WERF INFR4R12 Electro Scan Lateral Testing Project Kick-Off - - PowerPoint PPT Presentation
WERF INFR4R12 Electro Scan Lateral Testing Project Kick-Off - - PowerPoint PPT Presentation
WERF INFR4R12 Electro Scan Lateral Testing Project Kick-Off Conference Call Friday, June 29, 2012 Presentation Topics Project Team Project Overview and Research Objectives Schedule Efforts to Date Next Steps Project Team
Presentation Topics
- Project Team
- Project Overview and Research
Objectives
- Schedule
- Efforts to Date
- Next Steps
Project Team
Project Overview and Research Objectives
- Research Objectives
– Compare Electro Scan results to actual infiltration estimates for laterals during rainfall simulation – Compare Electro Scan results to air pressure test results – Compare Electro Scan results to television inspection results
- Project Overview
– Areas – Tasks
Project Areas
65th Street
- Previously rainfall simulation
with “soaker hose” and dye water tested
- Rehabilitate 75 laterals
- Laterals to be lined in phased
approach (priority 1, priority 2)
- Planned for rainfall simulation
with “soaker hose” and dye water testing between phases; flow measurements taken during tests
- Flow metering at downstream
end of project
- Clean outs installed external to
house at most locations
Eagle Street
- Previously rainfall simulation with “soaker hose” and dye water tested
- Rehabilitate 42 laterals
- Laterals to be lined in phased approach (all to property line, priority 1,
priority 2)
- Planned for rainfall simulation with “soaker hose” and dye water testing
between phases; flow measurements taken during tests
- Clean outs installed external to house at most locations
Eagle Street
Project Tasks
- Task 1: Coordinate with City Rehabilitation
Pilot Project
- Task 2: Perform Electro Scan Lateral Tests
- Task 3: Perform Low Pressure Air Lateral Tests*
- Task 4: Data Analysis
- Task 5: Prepare Final Deliverable
Electro Scanning Approach
Schedule
- Commence pilot project design: Feb. 8, 2012
- Hold public meeting for property owners in pilot area: Feb. 23, 2012
- Advertise bid to install lateral clean outs: April 19, 2012
- Bid opening: May 3, 2012
- Issue City Contractor Notice to Proceed: May 29, 2012 Actual was June 8
- Perform dye water/rainfall simulation tests: June 18 to June 29, 2012
- Install clean outs and clean and inspect laterals: June 18 to July 27, 2012
- Perform Electro Scan Tests and Air Pressure Tests: June 25 to Aug. 3, 2012
- Develop Comparative Analysis of Lateral Testing Methods: Aug. 6 to Sept. 28,
2012
- Quarterly Report # 1: Sept. 3, 2012
- Develop Report: Sept. 3 to Dec. 7, 2012
- Submit draft final report: Dec. 7, 2012
- Response to draft report comments: Dec. 21, 2012
- Quarterly Report #2: Jan. 1, 2013
- Submit final report: Jan. 18, 2013
Efforts to Date
- Lateral Inspections
- Metering and Weir Flow Device
- Rainfall Simulation
- Clean Out Installations and Lateral Cleaning
- Electro Scan Training and Field Tests
– Low Pressure Air Test Evaluation – Water Exfiltration Testing – Revisions to Field Test SOPs
Lateral Inspections
Flow Metering
Rainfall Simulation
Dye Water Test
Stormwater Pipe Crosses over Sanitary Lateral
Private Property Public Storm water Sanitary sewer main Foundation drain Downspout connection to foundation drain Downspout to ground Yard slope to street Yard slope to house Catch basin curb Street sidewalk basement Lateral Sanitary sewer manhole
Rainfall Simulation
Clean Out Installation
Contractor
- Locate lateral
- Install cleanout
- Televise and clean lateral
- Issue inspection report
- Notifies BC/OTIE lateral is prepped for scan
- Provide scheduled date for lining lateral
BC/OTIE
- Review inspection report
- Confirm lateral material
- Plan daily work
- Populate inspection form
- Perform probe calibration check with
field data recording device Contractor
- Review daily work
plan
BC/OTIE
- Arrive at site, review CO conditions
- Address site issues, open CO cap
and assess lateral conditions for testing
- Confirm resident is aware of test or
not home
- Confirm water source from City
water truck
- Assess need to use Sea Snake
camera to evaluate lateral and plug conditions
- Insert US plug into lateral and
inflate to 25 psi
- Push DS plug into main
- Inflate DS plug to 15 psi and pull
back to connection
- Deflate plug and pull back 2 feet
toward CO
- Inflate DS plug to 25 psi and leave
pump connected
Prep Work Phase
Testing Downstream Pipe
BC/OTIE
- Insert probe through cleanout to lateral invert
- Connect field computer to probe
- Set zero on field computer
- Push probe into lateral toward downstream
plug
- Press RECORD on field computer
- Start scan by pulling probe toward clean out
with reel
- Maintain recommended scan speed for probe
- Stop scan when probe reaches CO
- Remove probe
- Set GPS coordinates for US (SC for sidewalk
CO and PC for CO near house) and DS (ST) ends
- f lateral in field computer
- Confirm all site data is entered in field
computer form, including special notes
- Review scan graph
- Save scan by pressing Save Customer Info
button BC/OTIE
- Hold air line and release
pressure in DS plug to empty water from lateral
- Hold air line and release
pressure in US plug
- Remove DS plug from
lateral
- Remove US plug from
lateral
- Contact property owner
to inform them test is complete and ask to confirm basement conditions
REVISED 6/28/12 Process for Gathering Lateral Inspection Data
BC/OTIE
- Fill lateral with water to level
above pipe crown at CO, adding salt at same time
- Set ground stake within 100
feet of lateral and confirm signal strength (10%)
- Determine if exfiltration test
is feasible based on rate of water loss at CO
- Stop water and perform
exfiltration test for 1 foot drop and record time on data sheet
- Start water at rate that holds
desired level in CO
Testing Upstream Pipe
BC/OTIE
- Insert SeaSnake into
upstream lateral to confirm any special conditions and remove camera
- Estimate distance to deploy
ElectroScan plug upstream to within 5 feet of house
- Insert DS plug into lateral and
inflate to 25 psi
- Push US plug into lateral to
desired distance
- Inflate US plug to 25 psi and
leave pump connected
- Insert SeaSnake camera into
lateral up to US plug to monitor water level and air BC/OTIE
- Insert probe through cleanout to lateral invert
- Connect field computer to probe
- Set zero on field computer
- Push probe into lateral toward US plug
- Press RECORD on field computer
- Start scan by pulling probe toward clean out with
reel
- Maintain recommended scan speed for probe
- Stop scan when probe reaches CO
- Remove probe
- Set GPS coordinates for US (HC for location near
house) and DS (SC for Street CO) ends of lateral in field computer
- Confirm all site data is entered in field computer
form, including special notes
- Review scan graph
- Save scan by pressing Save Customer Info button
BC/OTIE
- Hold air line and
release pressure in DS plug to empty water from lateral
- Hold air line and
release pressure in US plug
- Remove DS plug from
lateral
- Remove US plug from
lateral
- Contact property
- wner to inform them
test is complete and ask to confirm basement conditions BC/OTIE
- Fill lateral with water to level
above pipe crown at CO, adding salt at same time
- Set ground stake within 100
feet of lateral and confirm signal strength (10%)
- Determine if exfiltration test is
feasible based on rate of water loss at CO
- Stop water and perform
exfiltration test for 1 foot drop and record time on data sheet
- Start water at rate that holds
desired level in CO
- Remove SeaSnake camera
Electro Scan Testing – Set-Up
Electro Scan Testing – Scanning
Electro Scan Testing - Scanning
Electro Scan - Processing
Clean Out
Observations Through First 2 Days of Testing
- Low Pressure Air Test Replaced By
Water Exfiltration Test
- Deep Clean Outs
- Clean Outs with Poor Access
- Fresh Water Ion Availability
Contractor
- Locate lateral
- Install cleanout
- Televise and clean lateral
- Issue inspection report
- Provide scheduled date
for lining lateral BC/OTIE Does Inspection Report indicate any of the following?
- Roots
- Cracks
- Missing pipe
- Displaced joints
Contractor
- Recommend date and
time for lateral air pressure test to minimize impact to work schedule
DRAFT Process for Determining Ability to Air Test Lateral – Prior to Field Tests
BC/OTIE Recommend NO AIR TEST and document in record for lateral
YES NO
BC/OTIE Inform Contractor that Air Test will be attempted on
- lateral. Request
contractor assistance with inserting test bladder in main to isolate lateral connection
Conclusion from Field Test: Replace low pressure air test with water exfiltration test
Advantages of Water Exfiltration Test
- ver Low Pressure Air Test
- Electro Scan set up includes plugging lateral
test section and filling with water already
- Exfiltration test provides better comparison to
infiltration estimates made during rainfall simulation (gpm rather than pass/fail air test)
- Observed CCTV defects suggest these 80 year
- ld vitrified clay laterals would NOT have
passed air test
Next Steps
- Continue Electro Scan and Water Exfiltration