35 Ton Run 2 Hardware and Operational experiences Alan Hahn - - PowerPoint PPT Presentation

35 ton run 2 hardware and operational experiences
SMART_READER_LITE
LIVE PREVIEW

35 Ton Run 2 Hardware and Operational experiences Alan Hahn - - PowerPoint PPT Presentation

35 Ton Run 2 Hardware and Operational experiences Alan Hahn 4/14/16 Dune Friday Phone Meeting 1 Organization Overall Run Cryo Detector Hardware Categories TPC Including HV Cold Electronics Photon Detectors


slide-1
SLIDE 1

35 Ton Run 2 Hardware and Operational experiences

Alan Hahn

4/14/16 Dune Friday Phone Meeting 1

slide-2
SLIDE 2

Organization

  • Overall Run
  • Cryo
  • Detector “Hardware” Categories

– TPC

  • Including HV

– Cold Electronics – Photon Detectors – DAQ – Systems

4/14/16 Dune Friday Phone Meeting 2

slide-3
SLIDE 3

Run: 35T Cooldown and Filling

4/14/16 Dune Friday Phone Meeting LAPD Pump trip XFer from LAPD GAr xfer from LAPD (over weekend) ~1.5 tons Top-Off from TRAILER Membrane Temperature sensors 3

slide-4
SLIDE 4

Run: e- Lifetime

4/14/16 Dune Friday Phone Meeting

PrM2 & 3, both long PrMs midway heights in Cryostat(these lifetimes may drop a bit (~10%) using PrM0 as a constraint)

Sitewide Power Outage LN2 Cooling Loss Tubing Break Pump Start

4

3 ms

Bad News Period

slide-5
SLIDE 5

Run: Purity Stratification near start of Purification

4/14/16 Dune Friday Phone Meeting

PrM 1 (near Cryostat bottom) PrM 4 (near surface) O2 Gas Analyzer, ~(~80 cm from bottom)

5

slide-6
SLIDE 6

Geometry of 35 Ton Cryostat

(from E.Voirin recent 35 Ton FEA calculations Dune DocDb 1156)

4/14/16 6 Dune Friday Phone Meeting

4 purity monitors in this corner (Geometry Not in CFD model) PrM1 Pump intake Pump outflow

slide-7
SLIDE 7

Discussion of Results / Lessons Learned

Phase separator cools inlet flow to approach saturation temperature, which is below the “bulk temperature” of the argon. This cooler, more dense layer of argon tends to stay at the bottom, and not mix well with the rest of the argon. Back pressure control at the phase separator could allow us to flow in warmer argon, which would then mix well with the bulk.

4/14/16 7 Dune Friday Phone Meeting

Pump Suction Pump Discharge Pipe with Phase Separator on Top, LAr flows down, and impinges on cryostat floor.

New constraint

RTD measurements previous slide verifies this temperature stratification

slide-8
SLIDE 8

Run: Stratification Explanation PrM1&4 with 3 Precision RTDs

Opportunity provided by Power Outage

4/14/16 Dune Friday Phone Meeting 8

Pump is off PrM 1&4 show same lifetime 3 RTD offsets made to match Barometric Pressure Pump is on Uppermost RTD Lowest RTD PrM 1&4 lifetimes diverge

12 hrs after Outage

slide-9
SLIDE 9

Run: Beware the Ides of March

  • Three consecutive “events” ~one week apart and all on

weekends

1. Site-wide power outage stopped our recirculation and dropped the LAr Purity (3/4—Friday Night)

  • See the loss of purity due to outage on previous slides.

2. Loss of LN2 Cooling (broken valve) caused a loss of LAr (~1/2 ton through boil off) (3/12--Saturday)

  • Amount of loss because Autodialer Alarm had not been reset since the

previous week’s Power Outage—Doh!

– Only noticed on Sunday and fixed in afternoon

  • Dropped LAr level below desired HV-precaution level

3. Unrecoverable Contamination of LAr (3/17-Saturday 2 AM)

  • Small tube attached to GAr Bellows Pump that was being used to

transfer GAr between LAPD and 35Ton broke- pulling in air and injecting it into the LAr stream.

– Estimate it would take ~20 weeks of filtering/filter regeneration to remove just the O2, N2 would not be removed.

  • Went from 100 ppt to 30 ppm O2 in about 3/4 hr.

4/14/16 Dune Friday Phone Meeting 9

slide-10
SLIDE 10

4/14/16 Dune Friday Phone Meeting

This broken tubing is on the suction side of pump that was pulling GAr out

  • f LAPD, compressing it and injecting

it into the LAr coming from 35T just before the purification filters. This was how we were raising the LAr level in the Cryostat

10

Bellows Pump

slide-11
SLIDE 11

Cryo Issues

  • Pumping

– Had problems establishing the 35Ton Internal LAr Pumping – Pumps had been rebuilt after Phase 1, but had never been run in. – Finally putting 3 phase 208 AC on pump motor broke it free.

  • Then normal AC Drive worked fine.

– Lesson learned—nothing goes into cryostat without a functionality test

  • Even if it worked fine last time (e.g. Phase 1).
  • Need a better interface into Controls and Alarms

– Autodialer not working cost us LAr level when LN2 valve stopped functioning.

  • Did it help lead us a bit quicker into the Tubing break?? (Speculative)

– Painful to use the Cryo Interface at time – incredible slow downs.

  • Discourages one from looking at trends if it takes forever to get up and run.
  • Massive Contamination of LAr

– I believe there will be a review of exactly what happened and that will suggest several lessons to be learned from

  • How did we get into this situation in the first place?
  • Recognition of how fast you can completely contaminate a sizeable amount of LAr
  • How to identify other similar modes that might cause same problem.
  • Perhaps a way to quickly and automatically respond to an event since there is almost no

time for people to recognize what is going on.

4/14/16 Dune Friday Phone Meeting 11

slide-12
SLIDE 12

TPC

  • Detector Installation in Cryostat was a well planned and

effectively carried out enterprise

– Thanks Jack Fowler, Dan Wenman, Bo Yu, Lee Scott, Bob Kubinski – Demonstrates that careful planning actually works!

  • Field Cage, Cathode, HV

– 60 kV (@Cathode) in “clean” LAr

  • Wanted to get track measurements made at this lower field before

“risking” raising the HV higher and potentially breaking something.

  • Did see small spikes, and did have two apparent breakdowns (one while

ramping back up after first breakdown).

  • These breakdowns happened just ~12 hrs before the LAr

contamination

– Large disappointment with LAr contamination is that we weren’t able to test Cathode HV at 120 kV in pure LAr – However we did continue the tests in what we had

  • Held 120 kV for 1 week without breakdown
  • Held 135 kV for 1 day with breakdown.
  • A summary of the HV studies will be made.

– Most info is in elog

4/14/16 Dune Friday Phone Meeting 12

slide-13
SLIDE 13

HV History over Run

4/14/16 Dune Friday Phone Meeting 13

breakdowns 67kV 133kV 150kV 135kV 150kV

PowerOutage contamination Cooling Loss

These are Voltages at Power Supply , ~10% higher than at cathode.

slide-14
SLIDE 14

Cold Electronics

  • As is well known, the FEMBs + the APAs have been

plagued by relatively high noise levels

– These swamp the original specs that were based on thermal noise figures, as measured with capacitive loads – Clearly see noise influences that correlate to the individual wire planes

4/14/16 Dune Friday Phone Meeting 14

slide-15
SLIDE 15

4/14/16 Dune Friday Phone Meeting 15

Recent data from Cold Run17366 3/16)

Test done by Bo Y. and Matt W. at BNL with 3 Bd

  • APA. DocDB 9439, 7/2014

Data from 4 Bd taken at DAB (7/15)

slide-16
SLIDE 16
  • Our “low noise” state includes this correlated

noise.

  • In addition, we are occasionally/often

triggered into an extremely high noise state that makes it impossible to use the data for anything.

  • Much work is being done now by Marvin

Johnson, Brian Kirby, Linda Bagby, Steve Chappa… in trying to characterize this noise

– Hope that understanding can be fed into the electronics/APA design/??? for ProtoDune

4/14/16 Dune Friday Phone Meeting 16

Noise (Continued)

slide-17
SLIDE 17

Online Event Display -Collection Plane Top view of APA

4/14/16 Dune Friday Phone Meeting 17

“Normal” Noise State Very High Noise State APA Long drift Short drift

slide-18
SLIDE 18

Photon Detectors

  • Detectors

– One Detector left unplugged during cabling

  • Observed Low noise level for those channels wasn’t

recognized as the serious problem it was.

– PD Signals seem to be impacted by noise—not positive if this is noise being generated by the APAs

  • SSPs

– After fixing an issue with the NOvA timing chain (back at DAB), these have been reliable – We have had very good response from ANL when we have had any problems

  • Calibration Module

– Working fine, able to calibrate the PDs

4/14/16 Dune Friday Phone Meeting 18

slide-19
SLIDE 19

DAQ

  • Flange Board

– All signals/electrical services to APA/PD pass through this Board. – Had serious issues with initial version – Second version much better

  • Issue with Bias lines—leakage currents quite high, and very non-linear with

voltage

  • Eventually we bypassed the FB and went directly to SHV bulkhead connectors on
  • wn flanges.
  • PennTrigger Board

– Slow start, but eventually it wsa providing our triggers

  • Cosmic Ray Counters

– Allowed us to trigger on tracks that are useful for looking at the APA features.

  • Fiber Links

– Very problematic at DAB and early at PC4. Often had to “reseat” the

  • ptical transceivers, or reset the links.

– Settled down at some point and were less of a problem for rest of run.

  • RCE systems

– Once things calmed down, they appear to be working fine.

  • Spares were an issue, since a failure would take down ½ the TPC APAs

4/14/16 Dune Friday Phone Meeting 19

slide-20
SLIDE 20

DAQ (continued)

  • NEMA 12 Rack

– Turned out to be one of the highest risk items for the 35 T run (until Tubing at least). – Contains DAQ Servers, RCE Systems, Network Switches in a closed Air Condition Rack – The power for the Air Conditioning was put on an interlock that was tied into the Rack Smoke Detection Module and was not plugged into the rack power. Also an internal power switch for Air Conditioning could be switched off. – Three“near miss” incidents

  • Two were early in the DAQ installation at PC4 where the air conditioner could or actually was

disabled, with the rack doors closed. However these were caught before anything happened.

  • 3rd event was much more advanced when it was caught—rack temperatures were

in > 60C range as reported by Network switch in rack

  • Fortunately M. Convery came by PC4 from ROC-W (@7PM because he noticed the RCE

readout wasn’t working at ROC-W. He opened the doors, things cooled off. – After this last episode, we established

  • a management control signage to be used whenever rack was opened to be worked on.
  • Added an external light that was lit as long as power was available to the AC.
  • Recently a 50C klixon (thermal switch) was added that will drop rack power in case the Air

Conditioning fails. – Recommendation that one needs to do a careful risk analysis on a system like this.

  • Operation

– For better or worse, the DAQ servers were not setup as Fermi Standard, so we had several cases where we were halted because the experts were not available to get the systems running. – DAQ Running.

  • Due to event size we were typically limited to event rates ~1 Hz
  • Reliability had vastly improved near the end of the run.

4/14/16 Dune Friday Phone Meeting 20

slide-21
SLIDE 21

Systems—or how things play together

  • Grounding

– The 35 T cryostat was never designed with grounding in mind. – There is no way that the internal membrane could be kept isolated from contact with the concrete structure that encased the Cryostat.

  • Reason was that a carbon steel vapor barrier was bolted to the

concrete, and that was then welded to the A&B plates (which were welded to the stainless steel membrane).

  • Due to this inherent connection, it was never obvious to those in PC4

as to what the impedance between detector and building grounds should be, since the concrete impedance was sensitive to moisture, and that varied a lot from the installation to the running period.

– Then when we went to 35T installation, our grounding crew disappeared to uBoone. – Rest of us didn’t really know what to do but to turn down the “honking horn” on the ground fault device, since it could change on/off with nothing being done.

4/14/16 Dune Friday Phone Meeting 21

slide-22
SLIDE 22

4/14/16 Dune Friday Phone Meeting 22

Carbon Steel Vapor barrier Inside the Concrete Shell—note the iron

slide-23
SLIDE 23

Systems—or how things play together

  • System Integration

– Desperately need a real low noise Test Bed setup with a reasonable APA ---before one has committed to a final FEMB design.

  • These things can’t be thought of only in isolation, they impact

each other

  • Need Low noise Setup so one can beat the noise down knowing

it should be lower, rather than blaming external factors as causing the noise.

  • Need engineers during this period of time to see how their

equipment is working (or not).

– Installation is too late to be doing this debugging.

  • It is important that Groups that are producing parts

actually participate in the debugging, installation, and running of their products.

– We had too many MIA groups for the 35 T.

4/14/16 Dune Friday Phone Meeting 23

slide-24
SLIDE 24

Xtra slides

4/14/16 Dune Friday Phone Meeting 24

slide-25
SLIDE 25

Loss of N2 Cooling 3/12/16

4/14/16 Dune Friday Phone Meeting

LAr Level Drop ~ 3.8 cm ~1/2 ton RTD on tip of Corrugation Cryostat Pressure RTD on flat of top Membrane.

25

slide-26
SLIDE 26

LAr Level Concern

4/14/16 Dune Friday Phone Meeting 26

“Corrugations” Cathode (up to 135 kV) APA’s

slide-27
SLIDE 27

Tubing Break--3/19

4/14/16 Dune Friday Phone Meeting 27