WEKIVA PARKWAY A Regional Transportation Solution Kiwanis Club of Mount Dora September 13, 2012 WEKIVA PARKWAY A Regional Transportation Solution Completing The Beltway Around Northwest Metropolitan Orlando Improves Travel between


slide-1
SLIDE 1

WEKIVA PARKWAY…

A Regional Transportation Solution

Kiwanis Club of Mount Dora

September 13, 2012

slide-2
SLIDE 2
  • Completing The Beltway Around Northwest Metropolitan Orlando
  • Improves Travel between Orange, Seminole And Lake Counties
  • Improves Safety: Reduces Vehicle Crash Fatalities & Vehicle vs.

Wildlife Conflicts

  • Minimizes Impacts To The Wekiva Basin Area
  • Improves Wildlife Habitat Connectivity

WEKIVA PARKWAY… A Regional Transportation Solution

slide-3
SLIDE 3
  • Authorized in 2004 by the Wekiva Parkway and

Protection Act (Chapter 369, Part III, F.S.)

  • Constructs 25 Miles of New Toll Expressway
  • Total Estimated Cost: $1.7 Billion

– Includes $500 million of non–toll road improvements

  • Provides Connectivity to SR 417 and I-4

PROJECT DESCRIPTION

slide-4
SLIDE 4

WEKIVA PARKWAY

slide-5
SLIDE 5
  • 30+ Years in the Making
  • PD&E Study: More than 400 Meetings Held
  • Setting Aside More than 3,400 Acres for Conservation
  • Largely Elevated to Reduce Accidents Between Vehicles

& Wildlife

  • Numerous Wildlife Bridges

PROJECT HIGHLIGHTS

slide-6
SLIDE 6

WEKIVA PARKWAY

< x > Number of Lanes Both Directions Expressway Arterial

9.4 Miles Orange County Lake County

Seminole County

slide-7
SLIDE 7

FUNDING PARTNERS

slide-8
SLIDE 8

For Each Agency’s Respective Sections They Will:

  • Perform Final Design
  • Construct
  • Finance
  • Operate
  • Maintain
  • Collect Tolls
  • Keep All Toll Revenue

OOCEA/FDOT AGREEMENT

slide-9
SLIDE 9

Project Construction Sections

9

slide-10
SLIDE 10

Project Status

  • Final Design

– OOCEA Sections 1A, 1B & 2B began this summer – OOCEA Section 2A firm selected; Section 2C selection pending – * FDOT Section 3B to begin Oct.-Nov. – * FDOT Section 3A design ad Oct. – FDOT Section 4A & *4B Design-Build selection Oct. – * FDOT Section 5 under procurement – * FDOT Section 6 under procurement – FDOT Section 7A design ad Dec.

* Lake County Sections

10

slide-11
SLIDE 11

Project Status

  • Construction

– Construction anticipated Late 2012-2013 Sections 4A & 4B – *Wekiva Parkway Complete 2021

  • Schedules Highly Subject to Change

4A & 4B 1A & 1B 2A, 2B, 2C 3A & 3B 5 & 6 7A 7B 8 Design Section

2012 2013 2014 2015 2021 2016 2017 2018 2019 2020

11

slide-12
SLIDE 12

US 441/SR 46 INTERCHANGE EVALUATION

12

slide-13
SLIDE 13

US 441/SR 46 Interchange Studies

Evaluated two alternative design concepts

  • 3-Level Interchange

– US 441 depressed under SR 46 – Diamond interchange with flyover ramp

  • 2-Level Interchange

– US 441 at-grade signalized intersection at SR 46 – Flyover ramp

13

slide-14
SLIDE 14

Construction

  • Construction anticipated Fall 2012 in portion
  • f Orange and Lake County (4A & 4B)
  • Wekiva Parkway Complete Fall 2021
  • Revenue can be started by Jan 2015 (initial
  • perating section)

3-LEVEL INTERCHANGE

US 441 DEPRESSED UNDER SR 46 DIAMOND INTERCHANGE WITH FLYOVER RAMP

14

Plan View Profile View

slide-15
SLIDE 15

Construction

  • Construction anticipated Fall 2012 in portion
  • f Orange and Lake County (4A & 4B)
  • Wekiva Parkway Complete Fall 2021
  • Revenue can be started by Jan 2015 (initial
  • perating section)

15

3-LEVEL INTERCHANGE

US 441 DEPRESSED UNDER SR 46 DIAMOND INTERCHANGE WITH FLYOVER RAMP +6’ 0’

  • 17’
  • 7’

+10’

Elevation Difference Between Ramp and Ground at R/W in Feet: +10 Indicates Ramp is 10’ Higher than Ground

  • 17 Indicates Ramp is 17’ Lower than Ground
slide-16
SLIDE 16

Construction

  • Construction anticipated Fall 2012 in portion
  • f Orange and Lake County (4A & 4B)
  • Wekiva Parkway Complete Fall 2021
  • Revenue can be started by Jan 2015 (initial
  • perating section)

16

3-LEVEL INTERCHANGE

US 441 DEPRESSED UNDER SR 46 DIAMOND INTERCHANGE WITH FLYOVER RAMP

slide-17
SLIDE 17

2-LEVEL INTERCHANGE

US 441 AT-GRADE SIGNALIZED INTERSECTION AT SR 46 FLYOVER RAMP

17

Plan View Profile View

slide-18
SLIDE 18

18

2-LEVEL INTERCHANGE

US 441 AT-GRADE SIGNALIZED INTERSECTION AT SR 46 FLYOVER RAMP +1’

  • 25’
  • 15’
  • 7’

Elevation Difference Between Ramp and Ground at R/W in Feet: +5 Indicates Ramp is 5’ Higher than Ground

  • 25 Indicates Ramp is 25’ Lower than Ground

+5’

slide-19
SLIDE 19

19

2-LEVEL INTERCHANGE

US 441 AT-GRADE SIGNALIZED INTERSECTION AT SR 46 FLYOVER RAMP

slide-20
SLIDE 20

Entire corridor was analyzed

Traffic Study Area

20

slide-21
SLIDE 21

8% 73% 19% 47% 36% 17% 66% 23% 11%

SR 46 US 441

7% 69% 24% Existing Traffic

21

US 441/SR 46 Interchange

Existing Traffic Turning Movements

slide-22
SLIDE 22

Existing Traffic

22

US 441/SR 46 Interchange

2032 Traffic Turning Movements

SR 46 US 441

13% 63% 24% 2% 40% 58% 82% 10% 8% 20% 72% 8% Proposed Traffic

slide-23
SLIDE 23

Recommendation

The 2-Level Interchange is recommended:

– Meets the future traffic needs of the community – Significantly reduces property owner impacts – Reduces utility impacts and relocations – Best use of taxpayer dollars (cost savings of

  • ver $25M)

– Reduces traffic impacts during construction – Shortens construction time – Lowers height of flyover ramp

23

slide-24
SLIDE 24

Visual Rendering 2-Level Interchange Along SR 46 Looking East

Construction

  • Construction anticipated Fall 2012 in portion
  • f Orange and Lake County (4A & 4B)
  • Wekiva Parkway Complete Fall 2021
  • Revenue can be started by Jan 2015 (initial
  • perating section)

24

slide-25
SLIDE 25

Visual Rendering 2-Level Interchange Along SR 46 West

Construction

  • Construction anticipated Fall 2012 in portion
  • f Orange and Lake County (4A & 4B)
  • Wekiva Parkway Complete Fall 2021
  • Revenue can be started by Jan 2015 (initial
  • perating section)

25

slide-26
SLIDE 26

Visual Rendering 2-Level Interchange Along US 441 Looking South

Construction

  • Construction anticipated Fall 2012 in portion
  • f Orange and Lake County (4A & 4B)
  • Wekiva Parkway Complete Fall 2021
  • Revenue can be started by Jan 2015 (initial
  • perating section)

26

slide-27
SLIDE 27

Next Steps

  • Final Design Begins
  • Continued evaluation & community

coordination on interchange concepts

  • Opportunities for Community Input
  • First Public Meeting: Spring – Summer 2013
  • Community Presentations
  • Updates & Comments via Website:

www.wekivaparkway.com

27

slide-28
SLIDE 28

PUBLIC INFORMATION CONTACT: MARY BROOKS C: 407-694-5505 E: INFO@WEKIVAPARKWAY.COM W: WWW.WEKIVAPARKWAY.COM

28