AOC meeting
6 February 2018
AOC meeting 6 February 2018 Agenda Welcome Minute from last - - PowerPoint PPT Presentation
1 AOC meeting 6 February 2018 Agenda Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH
6 February 2018
Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH including updates on following issues:
Safety Security Update on the Baggage Factory West and the staff Canteen 2021-2022 Update on the new Pier E Update on the T3 Landside construction Misc.
2
AOC – February 6th, 2018 Lars Konrad Morten D. Nannestad
PRESENTATION VALIZO Explainer video
BRIEF INTRO
summer of 2016
and participation in the Danish CAA Security Seminar
VALiZO - freedom and energy to travellers while
Through integrity, credibility and professionalism we create strong relations to partners as well as employees with focus on the customer’s values
THE SERVICE
HOME Airport
HOME HOTEL Air BnB Vacation house Cruise
VALiZO brings luggage between home and airport, do check-in and deliver boarding pass
VALiZO check all travel documents and luggage allowance, and deliver bag tags and boarding pass upon pick up – just like when a passenger goes to the counter at the airport Several days before departure VALiZO makes a first check of travel documents and thereby avoiding troubles later in the process (for instance at the check-in counter or the gate) Price from 395 DKK (6 persons and 6 pieces of ordinary luggage)
TRUSTPILOT, 98% SCORES 5
A degree of ”waoo” effect when the customer has used the service. Allready we see repeaters, 30%+ has bought the service 2-10 times
TESTIMONIALS
CURRENT PARTNERS
THOMAS COOK AIRLINES DANISH AIR TRANSPORT ATLANTIC AIRWAYS PRIMERA AIR AIR GREENLAND SAS AVIATOR SAS GROUND HANDLING SEVERAL TRAVEL AGENCIES, HOTELS AND CRUISE HANDLERS CPH
THE PARTNER COOPERATION AND BENEFITS
Deliver an excellent and much appreciated service to the customer, eg. Stressfree pax Resolves issues regarding passport and visa before entering the airport It increases travel and converts loyal users of one airline/travel agency from those that doesn’t supply this service to those who does A more smooth luggage flow in the terminals, due to good coordination between handler and VALiZO
NEXT STEP
CAA- SOLVING THE ISSUE RELATED TO SEPARATING PAX AND LUGGAGE BEFORE ENTERING THE AIRPORT
Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH including updates on following issues:
Safety Security Update on the Baggage Factory West and the staff Canteen 2021-2022 Update on the new Pier E Update on the T3 Landside construction Misc.
10
PNR/API DATA TO SKAT
February 6th 2018. Project Manager Carsten M. Nielsen Project Assistant Mathias Olsen
Danish Law is only availible in Danish. The relevant laws and decrees are availible at www.retsinformation.dk but only in Danish. Danish Border Control: Decree no. 1197 of 26/09/2016 // Decree no. 1635 of 19/12 2017 Danish Law on Terror and Danish Law on Customs: Law no.1881 of 29/12-2015 Decree no. 1453 of 20/11/2016
All implementation and testing must be completed at this time.
compliant with the National Danish Laws and regulations.
passenger information on arrival and departure in Denmark, which would be a very time consuming action for both the airline and its passengers.
SKAT/Danish Customs Agency is the Danish ”Single-Window” regarding all API/PNR data.
05-02-2018 12
The grace period will terminate at 30th June 2018
Decree no. 1508 of 14/12/2017 – granting an extension of the grace period.
B address: CPHPPXA (Production) CPHPTXA (Test) Format: PAXLST 05B or higher UNB Segment Interchange Recipient ID Element: DKSKATAP UNG Segment Application Recipient ID Element: DKSKATAP Time of delivering: No later than wheels-up For PAX and CREW Inbound and Outbound Non-Schengen flights MQ or B address: CPHBPXA (Production) CPHBTXA (Test) MQ: Please contact ARINC Version: 11.1, 13.1 or 15.1 or higher UNB Segment Interchange Recipient ID Element: DKSKATPN UNG Segment Application Recipient ID Element: DKSKATPN Time of delivering:
For PAX Inbound and Outbound Schengen and Non-Schengen flights
05-02-2018 13
API PNR
Delivering data
All implementation and testing must be finalized latest 30th June 2018
SKAT/Danish Customs (Danish Single Window) APAS-DK@skat.dk
The mailbox is checked during normal office hours.
ARINC/Rockwell Collins (Data Provider) Jon Floyd, jfloyd@arinc.com Ricky Woolway, rwoolway@arinc.com
Please CC APAS-DK@skat.dk when in any contact ARINC/Rockwell Collins regarding data to Danish Authorities.
05-02-2018 14
Contact information
Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH including updates on following issues:
Safety Security Update on the Baggage Factory West and the staff Canteen 2021-2022 Update on the new Pier E Update on the T3 Landside construction Misc.
15
Be responsible Comply with rules Share your concerns
We respect persons who report their involvement in safety
We treat reports confidentially and protect personal information at all times. CPH Safety & Crisis Management (SCM) January 2018 Rapport
Total reported Absolute number per type of operation
Nothing to report for this month.
Total reported Absolute number per type of operation
Nothing to report for this month.
Total reported Avoiding action required
Figure 1: Increasing trend indicates the awareness of reporting such event; Figure 2: No significant increasing trend.
Total reported to CPH Absolute number per type of operation
1 damaged cargo compartment during cargo loading reported.
Total reported Reported per Aircraft Stand Type
1 reported for aircraft stand equipped with centreline/stop marking.
DGS: meaning pilot follows electronic dock station when taxiing a/c onto stand. Marshaller: meaning pilot is guided by CPH marshaller when taxiing a/c onto stand. Centreline/stop marking: meaning pilot follows day markings on ground when taxiing a/c onto stand.
CNS/ATM system Support system to CNS/ATM system
(power supply, network, etc.)
SCM and ATM department are working on improving the presentation form of CNS/ATM related safety data. Therefore, no trend and analysis will be displayed for the moment.
No actual safety consequences:
The screen of ASMGCS redundant position for
APRON in TOWER stopped updating every 10 seconds and user couldn’t give input by mouse and keyboard. IT will keep a close watch on the performance of this screen.
5 min. outage on two of the MLAT- antennas
due to failure of diesel generator. The event is reported to TBST.
LED approach light on RWY 22R was
reported dazzling pilot’s eyesight.
False alarm in MET in TOWER. Naviair is
investigating.
UPS was running with limited time capacity, as
two of the three power supplies for UPS were
generator failed and couldn’t be repaired within short time; mobile generator was under
Should UPS have had failed would Radar Nord be out of service, which would resulted in increased operational workload in TOWER.
Aerodrome area related
(runway incursion, damage on ground and movement in front of/behind moving aircraft)
CNS related self-reporting
(report of human factors that (can) lead to safety-concerns)
Nothing to report for this month.
4 out of 15 self-reportable events were not reported by involved person. Three were related to movement in front of/behind moving aircraft, though no avoiding action was required. One was related to aircraft damage from cargo loading.
Total analysed birdstrikes Birdstrikes anlaysed of high risk
None of the birdstrikes in this month were reported by pilots.
X1 X2
Musvåge Common Buzzard Mosehornugler Short-eared owl
Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH including updates on following issues:
Safety Security Update on the Baggage Factory West and the staff Canteen 2021-2022 Update on the new Pier E Update on the T3 Landside construction Misc.
25
by/Johnnie Müller
CSC Performance report week 1-5 CSC Update
27
28
29
Waiting time at CPH Express – January 2018
There were 3 days in January with waiting times more than 5 minutes (KPI 99%)
Thursday 01-02-18: (KPI 98.7%) Friday 02-02-18: (KPI 97.9%) Sathurday 03-02-18: (KPI 95.4%) Due to the recent relocation of advanced bording west, we have experienced a few days with challenges with the CPH Express passenger flow. This is caused by lack of signage and a procedure for the usage of more than one express track. This work is underway, and we therefore expect that this challenge is solved this week.
30
Tremendously capacity improvement for our passengers
31
Flow
Efficient Quick Smooth Unproblematic Predictable
Experience
No stress Feeling secure Outstanding service Good working environment
Security
High level of Security Modern High-technology First mover
32
Test lanes 23 + 24 Development and test (equipment,
flow etc.)
Staff involvements in the solutions Test, implementation and daily
10
The new CSC area stairs to second floor
34
Lane number 23 and 24 are the 2 new test lanes
35
Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH including updates on following issues:
Safety Security Update on the Baggage Factory West and the staff Canteen 2021-2022 Update on the new Pier E Update on the T3 Landside construction Misc.
36
Make-Up EBS Centralized Off load Reclaim hall BF3 Make-Up EBS
Screening
AOC 6/2 2018
Screening
38
LB6 LB14 Terminal 2
39
40
41
42
43
Specification Contracting Design Construction Basement + Baggage Factory Construction Upper floors Baggage installation Enabling works HBS Standard 3 upgrade
AOC February 2018 Summer 2021
Ground handler input – support areas Ground handler work shop Stakeholder involvement Fall 2018 / Spring 2019 Test and commissioning Familiarization Training Trials
Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH including updates on following issues:
Safety Security Update on the Baggage Factory West and the staff Canteen 2021-2022 Update on the new Pier E Update on the T3 Landside construction Misc.
44
Jenny Secher AOC | Feb 6th 2018
5 February, 2018
Supply additional space for long-haul traffic
and large aircrafts - both indoor and stands
New and improved open bus-gate area with
bus-gate capacity for wide-body aircrafts
Support new Border Control regulations –
100% control in/out of Schengen
Supply space for support to the airport Enable other “Expanding CPH” projects Create safer work environment around the
bus-parking WBC2019+ Programme
Purpose of Pier E
47
Pier E Phase 1 Pier E Phase 1.1 Pier E Phase II
WBC2019+ Programme
Pier E phases
In operation Q2 2019
1 wb contact gate + 6 nb bus gates Border Control (BC) Building Support Building
In operation Q2 2019
2 wb bus gates* incl. a boarding bridge
*1 gate becomes contact gate with stand expansion 2020
In operation Q4 2020
4 wb gates: 1 wb contact + 3 wb bus gate
5 February, 2018
Finalised enabling works and projects:
Hangar 1 demolished
Services in ground
Temporary GO Connector
Stand Design (5 wb stands: 3 remote, 2 contact stands)
Current projects:
Pier E carcass and façade in progress
Support Building in progress
BC Building foundation to be intiated soon
Enabling works for Phase 2 initiated
Phase 2 design in progress
Border Control facilities Design in progress
WBC2019+ programme
Status
2Q16 Mar17 Dec 17
5 February, 2018
Front office:
Passport control booths Border Police (PRM, crew,
diplomats)
Staff lock (ID card holders) Customs process points
Back Office:
Police facilities in Support
Building
Customs back office
WBC2019+ programme
Border Control
Front-office, Police (Green areas: Customs Front- and Back office)
(preliminary, not final)
Back-office, Police
(preliminary, not final)
Welcome Minute from last meeting Valizo presentation, Off Airport Check-In and Baggage Handling SKAT authority gives an update on airlines reporting of API and PNR Information from CPH including updates on following issues:
Safety Security Update on the Baggage Factory West and the staff Canteen 2021-2022 Update on the new Pier E Update on the T3 Landside construction Misc.
55
Jonas Kjær-Westermann, CAP 17-01-2018
56 T3W (udførelsesfase/under construction) Metrobroen (udførelsesfase/under construction) Nyt folie – nye rækværk ved ankomstområdet/
Ændring af toldslusen – Færdigmeldt // Arrivals - finished Ombygning af DSB billetsalg – Færdigmeldt // DSB ticket area - finished
57
5 February, 2018 5 February, 2018
Byggeri afsluttes
Uge 4 Nyt granitgulv: Byggeriet er færdigt. Uge 6 Tilbygning, T3 West: Indvendige arbejder på gulvet færdigt.
Fortsat byggevægge på 1. sal
Uge 7 Gangbro fra metro til sikkerhedskontrol: Byggevæg opsættes. Uge 22-24 Gangbro fra metro til sikkerhedskontrol: Byggeriet er færdigt. Uge 26 Tilbygning, T3W: udvendige arbejder færdigt.
Byggeri afsluttes Byggeri afsluttes
59
60
61
62
63
64
T3W
65
T3W
66
Layout – stueplan T3W
TA AA AB AC AD A27 A26 A25 A24 A23 A22 A21 DISP. A: 50,80 m2 DISP. A: 110,18 m2 PAX FLOW A: 793,82 m2 Trapperum 5 T3-ST-(K1)074 Trapperum 1 T3-ST-027 59 61 60 58 57 56 55 54 53 A89 A82 A81 A78 A72 A68 A62 A57 052 053 054 055 056 057 058 059 060 061 SE SF SG SH DISP. A: 56,26 m2 (F&B) A: 175,72 m25 February, 2018 5 February, 2018
Byggeri afsluttes
Uge 4 Nyt granitgulv: Byggeriet er færdigt. Uge 6 Tilbygning, T3 West: Indvendige arbejder på gulvet færdigt.
Fortsat byggevægge på 1. sal
Uge 7 Gangbro fra metro til sikkerhedskontrol: Byggevæg opsættes. Uge 22-24 Gangbro fra metro til sikkerhedskontrol: Byggeriet er færdigt. Uge 26 Tilbygning, T3W: udvendige arbejder færdigt.
Byggeri afsluttes Byggeri afsluttes