

4 1 2 1

g tr s g tr s g tr s g

P X a V Q X a V Q X a V V −

  • +
  • +

+

  • =

0.94 0.96 0.98 1 1.02 1.04 1.06

  • 300
  • 200
  • 100

100 200 300 400 Voltage (p.u.) Q (MVAr)

Point 1:

1.05pu Voltage at the GEP 1.0pu Generator Terminal Voltage Tap position 9

Point 2:

Change to tap position 6

Point 3:

Increase the machine terminal to 1.031pu

1 2 3

slide-17
SLIDE 17

Reactive power output Rate of change of reactive power output for a step change in voltage at the Grid Entry Point

17

Response to a step change in voltage

a P aX V V V aX V V Q

g tr s g s tr g s g

= ∂ ∂

2 2

a P aX V V X V Q

g tr s g tr g

g

=

2 2

slide-18
SLIDE 18

0.9 0.92 0.94 0.96 0.98 1 1.02 1.04 1.06 1.08 1.1 85 90 95 100 105 110 115 Vg(pu) ∆Q (MVAr)/5% drop in Vs Tap Position 9 Tap Position 6 Point 1 Point 2 Point 3

18

Response to a step change in voltage

Point 1, 2, and 3 correspond to the same initial operating points as per previous slide Diagram shows increase in reactive power injected in response to a 5% step drop in voltage at the Grid Entry Point. Results seem to suggest an improvement which is not evident from study work

slide-19
SLIDE 19

19

Summary

Results of multi machine studies (South Coast) show an second order effect but difficult to draw exact conclusions Theoretical analysis suggests that an improvement in performance could be obtained if terminal voltage contributes to the HV voltage This needs to be re-assessed in Digsilent / Power Factory to confirm the theory Further feedback from working group required

slide-20
SLIDE 20

20

Discussion