6/12/2015 Treating Redevelopment: A Watershed Restoration Tool for - - PDF document

6 12 2015
SMART_READER_LITE
LIVE PREVIEW

6/12/2015 Treating Redevelopment: A Watershed Restoration Tool for - - PDF document

6/12/2015 Treating Redevelopment: A Watershed Restoration Tool for Local Governments South Carolina Association of Stormwater Managers Quarterly Meeting Mike MacIntyre, PE June 11, 2015 Key Terms Development Land-disturbing


slide-1
SLIDE 1

6/12/2015 1

South Carolina Association of Stormwater Managers Quarterly Meeting Mike MacIntyre, PE

June 11, 2015

Treating Redevelopment: A Watershed Restoration Tool for Local Governments Key Terms

  • Development

– Land-disturbing activity that creates impervious area or that otherwise decreases the infiltration of precipitation into the soil

  • Redevelopment

– Land-disturbing activity that does not result in a net increase in impervious area and that provides greater or equal stormwater control than the previous development

Building Addition

Development Example

Existing Building

slide-2
SLIDE 2

6/12/2015 2

New Building Existing Building

Redevelopment Example Key Terms

  • Detention

– Peak Control (flood relief)

  • The controlled release of the runoff from 10-, 25-,

and possibly larger 6-hour storms to prevent flooding

  • f downstream structures and properties

– Volume Control (stream erosion prevention)

  • The slower, controlled release of the runoff from a 1-

year, 24-hour storm in order to protect streambanks from being eroded

Requirements for Development

  • Meet each of the following requirements:

– Pollutant Removal

  • Remove pollutants from runoff through filtration,

settling or infiltration – Detention

  • Stream Erosion Protection and Flooding Relief for

Storm Drainage Systems, Streets, and Downstream Structures

  • Hold & slowly release runoff from medium and large

rainfall events – Stream Buffer Protection

  • Expands/complements previous efforts to preserve

buffers adjacent to streams – Natural Area Protection

  • 10% to 25% depending on density of the

development (treed area)

slide-3
SLIDE 3

6/12/2015 3

Requirements for the Transit Station Areas and the Distressed Business District (Yellow and Green Areas of the Map)

  • Choose one of the following requirements:

– Pollutant Removal

  • Remove pollutants from runoff through filtration,

settling or infiltration – Detention

  • Stream Erosion Protection and Flooding Relief for

Storm Drainage Systems and Streets

  • Hold & slowly release runoff from medium and large

rainfall events – Mitigation Fee

  • Pay the City a mitigation fee to install water quality

enhancement measures within the same watershed

  • And provide:

– Stream Buffer Protection – Peak Detention on Additional Impervious Area

Payment of Mitigation Fee – (Nov 2011-Jan 2015) in respect to Transit/Distressed Geography

8

Requirements for Redevelopment (in White Area of the Map)

  • Choose two of the following requirements:

– Pollutant Removal

  • Remove pollutants from runoff through filtration,

settling or infiltration – Detention

  • Stream Erosion Protection and Flooding Relief for

Storm Drainage Systems and Streets

  • Hold & slowly release runoff from medium and large

rainfall events – Mitigation Fee

  • Pay the City a mitigation fee to install water quality

enhancement measures within the same watershed (may be a larger fee if conditions are met)

  • And provide:

– Stream Buffer Protection – Peak Detention on Additional Impervious Area

slide-4
SLIDE 4

6/12/2015 4

Mitigation Fee

  • Set by City Engineer based on City’s cost to design and

construct stormwater control measures

  • Fee has not changed since inception (still many
  • pportunities for cost-effective projects)
  • As costs of projects increase and large, regional
  • pportunities diminish, fee may increase

10

Fee Structure

  • Lots less than 1 acre [18-161(a)]- $60,000/impervious acre
  • Within Transit Station Area/Distressed Business District

[18-161(b)]– $60,000/impervious acre

  • Redevelopment [18-161(c)]-$ 60,000/acre for the first

impervious acre, then $90,000/impervious acre for each additional acre

  • Mitigation fee is prorated for partial acres

11

Fee Structure

$0 $100,000 $200,000 $300,000 $400,000 $500,000 $600,000 1 2 3 4 5 6 7

Redevelopment Site Size, acres

For Example, a 2 acre redevelopment site outside the transit/distressed areas pays a $150,000 fee in lieu of onsite controls

slide-5
SLIDE 5

6/12/2015 5

Activity Centers

13

“70% of new multi-family and 75% of new office to be constructed in Activity Centers and Growth Corridors, with emphasis in Growth Corridors on Transit Station Areas.”

Mixed Used Activity Centers

14

Payment of Mitigation Fee – (Nov 2011-Jan 2015) in respect to other priority areas

15

slide-6
SLIDE 6

6/12/2015 6

Redevelopment Projects paying Fee by Year

  • How long have the mitigated projects been there?

Redevelopment Mitigation Payments Received By Fiscal Year 2012 – 4 projects, 3.49 acres 2013 – 1 project, 1.10 acres 2014 – 2 projects, 5.22 acres 2015 – 5 projects, 5.23 acres

16

Redevelopment Projects Approved Since November 2011

17 Chart includes 4 redevelopment projects that have not yet been completed/paid the fee

8 2 6

Provided Detention and Paid Fee Paid Fee for Redevelopment and Met Development Standards for Increase Paid Fee Only

50% 12% 38%

Stormwater Control Measures Approved Since November 2011

18

66 63 52 45 18 15 4 3 2 2 10 20 30 40 50 60 70

Above Ground Sand Filter Underground Detention Above Ground Detention Wet Pond Bioretention Underground Sand Filter Proprietary Device Wetland Infiltration Trench/Pond Permeable Pavement

slide-7
SLIDE 7

6/12/2015 7

Screening Process to Allow a Fee for Detention

19

Screening Process to Allow a Fee for Detention

  • Is there an increase of impervious area on the project site?
  • Are there open stormwater requests for erosion or flooding?
  • Where does the project drainage area become less than

10% of the total drainage area?

  • Are there other downstream concerns (e.g. – is there a

residential neighborhood that may be negatively impacted)?

  • Is the local infrastructure adequately sized?
  • What type of limitations are there on site?

20

Limitations of Redeveloping Sites

Redevelopment sites often face substantial challenges accommodating stormwater controls on-site

  • Difficult topography
  • Underground utility conflicts
  • Lack of available space onsite
  • Brownfield sites
  • Maintain site operations

21

slide-8
SLIDE 8

6/12/2015 8

Why is there a fee in the first place?

  • Existing paved sites typically have no form of runoff control
  • Paved surfaces causes runoff that impairs surface waters
  • Post Construction ordinance requires on-site measures
  • Redevelopment faces challenges accommodating runoff

controls on-site

  • Caps the compliance cost of affordable housing,

redevelopment projects, and increases economic development opportunities

22

Why is there a fee in the first place?

  • Increases flexibility, and predictability for redevelopment

projects

  • Reduces greenfield development by making redevelopment

more affordable

  • Accelerates watershed recovery by encouraging

redevelopment over green field development

  • The offsite, regional approach recovers watersheds at a

faster pace.

  • Offsite mitigation is an effective strategy in communities

nationwide to protect environment while considering costs

23

What Other Local Governments Use Mitigation Fees?

  • What other municipalities have a mitigation fee?

– Atlanta, GA – Austin, TX – Columbus, OH – Orlando, FL – Prince George County, MD – San Antonio, TX – San Francisco, CA – Tampa, FL – Washington, DC

24

slide-9
SLIDE 9

6/12/2015 9

Operation and Maintenance

  • Who maintains stormwater control measures?

– Private commercial projects: owner – Multi-family sites: owner – Single-family subdivisions: HOA may petition City to take over maintenance if the measure is in good order two years after it goes into service – Public projects: owner agency

25

Redevelopment Case Study Seven Eleven – N Wendover Rd

Pre-Project Conditions (2011)

27

slide-10
SLIDE 10

6/12/2015 10

Redevelopment Conditions (2015)

28

Aerial Comparison 2013 Aerial 2014 Aerial

29

Downstream Analysis

30

Open Channel Stormwater Pipe Pipe installed by project.

slide-11
SLIDE 11

6/12/2015 11

Downstream Analysis – 10% Point

31

Open Channel Stormwater Pipe

Site Constraints

32

  • Side/Rear Yards and

Setbacks required by Zoning Ordinance

  • Tree Save Areas required

by Tree Ordinance

  • Internal Tree planting

required by Tree Ordinance

  • Underground Stormwater

Control Measure (SCM) required by Post- Construction Stormwater Ordinance (PCSO)

Tree Save Area

Redeveloped Site Specifics

33

Pre-Project (acres) Redevelopment (acres) Tree Save 0.24 Additional Vegetated Area 0.60 0.07 Total Pervious Area 0.60 0.31 Impervious Area 0.47 0.76 Site Area 1.07 1.07

slide-12
SLIDE 12

6/12/2015 12

Stormwater Development Requirements

  • Provide onsite detention to reduce downstream

erosion and flooding impacts. This was accomplished by installing an underground detention system.

  • Pay mitigation fee for water quality impact at rate of

$60,000 per acre of Built Upon Area (BUA). This site paid $44,340.

34

Task Force Questions

  • Are current stormwater ordinances working to

stop degradation?

  • What are the impacts to the floodplain?

35

How The Current Ordinance Improves the Watershed Through Redevelopment

36

Redevelopment Requirements:

  • Detention is

provided to slowly release runoff to reduce stream erosion

  • Detention is

provided on-site to reduce downstream storm drainage system burden

  • Detention is

provided on-site to reduce downstream street flooding

0.5 1 1.5 2 2.5 3 3.5 4 4.5

Stream Erosion Flow Storm Drainage System Flow Street Flooding Flow

Stream Protection and Flood Reduction

Pre-Project Redevelopment

slide-13
SLIDE 13

6/12/2015 13

How The Current Ordinance Improves the Watershed Through Redevelopment

37 Undeveloped Pre-Project Redevelopment

Hydrograph for Stream Erosion Flow

How The Current Ordinance Improves the Watershed Through Redevelopment

38 Undeveloped Pre-Project Redevelopment

Hydrograph for Storm Drainage System Flow

Redevelopment Case Study Hendrick Autohaus